Rushern L. Baker, III County Executive

Rushern L. Baker, III County Executive. Haitham A. Hijazi Director. Project Information Meeting. Sunnyside Avenue Bridge Replacement. Agenda Exhibit Review Welcome Presentation Q/A. Beltsville Academy May 17, 2012. Sunnyside Avenue Bridge Replacement. Existing Roadway.

sezja
Download Presentation

Rushern L. Baker, III County Executive

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Rushern L. Baker, III County Executive Haitham A. Hijazi Director Project Information Meeting Sunnyside Avenue Bridge Replacement Agenda • Exhibit Review • Welcome • Presentation • Q/A Beltsville Academy May 17, 2012

  2. Sunnyside Avenue Bridge Replacement Existing Roadway

  3. Sunnyside Avenue Bridge Replacement Existing Bridge • Bridge History • - Type: single span, steel • multi-beam bridge with • a concrete deck • - Length: 37 feet • - Clear Width: 22 feet • - Built: 1946 • - Frequent flooding • - Structurally Deficient

  4. Sunnyside Avenue Bridge Replacement Existing Bridge Extensive Deterioration

  5. Sunnyside Avenue Bridge Replacement Existing Bridge Extensive Deterioration

  6. Sunnyside Avenue Bridge Replacement Proposed Bridge

  7. Sunnyside Avenue Bridge Replacement Planned Improvements Mitigate flooding Create a “Green / Complete Street” that includes shoulders, bike paths, sidewalks and street lights Create additional environmental features, including additional wetland beneath the bridge, Storm Water Management facilities

  8. Sunnyside Avenue Bridge Replacement Proposed Roadway • