Olympus Programme

DESCRIPTION

Olympus Programme. Project Planning Identifying Scope of Work 9 November 2011. Aims and Objectives. The aim of this course is to provide you with a tool that can be used in any situation in which you have to identify the ‘scope of work’ for a project and how that work will be done.

1 / 16

Download Presentation

Olympus Programme

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Olympus Programme Project Planning Identifying Scope of Work 9 November 2011

  2. Aims and Objectives • The aim of this course is to provide you with a tool that can be used in any situation in which you have to identify the ‘scope of work’ for a project and how that work will be done. • It is not however, in place of your current client working practices but will add to your ability to work efficiently and effectively. • Objectives- By the end of this course you will • Understand and be able to demonstrate principles of indentifying the scope of work • Identified how you may use this knowledge in your day to day work. Olympus: Project Planning

  3. Project Planning Exercise Identify the work necessary to build this cottage Olympus: Project Planning

  4. Project Documents • Charter/Authorization • A document issued by the project initiator or sponsor. • Formally authorizes the existence of the project • Provides the project manager with authority • Scope Statement • Narrative description of the project scope • Basics for future project decisions • Confirms common understanding of project scope • Management Plan • The BARF document (bought-in, approved, realistic, formal) defines how the project is executed, monitored and controlled Olympus: Project Planning

  5. Integrated Change Control • Constraints • Scope • Schedule • Cost • Quality • Risks • Customer Satisfaction • NBIf any one of the constraints change it is necessary to measure the impact on other 5. Olympus: Project Planning

  6. Process of identifying scope of work- key actions • 1. Determine how you will do the planning – i.e. individual or team • 2. Understand the scope of the project – identify requirements • 3. Create WBS and WBS dictionary- common language • 4. Create activity list- who does what • 5. Create network diagram- scheduling plan Olympus: Project Planning

  7. Work Breakdown Structure (WBS) • The WBS is a deliverable-oriented hierarchical decomposition of the work to be executed by the project team, to accomplish the project objectives and create the required deliverables • The WBS subdivides he project work into smaller, more manageable pieces of work, with each descending level of WBS representing an increasingly detailed definition of the project work Olympus: Project Planning

  8. 3.3 Work Breakdown Structure (WBS) Project life cycle Work packages Work package Olympus: Project Planning

  9. Work Breakdown Structure (WBS) • Rules for creation of WBS • It is created with the help of the team • The first level is completed before the project is broken down further • Each level of WBS is a smaller piece of the level above • The entire project is included in each of the highest levels of the WBS • Includes only work needed to create deliverables • Followed with WBS Dictionary and Activity List Olympus: Project Planning

  10. Project Planning Exercise Create a WBS for this cottage Olympus: Project Planning

  11. WBS for cottage Olympus: Project Planning

  12. Activity Sequencing- Prioritization of work • Identifying and documenting dependencies among schedule activities • The result of activity sequencing is a network diagram 2 4 END START 1 3 5 Olympus: Project Planning

  13. Activity Sequencing- Dependencies • Finnish-to-start – an activity must finish before the successor can start • Start-to-start – an activity must start before the successor can start • Finnish-to-finish – an activity must finish before the successor can finish • Start-to-finish – an activity must start before the successor can finish (rare) Activity A Activity A Activity B Activity B Activity A Activity A Activity B Activity B Olympus: Project Planning

  14. Project Planning Exercise Create a network diagram Olympus: Project Planning

  15. Sample network diagram for cottage 1.1.1 2.1 2.2 2.3 1.1.2 1.1.3 4.2 5 3.1 3.2 3.3 3.5 1.1.4 3.4 4.1 Note start to start dependency! Olympus: Project Planning

  16. Gateway Olympus: Project Planning