An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. INTERREG III B CADSESNeighbourhood Programm 2000-2006“HERITOUR” Work Package 3 - Planning Activities Clara Puech European Projects Coordinator EGNATIA EPIRUS Foundation 16-17 September 2005 Somlóvásárhely, Hungary

  2. WORK PACKAGE 3 - Planning Activities • WP LEADER: EGNATIA EPIRUS FOUNDATION • Coordination of Work Package 3 • Extensive experience and know-how in cultural, tourism & ITC related initiatives • Participation in local management activities • Contribution to project methodology • Evaluation of project results and dissemination activities

  3. WORK PACKAGE 3 - Planning Activities • OBJECTIVES • Preservation of local cultural heritage in European villages • Assessment of local cultural heritage based on transnational and regional cooperation • Elaboration of feasibility studies and marketing strategies on possible transnational thematic cultural routes • Architectural planning activities for investment proposals • Implementation of marketing tools

  4. WORK PACKAGE 3 - Planning Activities • OVERVIEW • Task 3.1 – Assessment of the local cultural heritage • Task 3.2 – Survey and Analysis of target groups • Task 3.3 – Feasibility Study . Part 1 • Task 3.4 – Feasibility Study . Part 2 • Task 3.5 – Architectural Planning . Part 1 • Task 3.6 – Architectural Planning . Part 2 • Task 3.7 – Marketing planning • Task 3.8 – Transnational marketing plan • Task 3.9 – Architectural Planning . Part 3

  5. WORK PACKAGE 3 - Planning Activities Task 3.1 – Assessment of local cultural heritage • Month of start: January 2006 • Month of completion: March 2006 • Duration: 3 months • Assessment of local cultural heritage • Preparation of a database of cultural heritage, for tourism planning purposes

  6. WORK PACKAGE 3 - Planning Activities Task 3.2 – Survey and Analysis of target groups • Month of start: April 2006 • Month of completion: July 2006 • Duration: 3 months • Target groups/areas Surveys based on questionnaires • Publication of brochures in native, English and German languages

  7. WORK PACKAGE 3 - Planning Activities Task 3.3 – Feasibility Study . Part 1 Tourism Product Development • Month of start: July 2006 • Month of completion: September 2006 • Duration: 2 months • Analysis of cultural heritage protection needs and methods • Analysis of best practices for each cultural tourist route • Proposals for regional and transnational thematic routes • Analysis of attraction potential

  8. WORK PACKAGE 3 - Planning Activities Task 3.4 – Feasibility Study . Part 2 Operational Planning • Month of start: October 2006 • Month of completion: December 2006 • Duration: 2 months • Operational planning • Management methods • Financial plans

  9. WORK PACKAGE 3 - Planning Activities Task 3.5 – Architectural Planning . Part 1 • Month of start: August 2006 • Month of completion: December 2006 • Duration: 4 months • Construction plans for visitor-friendly infrastructure in the New Atlantis small region, Hungary • Initial architectural plans in the Region of Epirus, Greece and Gödöllö and Vicinity Region, Hungary

  10. WORK PACKAGE 3 - Planning Activities Task 3.6 – Architectural Planning . Part 2 • Month of start: January 2007 • Month of completion: April 2007 • Duration: 4 months • Construction plans in New Atlantis, Hungary

  11. WORK PACKAGE 3 - Planning Activities Task 3.7 – Marketing planning • Month of start: December 2006 • Month of completion: February 2007 • Duration: 3 months • Elaboration of marketing plans for each local projects • Preparation of a marketing budget

  12. WORK PACKAGE 3 - Planning Activities Task 3.8 – Transnational marketing plan • Month of start: February 2007 • Month of completion: April 2007 • Duration: 3 months • Elaboration of a transnational marketing plan

  13. WORK PACKAGE 3 - Planning Activities Task 3.9 – Architectural Planning . Part 3 • Month of start: May 2007 • Month of completion: August 2007 • Duration: 4 months • Architectural plan for the construction of a bicycle road in the New Atlantis Region • Implementation of visitor-friendly infrastructure in Belluno Province, Italy

  14. WORK PACKAGE 3 - Planning Activities Task 3.1 – Assessment of local cultural heritage Methodology Key Idea: Route based Approach 3.1.1 Collection of Assets relevant for cultural related tourism Coordinator: EEF in close collaboration with P3, 2.1 WP Leader Contributors: All Partners Deadline: end December 2005 Objectives: Identify Cultural Assets /Tourist related attractions & activitiesand related source and level of information Methodology: Based on results of 2.1

  15. WORK PACKAGE 3 - Planning Activities Task 3.1 – Assessment of local cultural heritage Methodology Key Idea: Route based Approach • 3.1.2 Definition of structure and common fields • Coordinator: EEF • Contributors: All Partners • Deadline: end January 2006 • Objectives: Identification/Validation of database structure & fields • Methodology: EEF proposal (based on 3.1.1) • Review by all Partners Improvement

  16. HYPERTOUR Database Churches - Fields

  17. WORK PACKAGE 3 - Planning Activities Task 3.1 – Assessment of local cultural heritage Methodology Key Idea: Route based Approach • 3.1.3 Database Prototype • Coordinator: EEF • Contributors: All Partners • Deadline: end of February 06 (Consortium Meeting in Epirus, Greece) • Objectives: Development of Database Prototype • Methodology: Development of database (ACCESS) • Presentation to Partners at CM in February 2006 Feedback from Partners Improvement

  18. EPCON Database Hotels – Database Structure

  19. WORK PACKAGE 3 - Planning Activities Task 3.1 – Assessment of local cultural heritage Methodology Key Idea: Route based Approach 3.1.4. Content Collection and Edition Coordinator: EEF Contributors: All Partners Deadline: end of March 2006 (=deliverable) Objectives: Data input Methodology: Instructions regarding data edition - EEF Collection and entry of data – All Partners

  20. EPCON Database

  21. WORK PACKAGE 3 - Planning Activities Tasks 3.2 to Tasks 3.9 Methodology to be presented at the next Consortium Meeting