An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Master Plan Needs AssessmentChurch of theImmaculate ConceptionNovember 9, 2011

  2. Agenda for 11/9/11 • Prayer Fr. Joe Bar Pastor • Welcome/Introductions/Format Debra Bartgis Pastoral Council President • Master Plan Overview Fr. Joe Barr • Committee Reports (10 minute presentations with 5 minutes Q&A) • Cemetery Fr. Joe Barr • Worship Julio Esteban • Parish Community Life Carole Gibison • Administrative/Housing Brian Gobell • School George Towle • Facilities Dick Magnani • Closing Prayer Fr. Joe Barr

  3. Parish Mission Statement The Parish of the Immaculate Conception with special devotion to the Blessed Mother, our patroness, accepts God’s call to proclaim the Gospel though our commitment to evangelization, worship, education, service and stewardship.

  4. Master Plan Steering Committee To design/implement a master plan to meet the spiritual, educational, social needs of the parish with supportive considerations for the surrounding community. • Visionary Phase (current): Needs Assessment • Tactical Phase • Implementation Phase

  5. Master Plan Subcommittees & Chairs The five functional subcommittees are represented by parishioners with varied interests and expertise. • Administrative/Housing Chair: Brian Gobell • Cemetery Chair: Joe Hart • Facilities Co-chairs: Dick Magnani, Lou Baird • Parish Community Life Chairs: Carole Gibison, Jack McGrain, Lynn Lehneis • School Chair: George Towle • WorshipChair: Julio Esteban, Anne-Therese Bechamps

  6. Master Plan Steering Committee Foundation of a Master Plan • Over the summer months, the chairs and members met on numerous occasions developing a needs assessment for each of their respective functional committees

  7. Cemetery Committee • Established 13 Goals • Addressing specifics on how to improve our cemetery • Researched Secular & Church Cemeteries with Columbariums • 2 catholic and 6 secular cemeteries that had columbariums • 5 Churches (Catholic and Protestant) with columbariums within a 5 mile radius • Costs, fees, regulations

  8. Worship Committee • Post-Mass Gathering • Need Larger Gathering Space • Current narthex too small/congested • Limited space for parish announcements • Need More Time for Socializing • 30 minutes between Masses too restrictive • Mass schedule affects religious education classes • Need Less Restrictive Parking Plan • Stadium parking discourages lingering • Garage ingress/egress problem for priests

  9. Worship Committee • Sacristy • Need More Space for Clergy/Altar Servers • Must accommodate multiple users • Need Adequate User-Friendly Storage • Cabinets hard to reach; drawers shallow • Insufficient space for needed materials • Difficult/dangerous access to attic storage

  10. Worship Committee • Children’s Programs • Need Dedicated Space for Children’s Liturgy of the Word (CLOW) • Shared space with Chapel creates conflict • Inadequate learning environment • Need Indoor CLOW Space at Church • Time limited to liturgy • Need Child Care During Masses • Crying infants distract worshipers

  11. Worship Committee • Adoration Chapel • Need to Re-dedicate Purpose • Chapel has become multipurpose room • Separate space for other devotions • Needs 24-7 Dedicated Parking • Not enough current handicap spaces • Night-time safety issue • Need to Reconfigure Sacristy/Chapel Spaces • CLOW time limit requires space next to Church • Chapel can stand alone

  12. Worship Committee • Music Ministry • Need Separate Rehearsal Spaces • Three singing groups/different schedules • Rehearsals in Church conflict with religious activities • Need Working Space for Ministry • No current office space/facilities • No space for meetings

  13. Worship Committee • Fellowship • Need Facility to Host Large Events (300 +) • Existing parish hall too small • Need Facility to Host Fund Raising Meals • Inadequate parish hall kitchen • Need Hall Close to Church • Existing parish hall too far to walk • Hall to house/unite various parish functions

  14. Parish Community Life Committee • Meeting Space Needs • Multi-purpose room to accommodate all youth activities • Movable sound-proof walls equipped with technology • Adult Faith meetings range from 9 in Convent – 65 people Parish Hall • Respect Life committee 20 people in Convent – up to 100 for sponsored speakers in Parish Hall • Scouts (Boys/Girls) – weekly (afternoons/evenings) during school year • Social Functions – use Parish Hall

  15. Parish Community Life Committee • Child Care Needs • During Mass adjacent to Church • Adult Faith Committee and Respect Life near meeting rooms • Child-age equipment /technology • Nearby restrooms • Library/Resource Room Needs • Currently inadequate space for Scouts after school programs, and as a technology center during school • Storage Needs • Dedicated storage for our participating ministries and groups

  16. Parish Community Life Committee • Religious Education Needs • School of Religion – 200 students weekly • Sacramental Preparation – September-May involving 175 students and parents • Children’s Liturgy of the Word – year-round – up to 20 children per Mass • Vacation Bible School – last two weeks of July – 200 students & adult volunteers • RCIA – September-April one evening weekly

  17. Parish Community Life Committee • Youth Ministry Needs • Theme-based religious activities each week (Bible Study, Topic Night, Worship) – 35 students • Use Parish Hall, Gym, Cafeteria, Convent, Church • Expansion into Middle School this Fall • Exploring expansion into Young Adults • Athletic Association (ICAA) Needs • Upgraded gymnasium

  18. Administrative and Housing • Administration • Existing Conditions • Located in the basement and first floor of the Convent (second floor storage only) • 7,000 square feet of space on two levels used for business; vacant convent housing on 2nd & 3rd floors used for storage • (9) full-time and (6) part-time staff members • Needs Assessment (based on survey results) • Segregation of staff (by floor) is inefficient • Additional offices for part-time staff • Additional offices can be shared (day-evening) • Large gathering space for 300+ is sometimes requested for Archdiocesan events • Business meeting spaces for 30 – 60 people

