1 / 44

Energy Gateway Gateway West Project Gateway South Project

Energy Gateway Gateway West Project Gateway South Project . Technical Study Leads: Idaho Power (Gateway West) and PacifiCorp (Gateway South) WECC Phase 2 Study Group Kick-Off Meeting May 22, 2009 Salt Lake City, Utah. Standards of Conduct Non-Disclosure Statement.

shiloh
Download Presentation

Energy Gateway Gateway West Project Gateway South Project

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Energy GatewayGateway West Project Gateway South Project Technical Study Leads: Idaho Power (Gateway West) and PacifiCorp (Gateway South) WECC Phase 2 Study Group Kick-Off MeetingMay 22, 2009Salt Lake City, Utah

  2. Standards of Conduct Non-Disclosure Statement The following procedures have been implemented to provide Standards of Conduct Safeguards: • Ten day advance notice of public meeting • All eligible customers invited • Telephone participation provided • Handouts posted on OASIS prior to meeting • Meeting notes will be taken and posted • One eligible customer must be in attendance • Meetings no more than twice per month

  3. Our agenda for today… • Welcome • Introductions • EGW Phase 2 Study Process – PCC Presentation (April 2009) • Facility Staging • Study Area Path Interactions, Study Participants & Issues • Study Area: “Straw-man” Study Plan • Study Schedule • Q&A

  4. WECC Phase 2 Study Group Kick-Off Meeting • Welcome • Introductions

  5. WECC Phase 2 StudyGroupKick-Off Meeting • Energy Gateway Phase 2 Study Process - PCC Presentation (April 2009)

  6. Gateway West MSTI SWIP

  7. Gateway South

  8. Phase 1 Study Effort Studies were performed and reported by path Five for Gateway West Three for Gateway South Reviewing entities interested in local impacts

  9. Leverage Phase 1 Experience Perform and review studies within a local area Attach appropriate local area studies for Phase 2 reports

  10. Phase 2 Method Hold Energy Gateway review meetings Gateway West Project Review Study Group Gateway South Project Review Study Group Form five sub-area study groups

  11. Gateway West Study Areas MSTI Windstar Study Area Southern Idaho Study Area Bridger Study Area SWIP

  12. Gateway South Study Areas Aeolus South Study Area Mona South Study Area

  13. Process Flow Diagram

  14. Example Phase 2 Report Appendix C Windstar Area Study Gateway West Phase 2 Report Appendix B Bridger Area Study Appendix A Southern Idaho Area Study

  15. Energy Gateway Project • Facility Staging

  16. EGW Facility Staging • Due to the scope and nature of the EGW project, not all facilities will be constructed during the same period. • As such, facilities will be installed following a segmented approach – focusing on one leg of the project, then another leg, etc. • For example: • Populus – Terminal 345 kV #1 & #2 will be in-service 12/2010 (This project was granted Phase 3 status in 11/2008) • Pinto 345 kV series capacitor (on PNT-HNT 345 kV line) will be in-service 5/2010 • St. George (Utah) SVC will be in-Service in 5/2011

  17. EGW Facility Staging • Rather than initiate technical studies for each transmission segment, it was decided to group transmission segments into two logical project stages that would be evaluated by WECC Phase 2 study group (or sub groups). • Incremental transmission limitations for transmission segments that are added between stages, will be addressed via OTC studies. [This same process was followed by BPA and AVISTA for the West of Hatwai Expansion project.]

  18. EGW Facilities – Stage 1 (1500 MW)

  19. Gateway West – Stage 1 Facilities Hemingway - Bridger

  20. Gateway West – Stage 1 Facilities Bridger - Windstar • The current schedule calls for all Gateway West – Stage 1 facilities will be in-service by 12/2016.

  21. Gateway South – Stage 1 Facilities Aeolus – Mona – So. Nevada • The current schedule calls for all Gateway South – Stage 1 facilities will be in-service by 12/2017.

