1 / 5

Tasks & Deliverables

Tasks & Deliverables. Tasks. Deliverables. 5/01: Three HB sections assigned for updating (Wind, Lightning & Radiation). 8/01: Partial initial drafts on Wind and Lightning received. 10/01: Initial draft on Radiation received.

sofia
Download Presentation

Tasks & Deliverables

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Tasks & Deliverables Tasks Deliverables 5/01: Three HB sections assigned for updating (Wind, Lightning & Radiation). 8/01: Partial initial drafts on Wind and Lightning received. 10/01: Initial draft on Radiation received. 12/01: Extremes, Clouds, Constituents, Atmospheres, Storms & Sea State (six) sections started or on-going. Other sections being researched to be tasked. Related: Space Launch & Transportation Systems (SLaTS) Chapter 7 work on natural environment interaction with launch vehicle engineering. 9/5/01: 1st Updated draft completed. 12/01: Appendix draft completed.2/11/02: Next coordination meeting. NASA TECHNICAL STANDARDS

  2. Status • Status (R|Y|G|TBD|N/A) • Cost=G • Schedule=G • Technical=G • Customer satisfaction=TBD • Issues & Resolutions • Issue: Need $60K in FY02 (in USRA Task Agreement) to stay on schedule in the update and review of Standards Terrestrial Handbook. • Resolution: To be determined by availability of resources. • $10K (CSC) & $9K 2nd Gen (USRA) funds obtained and applied. • $12K (Standards) and $10K (FY02 Institutional) funding pending. • $29K short. Will look to SLI, 2nd Gen and Shuttle. • Comments • None NASA TECHNICAL STANDARDS

  3. Schedule • Milestones • Standards HB Update: • 2/01-1/02: Literature search for state-of-the-art technology on HB sections. • 8/01-10/01: Winds (CSC), Thermal Radiation (CSC), & Atmospheric Electricity (SD) 1st initial Section drafts delivered. • 12/01: Thermal Radiation review started. • 3/02: Winds and Electricity sectional drafts to be completed. • 08/02: Extremes, Clouds, Constituents, Atmospheres, Storms & Sea State sections started. Drafts anticipated completion by 08/02. • SLaTS: • 01/01-01/02: [SLaTS] Related - Space Launch and Transportation Systems (SLATS) work, involving book chapter #7 by ED44. • 02/28/01: Initial SLaTS draft submitted. • 08/16/01: Red-lined corrections sent back. • 09/05/01: Authors meeting and presentation at MSFC. • 12/01: SLaTS Appendix A revised. • 02/02: Work continuing on chapter 7 document for 02/02 meeting. NASA TECHNICAL STANDARDS

  4. Accomplishments & Plans • January Accomplishments • Standards HB Update: • Further literature searching continued on HB sections, for update purposes. • $12K Standards Program & $10K Institutional funding indicated. • Earlier: Draft Sections Received: Partial draft: Wind (CSC/Adelfang) and Lightning (SD/Koshak). Complete draft: Radiation (CSC/Justus). • Lightning and Wind section work continuing via Ratheon (Leahy) & CSC (Smith). Work progressing in 6 other sections (Clouds, Extremes, Constituents, Atmospheric Models, Storms & Sea State). • Radiation section internal review started. • SLaTS: • SLaTS chapter 7 work resumed, after 9/5/01 SLaTS symposium. • SLaTS Appendix A revised. NASA TECHNICAL STANDARDS

  5. Accomplishments & Plans • Plans • - Standards HB Update: • Continue literature research, establish section involvement, obtain needed models/documents/etc for HB update. • Seek potential funding - needed for HB technical update & review. • Continue in determining which personnel, software, databases, etc will be needed and involved in the update of various HB sections. • Lightning & Wind section initial complete drafts due in 03/02. • Radiation section review to finish. • - SLaTS: • Continue to work SLaTS chapter 7 document for 02/02 SLaTS coordination meeting. NASA TECHNICAL STANDARDS

More Related