How do you know which version of a Proprietary Guardrail End Treatment KY is Using? PowerPoint Presentation
Download Presentation
How do you know which version of a Proprietary Guardrail End Treatment KY is Using?

Loading in 2 Seconds...

play fullscreen
1 / 78

How do you know which version of a Proprietary Guardrail End Treatment KY is Using? - PowerPoint PPT Presentation


  • 94 Views
  • Uploaded on

Session 4 KY Type 1 End Treatment ET-PLUS Slide 6 by Trinity Highway Products SKT-SP Slide 63 by Road Systems. How do you know which version of a Proprietary Guardrail End Treatment KY is Using?. Go to the KYTC Div of Design Home Page http://transportation.ky.gov/Highway-Design

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about 'How do you know which version of a Proprietary Guardrail End Treatment KY is Using?' - tiva


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
slide1

Session 4KY Type 1 End TreatmentET-PLUS Slide 6 by Trinity Highway ProductsSKT-SP Slide 63 by Road Systems

how do you know which version of a proprietary guardrail end treatment ky is using
How do you know which version of a Proprietary Guardrail End Treatment KY is Using?
  • Go to the KYTC Div of Design Home Page

http://transportation.ky.gov/Highway-Design

  • On the lower right click on Standard Drawing
  • Brings up:
    • Standard Drawings
    • Active Sepia List
    • Approved Shop Drawings - Click
      • The drawings show the version PLUS, SP, 27 etc.
      • Basic Info – very useful
the et plus ky uses is 50 7 syt post 1 hba post
The ET-Plus KY Uses is50’, 7 SYT Post & 1 HBA Post

The Title Block Details which ET-Plus Model KY is using

installation instructions for proprietary guard rail end terminals
Installation Instructions for Proprietary Guard Rail End Terminals
  • This Std Draw Note appears on each Proprietary End Treatment used in KY - “The Manufacturer SHALL furnish two (2) sets of shop plans to the contractor with each installation”
  • Each Proprietary End Treatment “see shop drawings”
  • Added to Sect 719.03 of 2012 Std Specs: “Proprietary end treatments SHALL be installed according to the manufacturer’s assembly or installation instructions”
  • SHOULD NOT LET THE CONTRACTOR BEGIN INSTALLATION BEFORE SUPPLYING YOU WITH THESE SHOP PLANS & INSTALLATION INSTRUCTIONS – Both you and the contractor need these documents to properly do your jobs of installing and inspection propriety guardrail end terminals
type 1 trinity et plus http www highwayguardrail com products etplus html
Type 1 Trinity – ET-Plushttp://www.highwayguardrail.com/products/etplus.html
type 1 et plus standard drawing note
Type 1 ET-PlusStandard Drawing Note
  • “The Manufacture Shall Furnish Two (2) Sets of Shop Plans to the Contractor with Each Installation”
  • For the ET-Plus this is on line at
  • http://www.highwayguardrail.com/products/pdfs/ETPlus-Manual.pdf Call 1-800-527-7976 if you do NOT Understand Manual
  • This Manual is cumbersome and somewhat hard to follow
http www highwayguardrail com products pdfs etplus manual pdf
http://www.highwayguardrail.com/products/pdfs/ETPlus-Manual.pdfhttp://www.highwayguardrail.com/products/pdfs/ETPlus-Manual.pdf
et plus http www highwayguardrail com products etplus html
ET-Plushttp://www.highwayguardrail.com/products/etplus.html
  • Energy Absorbing End Treatment
  • 50 feet long
  • Post 1 - HBA Post (Hinged Break-Away)
  • Post 2-8 7 SYT Post (Steel Yielding Terminal)
  • Has a Strut between Post 1&2
  • No Tube or Soil Plates
  • Standard Guardrail begins at Post 9
et plus http www highwayguardrail com products etplus html1
ET-Plushttp://www.highwayguardrail.com/products/etplus.html
  • Do Not attach Guardrail to Post 1
  • Under no circumstances shall the guardrail within the ET-Plus Pay Limit be Curved – see Installation Instructions
et plus installing hba post bottom post 1
ET-Plus Installing HBA Post-Bottom Post 1