  22. EGW Facilities – Stage 2 (Full-Build, 3000 MW)

  23. Gateway West – Stage 2 Facilities Hemingway - Bridger

  24. Gateway West – Stage 2 Facilities Bridger - Windstar • The current schedule calls for all Gateway West – Stage 2 facilities will be in-service by 12/2017.

  25. Gateway South – Stage 2 Facilities Aeolus – Mona – So. Nevada • The current schedule calls for all Gateway South – Stage 2 facilities will be in-service by 12/2019.

  26. WECC Phase 2 StudyGroupKick-Off Meeting • Study Area Path Interactions, Study Participants & Study Issues

  27. Study Area Participation • Charts for each Study Areas, which indicate Area Path Interactions, (projected) Study Participants & a drawing of the facilities being evaluated, have been displayed in the meeting room. • Please take time during one of the breaks to review the information and make necessary changes or modifications. • These inputs will help us in move the Phase 2 study efforts forward.

  28. Paths Analysis Midpoint West Borah West (Path 17) Simultaneous Interactions Idaho – Northwest (Path 14) Midpoint – Summer Lake (Path 75) Boardman - Hemingway Montana – Northwest (Path 8) Path C (Path 20) Montana – Idaho (Path 18) MSTI Project SWIP (Great Basin – North, ENTP) Idaho – Sierra (Path 16) Gateway West - So. Idaho Study Area

  29. Path Analysis Bridger West (Path 19) Path C (Path 20) Aeolus West Simultaneous Interactions Aeolus South Path C (Path 20) Montana – Idaho (Path 18) Bonanza West (Path 33) Monument – Naughton (PAC Internal) RS/FH West (PAC Internal) Bridger West (Path 19) Bonanza West (Path 33) Monument – Naughton (PAC Internal) RS/FH West (PAC Internal) Aeolus South TOT 1A (Path 30) Bonanza West (33) Gateway West – Bridger Study Area

  30. Path Analysis TOT 4A (Path 37) Simultaneous Interactions Montana Southeast (Path 80) TOT 4B (Path 38) TOT 3 (Path 36) Yellowtail South TOT 1A (Path 30) Gateway West – Windstar Study Area

  31. Study Participants Basin Electric Power Cooperative Black Hills Cooperation Bonneville Power Administration, Transmission/Power Services Columbia Grid Deseret Generation & Transmission Edison Mission Energy Great Basin Transmission Group Idaho Power Company NorthWestern Energy NV Energy PacifiCorp Puget Sound Energy, Inc. TransCanada TransWest Express LLC Western Area Power Administration Western Grid Group Correspondents OPUC Avista Corp. NWPP Corporation Wyoming Public Service Commission EnTranTek LLC and Ridgeline Energy LLC Invernergy LLC Wyoming Public Service Commission Gateway West – Study Participants

  32. Other Issues GW interaction with Bridger West (PAC) Interactions between Bridger West and Path C (PAC) Wyoming Issues Evaluate interaction between GW and TOT 3 (Wyoming – Colorado); additionally GW and DJ-LRS-Ault transmission lines. (Basin Electric) Evaluate the interaction between TOT 1A path and each component of the project. (WAPA) When are SSR Studies planned for? (WAPA) Parallel to Phase 2 process, PACE will perform SSR analysis for portions of the Western Interconnection that are effected by the EGW Project. Gateway West – Study Issues

  33. Path Analysis Aeolus South Simultaneous Interactions Aeolus West Bridger West (Path 19) TOT 1A (Path 30) Bonanza West (Path 30) IPP DC Line, 2400 MW (Path 27) Intermountain – Mona (Path 28) Intermountain – Gonder (Path 29) Pavant – Gonder (Path 32) TOT 2C (Path 35) COI (Path 66) PDCI (Path 65) Gateway South – Aeolus South Study Area

