Polarized 3He Target System • Overview • Design • Vertical Polarization • Spin-Flip • Oven/Ladder/Enclosure/Access • Laser/Optics/Cells • Polarimetry • Safety/Documents • Installation/Switch-over • Milestone, Manpower and Responsibilities
Design Progress • Progress: (Estimated >90 person-weeks 3 months ago) Completed items: • Layout for all four experiments • New vertical Helmholtz coils and support • New RF coils for vertical polarization • New oven system • Oven support in the target lab • Target collimators • Replacement support for horizontal Helmholtz coils • New cells (with side pull-offs) • Extended magnetic shielding on BigBite fringing field • Conceptual design on laser optics lines • Conceptual design on vertical Compass
Remaining Items for Design • Remaining design items: (total < 20 person-weeks) • Main support Structure Supports for Target drive, Target Collimator, new RF coils, Ref. cell Target enclosure and windows • Target ladder and pick-up coils • Laser optics lines (including EPR, spectra-analyzer) and support • Personnel access • Safety interlock • Compass mounts
Progress in the target lab • Spin-flip test (mostly complete) • RF sweep NMR on 3He works • EPR works • New support for horizontal Helmholtz coils installed • New oven and support arrived, being assembled • Two new cells manufactured and to be tested • Cell characterization (density and window) setup ready • Optical fibers and combiners ordered • 5-to-1 combiners delivered, tested and problems found
Planned tests in the target lab • Install new oven, test • Test new cells • Characterizing new cells • Test new components • Test new optics • RF sweep water calibration • Combine polarization measurements with spin-flip • Spin-flip signal to DAQ • LabView communication with EPICS
Other Components • Compass (Kentucky):Conceptual design complete complete design, manufacturing and test • Vertical coils (order placed, delivery next month): setup in new target lab, align and field mapping then move to EEL target lab, integrate with horizontal coils • Lasers:9 in hand, 2 spare diodes; new vender: narrow lasers • Cells:new contracts with Princeton/Mike Souza medium size (3”) pumping chamber, production started, two in hand, plan to produce 1 cell every two weeks W&M and UVa groups
Safety and documents • There are a number of safety aspects for the target: • Laser safety: eye, skin, fire hazard, LSOP enclosure, alignment, eyewear, training • High pressure glass cells: explosion, radiation, OSP/RWP enclosure, windows, loop around pivot area cell handling: face mask, eye and hearing protection • Reference cell system: high pressure, hydrogen • Hot Surface/fire hazard from heating • Electrical from power supplies • Magnetic field • All documents will be updated
Manpower • Designer: A. Gavalya, S. Esp (and help from others) • Students: C. Dutta (KY), J. Katich (W&M), X. Zhan (MIT), • Physicists: T. Averett (W&M, part-time), W. Korsch (KY, short-term visit), and J. P. Chen (JLab). • Postdocs: from W&M, Duke • Help from past students/postdocs. • Off-site • Cell production/testing at W&M, UVa. • Compass design/testing at Kentucky.
Responsibilities • Overall: J. P. Chen • Design: A. Gavalya/ J. P. Chen • Vertical coils, holding field, oven system, ladder, support, cell characterization, reference cell, NMR: J. Katich/T. Averett • Spin-flip, EPR: C. Dutta/W. Korsch • Optics: C. Dutta/J. P. Chen • Software/Labview, communication with EPICS: X. Zhan/B. Moffit • Compass: A. Kolarkar/W. Korsch • Fringe field: P. Brindza • Safety, documents: J. P. Chen
Installation, commissioning, switchover • Coordinate with Ed Folts for installation: 4-6 week for the target • Move to the hall, survey • Move to pivot, survey, install components, • Install optical line support, instrumentation, power cables • Checkout magnets, measure field direction/survey • Install ladder, cells, survey • Install reference cell system, cooling jets • Water calibration • Laser safety inspection, switch to 3He, laser alignment • Pumping up, check out spectra-analyzer, EPR • Commissioning: elastic 3He asymmetry (T and L) • Switchover: • change cell, water calibration • change optical line and check alignment, pump-up • EPR, temperature test
Milestones for Polarized 3He • Spin-Flip test: done • NMR/EPR system working: done, keep improvement • New oven ready for cell testing/characterization: April 1 • Vertical coils test: June 1 • Cell production: 10 by July 1, 20 by Dec. 1 • New target structure: Sept. 1 • Compass: Sept. 1 • Laser optics line: Oct. 1 • NMR FM water (optional): Oct. 1 • Complete system test: Nov. 1 • Ready for installation: Jan. 1, 2008