Improving your stormwater pollution prevention plans
Download
1 / 38

Improving Your Stormwater Pollution Prevention Plans - PowerPoint PPT Presentation


  • 116 Views
  • Uploaded on

Improving Your Stormwater Pollution Prevention Plans. Ryan Alltop, CPESC, DECI Quality Control Manager. Overview. Regulations SWPPP Erosion Control vs. Sediment Control Standards, Specifications, & Drawings Recommendations What’s New Plan Design.

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about 'Improving Your Stormwater Pollution Prevention Plans' - taariq


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
Improving your stormwater pollution prevention plans

Improving Your Stormwater Pollution Prevention Plans

Ryan Alltop, CPESC, DECI

Quality Control Manager


Overview
Overview

  • Regulations

  • SWPPP

    • Erosion Control vs. Sediment Control

    • Standards, Specifications, & Drawings

    • Recommendations

  • What’s New

  • Plan Design


Regulations for erosion and sediment control
Regulations for Erosion and Sediment Control

  • Environmental Protection Agency – National Pollutant Discharge Elimination Systems (NPDES) Phase I & II

  • U. S. Army Corps of Engineers

  • County and Municipal Ordinances


National pollutant discharge elimination system npdes illinois construction activities
National Pollutant Discharge Elimination System (NPDES) Illinois-Construction Activities

  • Clean Water Act

  • Administered by the Illinois EPA through the ILR10-Stormwater Permit for Construction Site Activities

  • Phase II requires permit for projects disturbing one (1) acre or more or projects that are “..part of a larger common plan of development or sale.”

  • Information and forms available at: www.epa.state.il.usandhttp://www.epa.state.il.us/water/permits/storm-water/construction.htmll


Some of the npdes requirements taken from the ilr10 permit and general permit no 2
Some Illinois-Construction Activities of the NPDES Requirements(taken from the ILR10 permit and General Permit NO 2)

  • Notice of Intent (NOI)—Submit to IEPA and Local MS4 Community

  • Stormwater Pollution Prevention Plan (SWPPP)

  • Incidence of Non-Compliance (ION) (IL)— submitted electronically to state within 24 hours of incidence

  • Notice of Termination (NOT) (IL) or Notice of Discontinuation (IA)

  • Records Retention—three (3) years from final stabilization


Swppp deadlines for preparation and signature review and notification requirements
SWPPP – Deadlines for Preparation and Signature, Review, and Notification Requirements

  • SWPPP must be completed prior to submitting your NOI and must provide compliance with schedule of construction activities.

  • The SWPPP shall be signed and be retained on-site at the facility which it is written for.

  • Plan must be available for review by IEPA, IDNR, local agencies, stormwater regulators, municipalities, and the public.

  • Any identified deficiencies must be rectified within 7 days of occurence.


Swppp management
SWPPP - Management and Notification Requirements


Swppp keeping plans current
SWPPP – Keeping Plans Current and Notification Requirements

  • The Stormwater Pollution Prevention Plan is intended to be a dynamic document which should change or be modified as necessary to protect receiving waters from pollutants.

  • The permitee is required to amend the plan whenever there is a change in design that effects the plan or if the plan has been shown to be deficient or ineffective in protecting waters of the state or other off site areas.

  • Changes is control measures should be noted on the plan in pencil, pen, or marker. Hand drawings or shop drawings are acceptable as modifications to the plan.

  • Additional contractors should be modified whenever a new contractor comes on site.


Swppp keeping plans current1
SWPPP – Keeping Plans Current and Notification Requirements


Swppp contents of the plan
SWPPP – Contents of the Plan and Notification Requirements

  • Site Description

  • Best Management Practices (BMPs)

  • Maintenance

  • Inspections

  • Non-Storm Water Discharges

  • Contractors

  • Signatory Requirements


Contents of the plan site descriptions
Contents of the Plan – Site Descriptions and Notification Requirements

  • Describe construction activity

  • Sequence of major activities which will disturb the site

  • Estimate of total acreage of the site and the acreage of disturbance

  • An estimate of the runoff coefficient of the site after completion

  • Site Map including drainage patterns, grading changes, stormwater facilities and discharge points, major structural and nonstructural Stormwater pollution controls, and receiveing water bodies. (Civil Drawings and Location Map)

  • Receiving water bodies and the ultimate receiving waters and aerial extend of any wetlands on-site or as a receiving body should be identified.