  34. Path Analysis Mona South TOT 2C Simultaneous Interactions IPP DC Line, 2400 MW (Path 27) Intermountain – Mona (Path 28) Intermountain – Gonder (Path 29) Pavant – Gonder (Path 32) TOT 2C (Path 35) COI (Path 66) PDCI (Path 65) TOT 2A (Path 31) TOT 2B1/2B2 (Paths 78 & 79) IPP DC Line, 2400 MW (Path 27) Intermountain – Mona (Path 28) Intermountain – Gonder (Path 29) Pavant – Gonder (Path 32) Centennial Project (Path 81) SWIP COI (Path 66) PDCI (Path 65) Gateway South – Mona South Study Area

  35. Arizona Public Service Basin Electric Power Cooperative Black Hills Corporation Columbia Grid Deseret Generation & Transmission Idaho Power Company Los Angeles Department of Water & Power LS Power NorthWestern Energy NV Energy PacifiCorp Puget Sound Energy Southern California Edison Salt River Project TransWest Express LLC Tri-State Generation & Transmission Utah Association of Municipal Power Systems Western Area Power Administration Wasatch Wind Gateway South – Study Participants

  36. Simultaneous Interaction between each of the paths noted below and each component of the GS project, and the project as a whole at the projects max loading: Path 27 (IPPDC 2400 MW) Path 28 (Intermountain – Mona) Path 29 (Intermountain – Gonder) Interactions between existing & proposed PST’s at Crystal TOT 2C path (+/- 600 MW and +2100/-1700 MW) interaction with other paths. Staging of TOT 2C facilities Each of the SPS schemes in the report will be further refined and added to the Project POS. Continue to evaluate simultaneous interactions among components within the GS Project. Short circuit analysis to quantify impacts on existing breakers in the southern Nevada/Eldorado Valley Gateway South – LADWP Study Issues

  37. Evaluate interaction between GS and TOT 3 (Wyoming – Colorado); additionally GS and DJ-LRS-Ault transmission lines. (Basin Electric) (UPALCO-Carbon 138 kV line): TOT 1A should be monitored and interactions determined in the next phase of studies. (WAPA) When are SSR Studies planned for? (WAPA) Parallel to Phase 2 process, PACE will perform SSR analysis for portions of the Western Interconnection that are effected by the EGW Project. How will PacifiCorp determined if the Harry Allen – Mead 500 kV #2 line should be included in the GS plan-of-service. (TWE) Detailed analysis of the impacts of a new transmission line between Crystal and Mead and the Centennial Project will be evaluated during the Phase 2 studies. Is there a dependent relationship between the PacifiCorp and other project in WECC Phase 2? (TWE) Phase 1 studies demonstrated thatGateway South can achieve its ratings with or without the Great Basin North 500 kV line being constructed. Additional simultaneous analysis for other Western Interconnection paths will be performed during Phase 2 technical studies.  Gateway South – Other Study Issues

  38. WECC Phase 2 StudyGroupKick-Off Meeting • Study Area: “Straw-man” Study Plan

  39. Study Area – “Straw-man” Study Plan • Study Plan Format: • Detail for Phase 1 Analysis • 2015 HS base case • Resource Assumptions (PAC IRP & OASIS Inputs) • Project Configuration (Full-Build Option) • Study Criteria • List of Outages, etc. • Place Holder for Phase 2 Studies • Project Staging (1500 MW/3000 MW) • Study Base Cases → See Next Slide • Resource Assumptions • Stage 1 – Updated IRP, Stage 2 – Extended IRP *Being Refined* • Path Simultaneous Interactions • Issues raised by Phase 2 Study participants • Once approved, Study Plan will need to be tailored for each sub-Area

  40. Energy Gateway Base Cases

  41. WECC Phase 2 StudyGroupKick-Off Meeting • Study Schedule

  42. Study Schedule • IPC: West of Populus

  43. Study Schedule • PacifiCorp

  44. WECC Phase 2 StudyGroupKick-Off Meeting • Q&A

More Related