An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Public Information Meeting Rehabilitation of Bridge No. 00245 Flat Rock Hill Road over I-95 Old Lyme, Connecticut

  2. Bridge No. 00245

  3. CTDOT Role and Mission Bureau of Engineering and Construction • Responsible for engineering design, construction, and inspection of transportation projects Project Manager: Mr. Louis D. Bacho Contact: Ms. Mary E. Baker

  4. Close, Jensen and Miller, P.C.Consultant Liaison Engineers CTDOT has retained the firm of Close, Jensen and Miller to supervise the activities relative to the design of this bridge project. Contact: Mr. Jeffrey J. Fontaine

  5. Project Goals • Rehabilitate Bridge No. 00245 • Minimize disturbance to traveling public • Complete construction in a timely manner • Effectively use funds Address above with consideration for context sensitive design

  6. Bridge No. 00245 Elevation looking East on Interstate 95

  7. Bridge No. 00245 Elevation looking Weston Interstate 95

  8. Existing Bridge Description Bridge No. 00245 • Four-Span, Continuous Steel Multi-Girder Structure built in 1958 • Carries one lane of traffic in each direction • Estimated Average Daily Traffic (ADT) on Flat Rock Hill Road ~116 vehicles (2007) • ADT on Interstate 95 under Bridge No. 00245 ~67,900 (2009) • Structure Dimensions • Total Length = 173’ • Overall Width = 45’ 7” • Roadway Width = Originally 40’ 0” Reduced to 26’ 5” due to concrete barrier curb along Eastern side for girder protection

  9. Bridge No. 00245looking South

  10. Bridge No. 00245looking North

  11. Existing Bridge Description (cont’d) Bridge No. 00245 • Minimum Vertical Clearance over I-95 = 14’-2” • Reinforced concrete deck with concrete wearing surface • Substructure (Foundation) • Concrete abutments on steel piles • Two intermediate concrete piers and one center concrete pier on spread footings founded on bedrock

  12. Reasons for Project Structure recommended for rehabilitation under the State Bridge Program. • Structurally Deficient: • Overall Superstructure Condition Rating “4” • Jersey Barriers used to keep live loads off fascia girders • Fascia girders exhibit extensive vehicular impact damage • Girders exhibit moderate to heavy rust • Functionally Obsolete: • Minimum Vertical Clearance is Substandard

  13. Reasons for Project Fascia Girder over SB Traffic Impact damage Bearing Pads Sheared bolt due to impact damage

  14. Reasons for Project Steel Girders Rust along underside of structure Piers Light to moderate scaling, rust along underside of structure

  15. Proposed Construction • New two-span continuous multi-girder, high strength weathering steel superstructure • Increased Minimum Vertical Clearance over I-95 • Existing: 14’-2” • Proposed: 16’-3” • Deck will consist of cast-in-place reinforced concrete with membrane waterproofing and an asphaltic overlay. • Structure Dimensions • Total Length slightly increased due to abutment modifications • Match Existing Out to Out Width

  16. Proposed Construction (cont’d) • Pier Repair and Modification • Removal of Intermediate Piers • Reconstruction of Center Pier to form Pier Wall • Concrete Repairs to spalls and hollow areas • Abutments will be modified to accommodate increased loads and raised profile • Addition of heel length • Third row of steel H-piles • Minor concrete repairs to existing abutment stems

  17. Proposed Construction Bridge Elevation

  18. Stage 1 Construction

  19. Stage 2 Construction

  20. Proposed Construction Bridge Cross Section

  21. Public Utilities Utilities at the bridge site consist of aerial facilities (electric, telecommunication and cable) and a VMS cabinet located Northeast of the bridge. CTDOT has notified the appropriate utility companies of the scheduled project. Utilities will be temporarily relocated as part of the proposed construction activities.

  22. Rights-of-Way Based upon the State boundary map, the width of ROW for Interstate Route 95 at the bridge site is approximately 500 feet. No impacts to private property are anticipated. All work will be within the DOT-ROW.

  23. Project Cost The estimated construction cost for the project is approximately $5,800,000. This bridge replacement is anticipated to be undertaken using Federal and State funds.

  24. Project Schedule Construction of Bridge No. 00245 is anticipated to begin in the spring of 2013 and be completed in the fall of 2014. The schedule is preliminary and is predicated upon the availability of funding.

  25. Contact Information CTDOT Ms. Mary E. Baker 2800 Berlin Turnpike, P.O. Box 317546 Newington, Connecticut 06131-7546 (860) 594-3402 or mary.baker@ct.gov Close, Jensen and Miller, P.C. Mr. Jeffrey J. Fontaine 1137 Silas Deane Highway Wethersfield, Connecticut 06109 (860) 563-9375 or jfontaine@cjmpc.com