Contents of the plan site descriptions1
Contents of the Plan – Site Descriptions and Notification Requirements

  • Site soil maps (Web Soil Survey)

  • RUSLE 2 (Web Soil Survey)


Contents of the plan controls
Contents of the Plan – Controls and Notification Requirements

  • Controls make up the meat of the SWPPP when it is first created and are most often associated with the Erosion Control plan and associated details.

  • The SWPPP shall include a description of appropriate controls used on site and clearly describe and identify the implementation of the appropriate controls and the timing during the construction process where each control practice will be used.

  • The description of controls shall at a minimum include: Erosion and Sediment Controls, Stormwater Management, Other Control Measures, and meet the Approval of State or Local requirements.

  • The Illinois Urban Manual should be used for guidance in selecting and designing your controls in Illinois.

  • The Iowa Construction Site Erosion Control Manual should be used in Iowa


Contents of the plan controls1
Contents of the Plan – Controls and Notification Requirements

Erosion and Sediment Controls

  • Erosion Control Practices

    • Description of temporary, interim, and permanent practices including the scheduling and implementation of practices to vegetate or otherwise stabilized exposed soils or protect existing vegetation.

  • Sediment Control Practices

    • Description of practices installed to divert flows from exposed soils, store flows or runoff, and otherwise filter or limit the discharge of pollutants from the site.


Contents of the plan controls2
Contents of the Plan – Controls and Notification Requirements

Storm Water Management

  • Description of measures and practices that will be installed during the construction process that will serve to control the discharge of pollutants from the site during and after construction operations are complete.

  • Examples of practices include wet bottom detention basins, sediment basins, sediment traps, vegetated swales, infiltration trenches, and energy dissipation devices at the outfall of stormwater structures (rock lined aprons).


Erosion control primary design goal
Erosion Control-Primary Design Goal and Notification Requirements

  • Phased Construction

  • Limit Disturbed Area

  • Permanent Stabilization

  • Stabilize-As-You-Go

  • Winter Stabilization

  • Temporary Seeding

  • Mulching/Erosion Control Blanket

  • Velocity Minimization


Sediment control secondary design goal
Sediment Control-Secondary Design Goal and Notification Requirements

  • Barriers

  • Filtration

  • Sediment Containment Systems

  • Velocity Minimization


Contents of the plan controls3
Contents of the Plan – Controls and Notification Requirements

Other Controls and Approved State and Local Plans

  • Other Controls must ensure that solid materials or other pollutants are contained on-site and disposed of properly.

    • Spill Prevention and Clean-Up

    • Waste Disposal

    • Secondary Containment of Pollutants


Erosion sediment control plan

Erosion & Sediment Control Plan and Notification Requirements


Where do i start
Where do I start? and Notification Requirements

  • Identify Critical Area Protection

  • Where are my Cut/Fill Areas?

  • Temporary Drainage Conditions

  • Timing and Phasing

    • Time of Season

    • Duration of Construction


Standards specifications drawings
Standards, Specifications, and Notification Requirements& Drawings

  • Soil Erosion and Sediment Control (SESC) practices need to be DESIGNED into the project

  • SESC practices need to be treated like any other construction practice (i.e. sanitary sewer, water mains, etc.)

  • There’s more to SESC planning than inserting details


Standard drawings
Standard Drawings and Notification Requirements

  • Available in DWF, DWG, DXF, and PDF formats.

