1 / 15

Project Time Management

Project Time Management. Project time management includes the processes required to ensure timely completion of the project. This includes: Activity Definition Activity Sequencing Activity Duration Estimating Schedule Development Schedule Control. Strategic Project Management.

tavita
Download Presentation

Project Time Management

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Project Time Management • Project time management includes the processes required to ensure timely completion of the project. • This includes: • Activity Definition • Activity Sequencing • Activity Duration Estimating • Schedule Development • Schedule Control Strategic Project Management SPM Project Time Management 1

  2. Activities versus Tasks • There is some inconsistency within the Project Management community regarding the use of the terms “activity” and “task” • some say activities are composed of tasks • some say tasks are composed of activities • We will use the terms “activity” and “task” interchangeably • know how your company defines these terms Strategic Project Management SPM Project Time Management 2

  3. Project Time Management(continued) • We will focus on three processes: • Activity Sequencing, • Activity Duration Estimating, • Schedule Development • The PMI BOK presents a useful framework throughout the Processes Chapters • Inputs-Techniques-Outputs • Let’s look at Figure 6-1 (page 66, BOK 2000) • 2000 version has some updates over the 1996 Strategic Project Management SPM Project Time Management 3

  4. Activity Definition • Activity definition involves identifying and documenting the specific activities that must be performed in order to produce the deliverables. • Useful techniques include: • Work Breakdown Structures • Decomposition of Project Elements • Historical Information from Prior Projects Strategic Project Management SPM Project Time Management 4

  5. Work Breakdown Structure • A Work Breakdown Structure (WBS) is a deliverables oriented grouping of project elements • organizes and defines scope • develops and confirms common understanding • hierarchical structure with descending levels showing increasing detail • normally presented in chart form Strategic Project Management SPM Project Time Management 5

  6. Work Breakdown Structure(continued) • Items in the WBS can be given unique identification codes • Code of Accounts • Items at the lowest level are often referred to as Work Packages • Many organizations have standard WBSs which are used as templates. • PMI BOK contains several good examples • Figures 5-2, 5-3, 5-4 (p. 58-60, BOK 2000) • same content p. 54-55 BOK 1996 Strategic Project Management SPM Project Time Management 6

  7. Activity Sequencing • Activity sequencing involves identifying and documenting interactivity dependencies. • These can be broken into three types: • Mandatory dependencies • inherent in the nature of the work • physical limitations Strategic Project Management SPM Project Time Management 7

  8. Activity Sequencing(continued) • Discretionary dependencies • desired but not mandatory • inserted by project planners • frequently based on “best practices” • External dependencies • imposed from outside the project • multi-project issues • regulatory issues Strategic Project Management SPM Project Time Management 8

  9. Activity Sequencing(continued) • Useful techniques include: • Gantt Charts • Precedence diagramming • Activity on the Node • Activity on the Arrow • Conditional Diagramming • We’ll talk more about these later in the course. Strategic Project Management SPM Project Time Management 9

  10. Activity Duration Estimating • Duration estimating involves assessing the number of work periods that will be required to complete each activity. • May also include an estimate of elapsed time • Activity duration estimating typically requires two measures: • a measure of expected activity duration • a measure of variation of expected duration Strategic Project Management SPM Project Time Management 10

  11. Activity Duration Estimating (continued) • Useful techniques include: • Historical Information • Commercial Databases • Expert Judgement • Estimating using Analogies • Simulation • Reserve (Contingency, Buffer) Time • More on this later in the course. Strategic Project Management SPM Project Time Management 11

  12. Schedule Development • Schedule development means determining the start and finish dates (times) for project activities. • Useful techniques include: • CPM (Critical Path Method) • PERT (Project Evaluation & Review Technique) • GERT (Graphical Evaluation & Review Technique) • More on these in the next few topics. Strategic Project Management SPM Project Time Management 12

  13. Schedule Development(continued) • More advanced techniques related to Schedule Development include: • Resource Constraints and Leveling • Duration Compression (“Crashing”) • Simulation • More on these later in the course Strategic Project Management SPM Project Time Management 13

  14. Displaying the Schedule • After the preceding steps have been completed, the project schedule must be documented and, usually, displayed. • Useful approaches include: • Network Diagram with Dates (Figure 6-5) • Gantt Charts (Figure 6-6) • Milestone Charts (Figure 6-7) • Time-scaled Network Diagrams (1996, Fig 6-8) Strategic Project Management SPM Project Time Management 14

  15. Schedule Control • Schedule control is concerned with • managing the factors which lead to changes, • determining the need for a schedule change, • managing the actual changes. • Useful techniques include: • Change Control System • Milestone Progress Reporting Strategic Project Management SPM Project Time Management 15

More Related