CENTRAL POWER GENERATION CO. LTD. GENCO-II, GUDDU. BY:. ENGR. ABDUL MALIK MEMON CHIEF EXECUTIVE OFFICER. LOCATION. QUETTA 35 MW. GUDDU 1655MW + 747MW. SUKKUR 50 MW. THERMAL POWER STATION, GUDDU UNITS 1 TO 4. THERMAL POWER STATION, GUDDU UNITS 1 TO 13. KEY STATS AS ON 11 TH NOV.

teigra
Download Presentation

BY:

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CENTRAL POWER GENERATION CO. LTD. GENCO-II, GUDDU BY: ENGR. ABDUL MALIK MEMON CHIEF EXECUTIVE OFFICER

  2. LOCATION QUETTA 35 MW GUDDU 1655MW+747MW SUKKUR 50 MW

  3. THERMAL POWER STATION, GUDDU UNITS 1 TO 4

  4. THERMAL POWER STATION, GUDDU UNITS 1 TO 13

  5. KEY STATS AS ON 11TH NOV.

  6. UNITWISE DETAILS

  7. UNITWISE DETAILS

  8. UNITWISE DETAILS

  9. PERFORMANCE INDICATORS (%)2009-10

  10. PERFORMANCE INDICATORS (%)2009-10

  11. PERFORMANCE INDICATORS (%)2009-10

  12. PERFORMANCE INDICATORS (%)OVERALL

  13. GENERATION COST

  14. Major OverHauling (MOH)

  15. Major OverHauling (MOH)

  16. Major OverHauling (MOH)

  17. REFURBISHMENT PLAN

  18. REFURBISHMENT STATISTICS

  19. REFURBISHMENT PLANBLOCKS 3 & 4 Time Required : 10 &14 Months

  20. REFURBISHMENT PLANBLOCK 2 Time Required : 14 Months

  21. REFURBISHMENT PLANBLOCK 1 Time Required : 15 Months

  22. REFURBISHMENT INCREASE IN MW

  23. IMPROVEMENT IN HEAT RATE (BTU/kWh)

  24. RISE IN EFFICIENCY (%)

  25. CURRENT ISSUES SCRAP • INSUFFICIENT GAS SUPPLY • 260 AGAINST 360 MMCFD • SHORTAGE OF STAFF • TECH. , TEACHING & MINISTERIAL • SHORTAGE OF DOCTORS • JUNCKS

  26. CURRENT ISSUES PLANT 5. MISERABLE CONDITION 6. ESTT. COST FOR REHABTN. OF CHEMICAL PLANT GUDDU Rs.30M JAMSHORO Rs.80M

  27. CURRENT ISSUES COST OF R.O PLANT Rs. 80 Million 4 x 50 m3/hr 7. EVERSE OSMOSIS (R.O) PLANT WATER TREATMENT ANNUAL COST

  28. ISSUES RESOLVED • SUFFICIENT NUMBER OF VEHICLES PROVIDED • RECRUITMENT OF 22 JUNIOR ENGINEERS IN PROCESS • GUDDU COLLEGE UPGRADED TO DEGREE LEVEL

  29. ACHIVEMENT

  30. COMPLIANCE TO DECISION OF TRANSITION TEAM 1. THERMOGRAPHIC2. ULTRASONIC DETECTOR3. HELIUM DETECTOR CAMERA

  31. KEY PERFORMANCE INDICATORS (DRAFT) ST - 1 & 2 REPLACEMENTS • Boiler Burners and Burners Management System • Super Heaters No. 4 • High Pressure Steam Pipelines REHABILITATION • F.D Fan / I.D Fan 7 Flue Gas Recirculation Fan • HP & LP Bypass Station • Unit Auxiliaries Equipments • Generator & Allied Equipment • Instrumentation and Control System

  32. KEY PERFORMANCE INDICATORS (DRAFT) ST - 3 REPLACEMENTS • 2nd and 3rd Stag Convective Super Heaters No.6 and 7 of Boiler • Soot Blowing System • Fuel Oil Forwarding Pump at Oil Station • Oil Burners with Remote Control • 25 MVA Units Auxiliary Transformer to be installed REHABILITATION • H.P Heaters renovation • Heat Exchangers • Heating Elements of Air Pre Heaters (Cold and Hot ends) • Air Pre-heaters Flue Gas Ducts • Exhaust Stack (Chimney) • Close Cycle – Circulating Water System • Water Treatment Plant

  33. KEY PERFORMANCE INDICATORS (DRAFT) ST - 4 REPLACEMENTS • Furnace Supervisory Safety System (FSSS) of Boiler by new Modern System REHABILITATION • Soot Blowing System • Heat Exchangers • Air Pre-heaters Heating Elements (Cold and Hot end) • Close Cycle Circulating Water System • Regenerative Air Pre-heaters • Turbine Governing System