Long Guiding Tube R. Vuillermet 17/03/2011
Status at CERN • Status • Some connection prototypes are under fabrication (4 in totals). Louis Rose-Dulcina is in charge of this task • 3M DP460 scotch-Weld was ordered (shall be delivered next week) • Week 13, special cleaning and surface preparation will be done in the polymer lab at CERN for gluing test . • Once glued, some section cutting will be done to check the glue coverage to validate the joint geometry • Once validated, the machining of 3735 mm pipe will be done and prepare for the gluing (we are waiting Andrei for this final operation)