Install the Bottom of the HBA Post such that the large hole 13/16” is placed downstream (away from the Impact Head)

et plus installing hba post top post 1
ET-Plus Installing HBA Post-Top Post 1
  • Align the Holes of the Post Plates (either side of Ears) on the Top and Bottom Post
  • Insert a 3/8” x 2” Hex Head Bolt through the 7/16” hole in the Post Plates (Ears) with washer and lockwasher under the 3/8” Nut (one bolt assembly on each side of Post)
  • Note 3/8” Bolts can be installed with nuts inside or outside of Post Plates
et plus installing hba post top post 11
ET-Plus Installing HBA Post-Top Post 1
  • On the side opposite the Strut - Insert a ¾” x 2 ½ ” Hex Head Bolt through the 13/16” hole in the Post Plates with washer and lockwasher under the ¾” Nut
  • Note ¾ ” Bolts can be installed with nuts inside or outside of Post Plates
  • DO NOT install the ¾” Bolt on the Strut Side until installing the Strut
et plus post 2 8 syt post
ET-PlusPost 2 – 8 SYT Post
  • If properly Graded, drive all the 6’ SYT Post to the optimum depth where centers of the 4 Yielding Holes through the Flanges are at the Ground Line
  • Note: Post 2 does NOT have an offset block
  • Note: Post 3-8 receive 8” offset blocks
drive syt post at post 2 8 careful syt post and sp std post look very similar do not intermix
Drive SYT Post at Post 2-8. Careful SYT Post and SP (Std Post) look very similar – DO NOT INTERMIX

SYT Post have

4 holes near

Ground Line

DO NOT

INTERMIX

SYT Post and

SP Post

et plus installing the strut post 1
ET-PlusInstalling the Strut Post 1
  • Place Angle Strut on the Flange of the HBA Post 1 with ¾” Hex Head Bolt placed through the top and bottom Post Plates and connect with a ¾” Washer and Lockwasher under the ¾” Nut.
  • Note: Strut can be placed with one of the leg flat or leg edge on the ground
  • Note: Strut can be installed on traffic side or field side of the Post
et plus installing the strut post 2
ET-PlusInstalling the Strut Post 2
  • Place 2 – 7/16” Hex head Bolts with Washer into the two Slotted Holes of the Strut
  • Place a Lockwasher and Nut on the ends of each of the Inserted Bolts
  • Tighten Nuts to snug position
et plus installing the strut post 21
ET-PlusInstalling the Strut Post 2

Washers are

Important

Incorrect - Loose Fit

Without Washer & Lockwasher

Correct

Tight Fit With Washer

et plus install offset blocks rail panels post 3 8
ET-PlusInstall Offset Blocks & Rail PanelsPost 3 - 8
  • 25’ or 12’6” Rail Panels are acceptable
  • Splice the rail Panels with 8 - 5/8” x 1 ¼” HGR Splice Bolts and Nuts
  • Do NOT connect Rail Panel @ Post 1
  • NO Offset Blocks @ Post 1 or 2
  • Post 3-8 Insert 5/8” x 10” HGR Bolt thru Rail Panel, 8” Offset Block and SYT Post
  • Connect with 5/8” Round Washer and HGR Nut
et plus installing rail panel to post 2
ET-Plus Installing Rail Panel to Post 2
  • NO Offset Block @ post 2
  • Insert 5/8” x 1 ¼” HGR Bolt through the Rail Panel and SYT Post @ Post 2
  • Connect with 5/8” Round Washer and HGR Nut
et plus installing the cable anchor assembly
ET-PlusInstalling the Cable Anchor Assembly
  • Secure Cable Anchor Assembly to the Rail by Inserting the Square Protruding Hooks/Lugs into Square Holes in Rail Panel toward Post 1. Secure by pulling the Bracket toward the Impact head insuring the Hooks/Lugs are well Seated into the Square Holes.
et plus installing the cable anchor assembly1
ET-PlusInstalling the Cable Anchor Assembly
  • Slide one end of Cable into the Cable Anchor Bracket and the other end into Post 1
  • Place a 1” Washer and Hex Nut on the Bracket End near Post 2 and tighten until at least 2 Threads are showing
  • Place Bearing Plate on Impact Side of Post 1 where Cable extends through Post 1
  • Bearing Plate must have Long Dimension (5”) Up
et plus installing the cable anchor assembly2
ET-PlusInstalling the Cable Anchor Assembly
  • Place 1” Washer and Hex Nut on the end of the Cable extending through Post 1
  • Restrain the Cable with locking pliers at the end of the Cable being tightened
  • Tighten the Hex Nuts on the Cable Ends until TAUT – it is considered TAUT when Cable does not deflect more than 1” when pressure is applied
slide45

Tighten Anchor

Cable – Using

Vice Grips on Shank not on the Cable

et plus installing the cable anchor assembly3
ET-PlusInstalling the Cable Anchor Assembly
  • Shank portion of Anchor Cable MUST BE positioned so it bears on the bottom edge of the web of the HBA Post (Post 1)
  • Shank portion of Cable must also be centered Horizontally so the Bearing Plate bears uniformly on both Fingers of Post 1
et plus installing the extruder head
ET-PlusInstalling the Extruder Head
  • Rail feeds out the Extruder Head away from traffic – Arm points away from traffic
  • Push the Extruder Head as far as it will go on the Rail panel, making sure the Rail is in the Channel Chute
  • Place the Extruder head against the HBA Post (Post 1) parallel to the ground
et plus installing the extruder head1
ET-PlusInstalling the Extruder Head
  • Top and Bottom Flanges on the side of the Extruder Head each has 3 holes – use the hole that best aligns with the holes in top and bottom of the HBA Post & Extruder Head parallel to the rail panels
  • Place a 3/8” washer on a 3/8” x 1 ½” Hex Head Bolt – Insert Bolt through Flange of Extruder Head and Flange of HBA Post
  • Place 3/8” Fender Washer Under 3/8” Nut on the end of the inserted Bolt
  • Tighten until snug
et plus installing the extruder head2
ET-PlusInstalling the Extruder Head

