An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Lithuanian interconnection projects Donatas Matelionis LITGRID AB 2010-10-01

  2. Lithuanian–Swedish interconnection project NordBalt

  3. Project progress • Preparation of territorial planning documents for interconnection on land • Lithuanian and Swedish TSOs signed an agreement on implementation of investment • EC granted financial EU assistance to the project EUR 131 million from EEPR program • Baltic seabed survey works completed • Selected VSC (Voltage Source Converter) technology for interconnection • Preparation of the technical specifications for cable and converter stations • Tender for supply of cable and converter stations ongoing – bids from the supplier’s received • Analysis of proposals submitted and negotiation on the contracts • Preparation of territorial planning documents on land in Lithuania and Sweden • Land ownership issues • Preparation of technical project for interconnection • Permits and licensing issues • Construction of the interconnection • Commissioning of the interconnection

  4. LITPOL Link Key figures: • Type: • Back-to-back (in Alytus) • Length: • 154 km (Alytus – Elk) • Voltage level: • 330 kV LT • 400 kV PL • Capacity: • 2x500 MW Milestones: Commissioning 2015 (500 MW) and 2020 (1000 MW) Description: Interconnection of Lithuanian and Polish transmission grids, by building new back-to-back converter station and strengthening internal high voltage transmission grids in Poland and Lithuania. Total investment costs: €237 million

  5. LITPOL Link – current status • Investigation of Environmental Impact Assessment in Lithuania and Poland ongoing • Lithuania – due October 2010 • Poland – due August 2011. • Technical study for reconstructions in 330 kV Alytus substation, construction of BtB and 400 kV line in Lithuania under preparation (The study includes the choice of HVDC technology and preparation of technical specifications) • due December 2010.

  6. Thank you!