  1. West Newton Street Steam System Upgrade Tom Herlihy

  2. Contents • Who We Are • Why We Are Doing The Work • What We Are Doing • Where We Are Working • When We Are Working There • Questions

  3. Creative Solutions for our Environment313,000 Veolia Personnel Delivering Sustainable Solutions in 74 Countries 2010 Revenue$16.2 billion The standard for water services 2010 Revenue$10.1 billion The standard for energy efficient solutions The only company in the worldable to cover the entire rangeof environmental services (NYSE: VE) 2010 Revenue $12.4 billion The standard for wastemanagement and resource recovery 2010 Global Revenue $46.5 billion 2010 Revenue$7.7 billion The standard for managing safeand sustainable mobility solutions

  4. Veolia Environnement North AmericaThe Standard for Integrated Environmental Management Total Revenue: Approximately $4.7 billion Total Employees: Approximately 30,000 • No.1 in municipal partnerships & industrial outsourcing • Employees: • 3,400 • Top 1-4 in various categories of waste management • Employees: • 10,000 • Owns largest portfolio of heating and cooling systems in the USA • Employees: • 625 • No.1 in U.S. surface passenger transportation • Employees: • 16,000 2010 Revenue: $1.9 Billion 2010 Revenue: $1.0 Billion 2010 Revenue: $0.4 Billion 2010 Revenue: $1.3 Billion 4

  5. Veolia Energy North AmericaOperating Sustainable Energy Systems across the Continental USA 5

  6. Boston District Energy System • 24 hour a day presence • Energy services support the following systems: • Heating • Air conditioning and refrigeration • Humidification control • Sterilization systems • Food & beverage preparation • Energy company of choice for more than 44 million square feet of commercial, institutional and governmental facilities. 6

  7. Why We Are Doing The Work • We invest in our energy infrastructure and seek continuous improvements in our networks’: • Safety • Reliability • Efficiency • Expansion joints are a critical component • Found a better alternative to existing Bellows material of some joints in the area • Approximately 130 expansion joints to be replaced • Upgrade in joint quality

  8. What We Are DoingIn Coordination with all Applicable City Agencies Dig an 8x10 excavation Break out concrete Remove the asbestos insulation Cut & weld new expansion joints X-Ray & insulate Replace concrete, backfill & pave

  9. Where We Are Working • West Newton Street Between Tremont Street and Columbus Avenue • West Newton Street & Columbus Avenue • Columbus Avenue and Southwest Corridor Path • Southwest Corridor Path and St. Botolph Street • St Botolph Street & Huntington Avenue

  10. When We Are Working 11 Tremont to Columbus June7 – July 7 West Newton & Columbus July 25 – August 9 Titus Sparrow Park June 28 – July 20 Titus Sparrow to St. Botolph July 7 – July 25 St. Botolph to Huntington Av July 15 – August 2

  11. Questions? 12