Presented by Ms. T. Mpotulo Department of Water Affairs and Forestry

BUCKET ERADICATION PROGRESS SELECT COMMITTEE ON LAND AND ENVIRONMENTAL AFFAIRS HEARINGS 22 & 23 February 2007. Presented by Ms. T. Mpotulo Department of Water Affairs and Forestry. PRESENTATION OUTLINE. Purpose Introduction National Perspective Backlog as of Jan 2007 Municipal perspective

Download Presentation

Presented by Ms. T. Mpotulo Department of Water Affairs and Forestry

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. BUCKET ERADICATION PROGRESSSELECT COMMITTEE ON LAND AND ENVIRONMENTAL AFFAIRS HEARINGS22 & 23 February 2007 Presented by Ms. T. Mpotulo Department of Water Affairs and Forestry

  2. PRESENTATION OUTLINE • Purpose • Introduction • National Perspective • Backlog as of Jan 2007 • Municipal perspective • Delivery “hot spots” • Spending pattern • Bucket eradication project status • Challenges • Interventions • Recommendations • Conclusion

  3. PURPOSE • Present progress • Hot Spots • Challenges • Interventions • Recommendations

  4. INTRODUCTION • February 2005 an allocation of R1.2 billion in MIG was ringfenced for Bucket eradication over MTEF period. • R200m in 2005/6 • R400m in 2006/7 • R600m in 2007/8 • Buckets confirmed were 252 254

  5. National perspective from February 2005-January 2007

  6. Backlog as of January 2007

  7. DELIVERY HOT SPOTS • Most of the remaining backlog is at 3 provinces • Free State 67% • North West 15 % • Eastern Cape 13 % • Free State in Nketoana construction of 700 VIPs brought to halt, community demands Water-borne • Eastern Cape, Emalahleni Local Municipality (Indwe and Dordrecht), 5 000 buckets to be replaced by VIPs. Community rejects VIPs and insist on water-borne.

  8. Spending pattern per province Expenditure pertains in 2 key Province’s 2006/07 Backlog Allocation Expenditure Rand Rand Eastern Cape R 23 431 R154 506 539 R 30 285 000 Free State R102 142 R145 662 562 R 78 292 381

  9. Spending Pattern see annexure A - attachment

  10. Bucket eradication project status see annexure B - attachment

  11. INTERVENTION Free State: Business Plan for Nketoana has been prepared to augment water supply to cater for water-borne sanitation. • A provincial bucket eradication summit held in Free State. • North West:- Bulk funding allocated to bucket eradication • 76 Million of unspent MIG funds allocated to bucket eradication • Dwaf deployed 21 engineers specific to bucket eradication to provide direct hands on support to WSA in planning, implementation and monitoring of programme • Siyenza Manje Programme by DBSA + SAICE- deployed engineers + compliments current interventions Eastern Cape: Chris Hani (Emalahleni) situation political sensitive- municipality planning to engage political leadership

  12. CHALLENGES • Inadequate water resource & bulk sewerage infrastructure to support waterborne sanitation • Community expectations (VIPs v/s water-borne) • Procurement processes of municipalities (take time to appoint contractors) • Unavailability of local contractors due to many infrastructure projects underway

  13. RECOMMENDATIONS • Recommend political intervention in areas where there is demand for water-borne irrespective of the availability of water. • Municipalities to prioritize the bucket eradication programme • Municipalities utilize their MIG funds to eradicate buckets or • National Treasury allocate R600m indicated as a budget fall.

  14. CONCLUSION • Municipalities are committed to eradicate buckets by December 2007 or even earlier up to January 2007. • The number of buckets removed is 149 583 out of the total 252 254 backlog confirmed in February 2005.

  15. THANK YOU