Department of Local Government & Housing Provincial Government Western Cape October 2005

PERFORMANCE REVIEW Outlook for 2005/06 Financial Year Performance/Expenditure Expenditure review 2001/02 – 2007/08. Department of Local Government & Housing Provincial Government Western Cape October 2005. OVERVIEW. A : Outlook 2005/2006. B : Expenditure review 2001 - 2008

Download Presentation

Department of Local Government & Housing Provincial Government Western Cape October 2005

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. PERFORMANCE REVIEW Outlook for 2005/06 Financial YearPerformance/Expenditure Expenditure review 2001/02 – 2007/08 Department of Local Government & Housing Provincial Government Western Cape October 2005

  2. OVERVIEW A : Outlook 2005/2006 B : Expenditure review 2001 - 2008 C : Budget planning : challenges D : Performance April - September E : Improved capacity F : Impact of new programmes

  3. A : OUTLOOK 2005/06 Department has R532m available for 2005/06 (R456m grant + R76m N2 ring fenced funds) • R180m spent April to September • 7,008 houses were built and 10,477 sites serviced by end September. • Expenditure is in line with projections to end of 2nd quarter.National department deviated from the transfer schedule and transferred extra funding in April/May • Anticipated that 16,000 houses will be built and 18,000 sites will be serviced by March 2006

  4. B: EXPENDITURE REVIEW 2001/02 – 2007/08 TRENDS 1994 to 2005 : • Houses built & under construction - 1994 – 1999 : 103,730 • Houses built & under construction - 1999 – 2004 : 89,090 • - 2004/05 : 16,965 sites were serviced, 15,921 houses provided. R511m spent. • More than of 200,000 houses have been provided in the Western Cape since 1994

  5. Trends continued • In 2001 there was a shift towards a higher quality product at an increased unit cost • In 1994 the unit cost for allowed for in the subsidy was R12,500. The current unit cost is almost R40,000. The unit cost has trebled since 1994 • Over the same period the Housing grant to the Western Cape has less than doubled, from R283m in 1994 to R456m in 2005/06 • It is therefore clear that a lower number of units are able to be produced currently due to the conditional grant not keeping pace with inflation and the improved specifications required.

  6. New policy framework • Integrated housing and human settlement development grant introduced in 2005/06 • Paradigm shift, introducing innovative new programmes which allow for varied forms of tenure. Unfortunately all new programmes need to be funded from the same grant • Number and quality of houses built will remain the primary indicator of performance, but is not the only output that will be measured in future. This will more accurately reflect the more varied nature of housing delivery options now available • Greatest challenge – housing delivery is being held back by insufficient funding

  7. C : BUDGET PLANNING • 300,000 + Western Cape backlog – Approximately 15,000 units p/a can be built within R456m allocation • Funds allocated according to needs survey in Provincial Housing Plan • Municipal need as % of Provincial need determines funds allocation • Expenditure monitored per municipality Management of housing grant involves the following :

  8. D: PERFORMANCE APRIL to SEPTEMBER • R 180m of the R 456m Grant was spent from April to September. • Upturn expected as new projects come on stream in 2nd half of year. • 10,477 sites serviced and 7,008 houses built to end Sept

  9. Actual expenditure

  10. Projected expenditure

  11. E : IMPROVED CAPACITY IN MONITORING PERFORMANCE • Department has engineers, project managers and inspectors who assesses performance of projects on a monthly basis • 3 project managers have been appointed by the department recently to boost the capacity of the team of 7 Engineers/Monitors. Cuban professionals are complementing capacity • At municipal level project managers and implementing agents have been appointed

  12. F : IMPACT OF NEW PROGRAMMES • UISP : (Upgrade of Informal Settlements Programme) New project applications withheld till 1st April, existing projects held back until conversion • Social Housing : New policy not finalised, funds only available from April 2006 • Subsidy increase effective date and implementation of new programmes leads to delivery delays. • New programs introduced with funding only available in subsequent year.

  13. New programmes cont’d • Delays due to lengthy community consultation processes • Municipal capacity (as developer) - lack of capacity especially project management • Planning - Insufficient planning in past - Province assisting in planning process

  14. Solutions : Interventions implemented and planned • Municipal capacity – Project managers appointed to assist in delivery. Capacity building programmes to up-skill staff • Planning greatly improved – Project managers and task teams within municipalities will improve this further

  15. Response to challenges • To alleviate the holding back of projects to the beginning of the financial year, the Western Cape has an approach of approving projects in phases, per financial year. • Increasing the quantum of the grant, to allow more than 15,000 houses to be built per annum, needs to be taken up at national level • Innovative ways to leverage more funding for housing are being explored.

  16. LOOKING AHEAD : SUSTAINABLE HUMAN SETTLEMENT SUMMIT • The summit will take place 24th-25th November in Stellenbosch. • The objective is to facilitate a forum for dialogue for all stakeholders related to the development of Integrated Human Settlements in alignment with the Breaking New Ground policy and Ikapa Elihlumayo. • The Summit outcome is the finalization of the strategic and implementation plan in line with new policies • Pilot projects will be launched to implement plans

  17. THANK YOU