  • Most require additional dimensions to be inserted


Details
Details and Notification Requirements

  • Provide details for each SESC practice called out on plans or in notes

  • Fill in required values

  • Provide manufacturer details if necessary

  • If no standard drawings exist use shop drawings or create drawings showing plan view and/or overview of practice


Recommendations and Notification Requirements

  • Visit the site before designing the Soil Erosion and Sediment Control Plan

  • Begin communication early with municipality and all regulatory agencies

  • Create the SESC plan and SWPPP as part of the overall construction plan

  • Visit site after creating plans to determine if they make sense


Sesc plan sheets
SESC Plan Sheets and Notification Requirements

  • Clearly display and label all SESC measures

    • Generate more than one SESC plan sheet, if necessary, to clearly show different stages of construction

  • Review existing and proposed drainage to ensure perimeter barriers/fences will function throughout the duration of the project


Sesc plan sheets1
SESC Plan Sheets and Notification Requirements

  • Show location for erosion control blanket and/or mulch installation

  • Show proposed locations of stockpiles with perimeter barrier

  • Show lined aprons at storm sewer outfalls


Sesc plan sheets2
SESC Plan Sheets and Notification Requirements

  • Replace straw bale ditch checks

  • Designate location of stabilized construction entrance(s)


Notes and specifications
Notes and Specifications and Notification Requirements

  • Standard Notes—contact regulating entity or visit website to determine if standard notes exist

  • Provide sequence of events and appropriate SESC measures for work in critical areas


Notes and specifications1
Notes and Specifications and Notification Requirements

  • Clearly explain when various practices should be implemented

  • Accommodate for temporary conditions (between mass grading and final grading and stabilization)


Notes and specifications2
Notes and Specifications and Notification Requirements

  • Permanent and temporary vegetation/stabilization schedule

    • Critical Dates

    • Species List

    • Application Rates

    • Winter stabilization plan

    • Stockpile Stabilization

  • Review site conditions and manufacturer’s specifications to determine if the proper ECB is being used


Contents of the plan inspections
Contents of the Plan – Inspections and Notification Requirements

  • Qualified personnel shall inspect the site at least once every seven (7) days or within 24 hours of any rainfall event of ½ inch or greater.

  • Monthly Inspections during periods of Snow Cover.

  • Any violation of the SWPPP or discharges to receiving water bodies should be reported by filing an “Incidence of Non-Compliance” (ION) to the IEPA within 24 hours.


Contents of the plan maintenance
Contents of the Plan – Maintenance and Notification Requirements

  • All practices in the SWPPP must be maintained in good and effective operating condition throughout the duration of the project.


Contents of the plan non storm water discharges
Contents of the Plan – Non-Storm Water Discharges and Notification Requirements

  • Any sources of non-stormwater listed as industrial activities that shall be combined with stormwater discharges must be clearly identified on the plan. Examples include:

    • Hydrant Flushing

    • Groundwater Pumping

    • Dust Control

    • Vehicle Washing


Swppp contractor certification statements
SWPPP – Contractor Certification Statements and Notification Requirements

  • The SWPPP must identify each contractor or subcontractor that will be responsible for implementing each measure in the plan.

  • All contractors must sign a copy of the Certification Statement and that signed statement shall be included as part of the SWPPP.

  • The certification statement must also identify the name and title of the person providing the signature, contact information for the contractors’ firm, address or name of site, and the date of certification signing.


Swppp delegation of authority
SWPPP – Delegation Of Authority and Notification Requirements

  • Owner or General Contractor Sign Off


General comments
General Comments and Notification Requirements

  • Complete SWPPP and submit plans for review to appropriate agencies BEFORE project goes out to bid

  • Include Erosion and Sediment Control in your bid.

  • SESC plans are reviewed for both temporary and permanent components

  • Plan for each stage of the project

  • Better to provide too much information than not enough

  • Attempt to get plans correct and effective the first time around, but NEVER be afraid to change or modify the SWPPP or the practices in the SWPPP if they are not being effective.


Questions
Questions? and Notification Requirements

Ryan Alltop, CPESC, DECI

Quality Control Manager

ENCAP, Inc.

2585 Wagner Ct., DeKalb, IL 60115

815-748-4500

www.encapinc.net

[email protected]


Up coming seminars
Up Coming Seminars and Notification Requirements

  • Great Connections 2014

    • www.greatconnections2014.com


ad