  19. Administrative and Housing • Housing • Existing Conditions • Located directly adjacent to the main Church • 5,000 square feet of space on three levels • (4) resident-priests + (1) seminarian suite • Needs Assessment (based on survey results) • Spatially, current living quarters are adequate • Privacy is compromised due to central location on campus • Not handicap accessible; no elevator • Garage parking access for priests an issue due to parking for Church/School functions • Other • Purchase of nearby residence (house vs. apartment) • Forecast of future priest staffing

  20. School • Need to Create Premier Middle School • High outcomes support growth • STEM, Blue Ribbon Status potential, low student turnover • 99% of ICS students accepted to first choice high school • Only parochial school in area growing in past 3 years • Significant opportunity for more students: need 750+ • Currently at 540; as high as 650 in 2002 • React to the demand now present in the market • Survey of parents with students leaving at 6th grade indicates 50% might have remained through 8th grade if ICS had: • Gifted & Talented Honors program • Athletic programs • Variety of extracurricular activities • Requires dedicated Admissions/Recruitment and Marketing Staff

  21. School • Need to Create First Class Pre-school/Kindergarten • Pre-k currently at Brown House, not integrated into school • Need to be seen as visible part of community • Need to coordinate schedules; current schedules not appealing to ICS parents • Need a “one-stop” solution for parents • Vibrant Pre-K program is key feeder to ICS • Financial model requires 80-100 kindergarten students for a solvent grade school • Current only 50 students in kindergarten • Kindergarten population should be “lock” for future students; we are currently jeopardizing the school with only 50 students • Requires dedicated Admissions/Recruitment and Marketing Staff

  22. School • Possible uses of TCHS building not recommended • Catholic Magnet School • Lack of interest from neighboring parishes • Regional Spiritual Life Center • Lack of revenue stream to support costs • Safety and security issues for ICS students in building and adjacent school • Rental of Space • Safety and security issues • Demolition of Building • Excessive Costs due to asbestos abatement • Negative effect on current ICS

  23. Facilities • Lower Rectory • Parish Library • Bell Tower • Parking Lots • Athletic Field • Playground • Cemetery • Roads & Sidewalks • Assets • Church Building • Adoration Chapel • Rectory & Garage • Convent • Parish Hall • Elementary School • Former High School • Brown House Site Approximately 12 Acres

  24. Facilities • Procedure • Toured each building and walked campus • Reviewed available construction drawings • Reviewed prior Master Plans dated 1998, 2002 & 2004 • Reviewed insurance replacement cost reports prepared by Suncorp • Met with Rubeling & Associates to discuss prior Master Plans

  25. Facilities • Building Issues • Church/Rectory/Rectory Garage • Well maintained and suitable for current use • Minor repairs required • Convent • Existing live load capacities limit reuse for other occupancy types • Wood construction of original 1920 building and 1952 addition - fire protection concerns • Asbestos and lead paint issues • Electrical and plumbing issues • No central HVAC system • Parish Hall • Warming kitchen is undersized

  26. Facilities • Building Issues (continued) • Elementary School • Undersized classrooms 29 total • Functionally obsolete in large part • New windows currently being installed • Building is air conditioned and sprinkled • Constructed in 1920, 1928, 1960 and 1998 • Asbestos and lead paint • Former High School • Constructed in 1952; 17 classrooms • Grade school uses first floor on a daily basis, balance is vacant • Neglected condition can be readily renovated • Structurally sound building live load capacities will permit any use • Needs to be brought up to code for Handicap access • Needs some life/safety upgrades • Plumbing, heating, electrical and HVAC systems need upgrading • Asbestos and lead paint issues

  27. Facilities • Building Issues (continued) • Brown House, Lower Rectory and Library • Physically and functionally obsolete - plumbing, electrical and HVAC systems have exceeded life expectancy • These buildings do not meet the current Building Codes in one aspect or another • Reuse as a residence rental property, offices for ICC use or rental offices will require extensive renovations to bring the buildings up to code and to upgrade or replace internal systems • Preschool space in Brown House is not at grade

  28. Facilities • Site Issues • How to get additional parking spaces • Improve traffic circulation on campus • Position of any new buildings • Enhance the appearance of the campus • Make walking from parking areas to buildings an enjoyable experience • Site is now close to maximum impervious area ratio • Additional storm water management issues will be required for any new construction, buildings, or paving for both quantity and quality creative solutions will be required • Inadequate play areas for preschool, elementary and middle schools

  29. Next Steps • Tactical Phase • 11/30/11 – Meeting with chairs to incorporate parishioner feedback into a final Master Plan needs assessment report • Communicated via 12/25/11 Bulletin • January 2012 – Interview Architecture Firms with Master Plan experience from an Archdiocesan approved list (select by February 2012) • February/March 2012 – Architecture Firm to meet with each Master Plan Sub-committee to further assess details of needs • Late Spring 2012 – Preliminary Master Plan to be unveiled at a Parish Town Hall meeting • Also via web site and bulletin

  30. Contact Information Questions? Email masterplan@theimmaculate.org • Administrative/Housing: Brian Gobell • Email: Bgobell@HCM2.com Phone: 443-451-2311 • Cemetery: Joe Hart • Email: jhart@gbmc.org Phone: 410-427-4715(McCarty) • Facilities: Dick Magnani • Email: dmagnani@comcast.net Phone: 443-253-5721 • Parish Community Life: Carole Gibison • Email:carolegibison@aol.com Phone: 410-825-1960 • School: George Towle • Email: gtowle@comcast.net Phone: 410-853-7444 • Worship: Julio Esteban • Email: esteban_j@verizon.net Phone: 410-821-1635