An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. COMPANY PORTFOLIIO MCLENDON ENTERPRISES FOOTPRINT IN GA.

  2. OFFICE LOCATIONS Main Office 2365 Aimwell RoadVidalia, GA 30474 (912) 537-7887 Savannah Office 9 Chatham Pkwy. S. Dr. Suite B-2 Savannah, GA 31405 (912) 349-0677

  3. MISSION STATEMENT McLendon Enterprises Inc. and its employees share the same goals of integrity, quality, teamwork, safety and continuous improvement in each and every project. MEET THE TEAM

  4. BACKGROUND McLendon Enterprises was incorporated in 1979 at which time the leadership role was then taken over by current President / Owner, Benny McLendon Contract Revenue Earned 2011: $ 33,457,474.00 2012: $ 46,660,631.00 *Number Of Permanent Employees* 2010: 93 2011: 112 2012: 130 2013: 140

  5. ON THE HORIZON Transportation Projects Georgia Department of Transportation CDBG Projects City Streets / Roadway Utility Installations Water Storm Sewer / Force main / Pump stations Other Projects Subdivisions Treatment Plants Design Builds

  6. CURRENT PROJECTS OVER $ 2,000,000.00

  7. PROJECTS COMPLETED WITHIN PAST TWO YEARS OVER $ 1,000,000.00

  8. BUILDING TODAY'S INFRASTRUCTURE WITH TOMORROWS TECHNOLOGY 3D-GPS, 3D-MILLIMETER GPS, LPS

  9. - INCREASE GRADING PRODUCTIVITY SIGNIFICANTLY - REDUCE STAKING ON JOBSITE ALMOST ENTIRELY - CONTROLLING OF MATERIAL

  10. - UP TO 300% MORE ACCURATE THAN STANDARD GPS - INCREASED PRODUCTIVITY – FEWER PASSES NEEDED TO REACH FINISH GRADE - GRADE TO TIGHTER TOLERANCES

  11. - HIGH ACCURACY FOR TIGHT TOLERANCES PROJECTS - USED WHEN THE JOBSITE DOES NOT HAVE VISIBILITY TO OPEN SKY I.E. WORKING BETWEEN BUILDINGS OR IN HEAVY TREE COVERAGE

  12. MCLENDON ENTERPRISES INC. FOOTPRINT IN GA. CURRENT PROJECTS AS OF AUGUST 1, 2013

  13. NORTH AVIATION EXPANSION - LENGTH OF TAXI WAY = 6,800 FEET - LENGTH OF TUNNEL =1,200 FEET - PILES DRIVEN = 688 - CUBIC YARDS OF DIRT MOVED = 850, 000 - COST OF PROJECT = $ 24,371,531.00

  14. PLANT VOGTLE “21” DAY EMERGENCY RAIL REPAIR - 15,000 CYDS. OF DIRT REMOVED - THREE RUNS OF 72” RCP 180’ LONG EACH REPLACED - 50 CYD. CONCRETE WEEP WALL INSTALLED - 20,000 CYDS. OF DIRT REPLACED - 130,000 LBS. OF SAND AND CONCRETE BAGS - REPLACED 300’ OF RAILROAD

  15. DEAN FOREST ROAD WIDENING - LENGTH OF PROJECT = 2.5 MILES - TOTAL UNDERGROUND UTILITIES INSTALLED = 9,750 FEET - CUBIC YARDS OF DIRT MOVED = 60, 000 - COST OF PROJECT = $ 7,895,231.00

  16. GA DOT MLP OO-0030-(081) EVANS COUNTY - LENGTH OF PROJECT = 1.58 MILES - CYDS. OF CONCRETE POURED FOR RETAINING WALL = THREE FOOTBALL FIELDS x THREE FT. DEEP - TOTAL UNDERGROUND UTILITIES INSTALLED = 84,480 FEET - COST OF PROJECT = $ 18,934,256.00

  17. VIDALIA, GA COST OF PROJECT = $ 4,183,202.00 ASPEN HEIGHTS APARTMENT COMPLEX NEW MEADOWS HOPISTAL STATESBORO, GA COST OF PROJECT = $ 2,569,941.00

  18. MCLENDON ENTERPRISES INC. WORKING HAND IN HAND

  19. BUDGETING - CREATING MAXIMUM VALUE FOR EVERYONE - WAYS TO MAINTAIN PROJECT SCHEDULES - HIGH QUALITY PROJECT RESULTS

  20. ON SITE MEETINGS - PLANNING AND PREPARING - PROJECTS PROGRESSION - EXECUTION OF PLANNING - PROJECT COST ANALYSING

  21. COMPLETION OF PROJECTS - - DID WE MAINTAIN A GOOD QUALITY PRODUCT ? - DID WE FINISH UNDER BUDGET ? - DID WE FINISH PROJECT EARLY ? - WHAT DID WE LEARN ?

  22. THE Way !

  23. ITEMS TO DISCUSS: - MCLENDON ENTERPRISES HISTORY: PAST, PRESENT, AND FUTURE - BUILDING TODAY'S INFRASTRUCTURE WITH TOMORROWS TECHNOLOGY - MCLENDON ENTERPRISES INC. WORKING HAND IN HAND