3 Holes in Extruder Head Flanges

slide62

NO CURVES

Energy Absorbing End Treatments

STRAIGHT FLARE / NOT CURVED

from the et plus installation checklist
From the ET-PlusInstallation Checklist
  • Extruder Head is pushed on as far as it will go on the rail panel ensuring the panels fully engage with the feeder chute
  • The Extruder Channel is approximately parallel to finished grade
  • Cable Anchor Bracket is locked into place, by pulling the bracket toward Post 1 making sure the Hooks/Lugs are well seated into the Square Holes
from the et plus installation checklist1
From the ET-PlusInstallation Checklist
  • Shank portion of Cable Anchor positioned against bottom web of top portion HBA Post 1
  • Hex Nuts on ends of Anchor Cable are tightened taut (Cable deflects less than 1”)
  • Cable Bearing Plate Oriented such that 5” dimension is up
skt sp road systems http roadsystems com pdf fleat sp installation manual pdf
SKT-SP Road Systems http://roadsystems.com/pdf/fleat/SP-Installation-Manual.pdf

SKT-SP & FLEAT-SP

A very easy to follow

“Assembly Instructions”

With Drawings and Photos

except for 5 differences the skt sp and the fleat sp are identical
Except for 5 Differences the SKT-SP and the FLEAT-SP are Identical
  • Please note: To Avoid duplication the Installation for the Type 1 SKT-SP is Covered with the Type 4A FLEAT-SP of this Training
5 differences type 1 skt sp type 4a fleat sp
5 Differences Type 1 SKT-SPType 4A FLEAT-SP
  • 1. Flare
    • SKT-SP: 12” FLEAT-SP: 48”
  • 2. Extrudes Guardrail
    • SKT-SP Away from Traffic
    • FLEAT-SP Towards Traffic
  • 3. Size of Impact Head & Feeder Chute
    • SKT-SP Longer
    • FLEAT-SP Shorter
5 differences type 1 skt 27 type 4a fleat 27
5 Differences Type 1 SKT-27Type 4A FLEAT-27
  • 4. Cable Fed Inside/Outside Feeder Chute
    • SKT-SP Cable Fed thru Feeder Chute
    • FLEAT-SP Cable Fed Outside Feeder Chute
  • 5. Bolt or No Bolt Connection to Post 3
    • SKT-SP Guardrail IS Bolted to Post 3
    • FLEAT-SP Guardrail is NOT Bolted to Post 3
flare type 1 skt sp 12 type 4a fleat sp 48
Flare Type 1 SKT-SP= 12”Type 4A FLEAT-SP = 48”

Type 4A

FLEAT-SP

48” Flare

Type 1 SKT-SP 12” Flare

Next to Roadway/Shoulder

extrudes guardrail skt sp away from traffic fleat sp towards traffic
Extrudes GuardrailSKT-SP Away from TrafficFLEAT-SP Towards Traffic

Type 1

SKT-SP Away from Traffic

Type 4A

FLEAT-SP Towards Traffic

size of impact head and feeder chute type 1 skt sp longer type 4a fleat sp shorter
Size of Impact Head and Feeder ChuteType 1 SKT-SP LongerType 4A FLEAT-SP Shorter

SKT-SP Longer

Impact Head

Feeder Chute

Feeder Chute Ends

FLEAT-SP Shorter

Impact Head

Feeder Chute

slide76
The KYTC Pay Limits for the Type 1 End Treatment SKT-SP is 50’ even though the SKT-SP Shop Drawing says 12’ 6” for the 37’ 6” System

KYTC Type 1 Guardrail End treatment Pay Limits 50 Feet

Standard Drawing RBR-020 Guardrail End Treatment Type 1

Road Systems SKT-SP

Pay Limits 12’ 6”

manufactures installation info
Manufactures Installation Info
  • SKT-SP Road Systemshttp://roadsystems.com/fleat.htmlhttp://roadsystems.com/pdf/fleat/SP-Installation-Manual.pdf
    • 1-432-263-2435
  • ET-Plus Trinity Highway Products http://www.highwayguardrail.com/products/pdfs/ETPlus-Manual.pdf
    • 1-800-282-7668 Elizabethtown KY
  • Both have a short Section on Repairs