Gas Section Objectives Meeting 2006. Gas systems Installation & Testing. Installation Dictionary. Infrastructure (power, cables, pipes, Ethernet, services…) Installation: Delivery of 100% tested racks to Points Fixation of racks in final position Support Team (component replacement, etc)

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

Gas Section Objectives Meeting 2006


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
gas section objectives meeting 2006

Gas Section Objectives Meeting 2006

Gas systems Installation & Testing

Mar CAPEANS

installation dictionary
Installation Dictionary
  • Infrastructure(power, cables, pipes, Ethernet, services…)
  • Installation:
    • Delivery of 100% tested racks to Points
    • Fixation of racks in final position
    • Support Team (component replacement, etc)
  • Piping work:
  • Cabling work:Experiments do Inter-Area cabling, connectors included (ATLAS do not do connectors). Gas Group do Inter-Rack cabling

Mar CAPEANS

2006 schedule milestones

April

Oct

Aug

Sept

Start RPC commissioning

SingleP systems commissioned

Start commissioning

+Side Commissioning

2006 Schedule & Milestones

Mar CAPEANS

test schedule when racks have to be shipped
Test ScheduleWhen Racks Have to be Shipped

Target Dates for Rack Shipment are defined by our Milestones, but somehow also by the period when External Companies are on site, ready to connect our racks

Mar CAPEANS

summary tests to do distribution pre distribution racks
Summary Tests - TO DODistribution & Pre-Distribution Racks
  • Now - March
    • ATLAS: 3
    • ALICE: 9
    • LHCb: 11
  • April
    • ALICE: 4
  • May - June
    • CMS: 14
  • July - August
    • ATLAS: 10

~ 3 racks tested/week

Mar CAPEANS

summary tests to do other than dist racks
Summary Tests - TO DOOther than Dist. Racks
  • Now to Summer 06
    • Test of 3x Humidifiers
    • 6 x Pump (1x MDT, 2-3x LHCb, 3xCMS)
    • TGC supply
    • Compressors for LHCb RICH1&2 in 2007
    • All electrical, Control Components
  • End 06 and 2007
    • Purifiers
    • Analysis in 07
    • Experiment Modules
    • Special TRT modules at the beg 07
    • Membranes for LHCb RICH1&2 in 2007

Mar CAPEANS

detailed analysis assumptions for inter rack cabling work
Detailed AnalysisAssumptions for Inter-Rack Cabling Work
  • We (Patrick & I) have taken into account:
    • that cables are installed with connectors at one or two ends
    • Lab-tests & estimates for cables inter-areas
    • for the final figures, we add a 20% contingency

Typical Figures:

Single-Path System ~ 0.5 days

Closed-Loop System ~ 1.5 days

Mar CAPEANS

inter area cabling
Inter-Area Cabling

SP System ~ 0.5 days, CL System ~ 1.5 days

Mar CAPEANS

inter area cabling1
Inter-Area Cabling

1 person could do!

Mar CAPEANS

detailed analysis assumptions for inter rack piping work
Detailed AnalysisAssumptions for Inter-Rack Piping Work
  • We (Fred & I) have taken into account:
    • Estimates based on ALICE SG experience
    • For the final figures, we add a 20% contingency

Average Time:

Single-Path System ~ 5 days

Closed-Loop System ~ 13 days

Mar CAPEANS

inter area piping
Inter-Area Piping

SP System ~ 5 days, CL System ~ 13 days

Mar CAPEANS

inter area piping1
Inter-Area Piping

ALICE SG

Estimate: ~ 440 h

Reality: 400 h FSU

Team of 2 people needed to meet Installation Milestones

Mar CAPEANS

fte for installation
FTE for Installation

Need to check tasks after Oct

Support for Commissioning not accounted.

Neither Fred & I

Mar CAPEANS

slide15
2006

Mar CAPEANS