120 likes | 277 Views
Solar Probe Plus FIELDS Pre-AGU Science Meeting Management 12/07/2013 Peter R. Harvey. AGENDA. [1] FIELDS status - hardware and program, iPDR , etc [ 2] Burst mode algorithms and data replay [ 3] RFS peak-tracking algorithms
E N D
Solar Probe Plus FIELDS Pre-AGU Science Meeting Management 12/07/2013 Peter R. Harvey
AGENDA [1] FIELDS status - hardware and program, iPDR, etc [2] Burst mode algorithms and data replay [3] RFS peak-tracking algorithms [4] MAG/MAG and MAG/SCM compatibility and boom accommodation [5] Dust science and measurements [6] …more science
REVIEW MANIA We PASSED all Reviews GOOD!
REVIEW MANIA .. But we accumulated a LOT of things to do!
STATUS of DELIVERABLES In October 2013
STATUS of DELIVERABLES In December 2013
FIELDS ScheduleETU I&T Milestones iCDR ETU I&T Performance Tests Full Environments FIELDS IPDR - Management