SEE goes north of the polar circle

SEE goes north of the polar circle. Christian Sigmund, Keller Austria. SEE goes north of the polar circle. Narvik. Narvikterminalen, Norway. Narvikterminalen, Norway. Narvik Harbor. Slab Area. Pile Area. Narvikterminalen, Norway. First job. Sealing slab. First job: sealing slab.

Download Presentation

SEE goes north of the polar circle

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. SEE goes north of the polar circle Christian Sigmund, Keller Austria

  2. SEE goes north of the polar circle Narvik www.KellerGrundbau.at

  3. Narvikterminalen, Norway www.KellerGrundbau.at

  4. Narvikterminalen, Norway Narvik Harbor www.KellerGrundbau.at Slab Area Pile Area

  5. Narvikterminalen, Norway First job www.KellerGrundbau.at Sealing slab

  6. First job: sealing slab Most shallow pit – inclined www.KellerGrundbau.at

  7. First job: sealing slab Deepest pit: 15 m / 10 m water www.KellerGrundbau.at

  8. First job: sealing slab Deepest pit: 15 m / 10 m water KCI in use! 20% additional columns! www.KellerGrundbau.at

  9. First job: sealing slab www.KellerGrundbau.at

  10. First job: sealing slab www.KellerGrundbau.at

  11. First job: sealing slab www.KellerGrundbau.at

  12. Narvikterminalen, Norway Second job www.KellerGrundbau.at Joint sealing between piles and rock

  13. Second job: Joint sealing between piles and rock www.KellerGrundbau.at

  14. Second job: Joint sealing between piles and rock www.KellerGrundbau.at

  15. Second job: Joint sealing between piles and rock Procedure Initial situation; positioningofthebarge / pontoonabovethesteelpile ±0 sealevel auxiliaryshipwithcrane bargewithsiteinstallation –25 m www.KellerGrundbau.at seabottom steelpile Ø 1100 mm –60 m to–75 m bedrock

  16. Second job: Joint sealing between piles and rock installationofrods; drilling down tothe final sealingdepth Procedure ±0 sealevel –25 m www.KellerGrundbau.at steelpile seabottom steelpile Ø 1100 mm concreteplug Soilcrete-drilling –60 m to–75 m bedrock bedrock

  17. Second job: Joint sealing between piles and rock executionofsealingelement ; pulling out oftherods Procedure grout ±0 sealevel –25 m www.KellerGrundbau.at steelpile seabottom steelpile Ø 1100 mm Soilcrete-sealing Soilcrete-sealing –60 m to–75 m bedrock bedrock

  18. Second job: Joint sealing between piles and rock installationofrodsincluding a down the hole hammer; drilling down intothebedrock; pullingofrods Procedure ±0 sealevel –25 m www.KellerGrundbau.at seabottom steelpile Ø 1100 mm Soilcrete-sealing –60 m to–75 m bedrock –75 to–90 m

  19. Second job: Joint sealing between piles and rock Installation andinjectionofthesteelties Procedure Steel ties grout ±0 sealevel –25 m www.KellerGrundbau.at seabottom steelpile Ø 1100 mm Soilcrete-sealing –60 m to–75 m bedrock steeltie –75 to–90 m injectedgrout

  20. Second job: Joint sealing between piles and rock All steelpilesofthenewharbourareaarenowanchoredintothebedrock Procedure ±0 sealevel –25 m www.KellerGrundbau.at seabottom steelpile Ø 1100 mm Soilcrete-sealing –60 m to–75 m bedrock steelties –75 to–90 m injectedgrout

  21. Second job: Joint sealing between piles and rock www.KellerGrundbau.at

  22. Second job: Joint sealing between piles and rock www.KellerGrundbau.at

  23. Second job: Joint sealing between piles and rock www.KellerGrundbau.at

  24. Second job: Joint sealing between piles and rock www.KellerGrundbau.at

  25. Second job: Joint sealing between piles and rock www.KellerGrundbau.at

  26. Second job: Joint sealing between piles and rock www.KellerGrundbau.at

  27. Second job: Joint sealing between piles and rock Drilling depth www.KellerGrundbau.at

  28. Thank You!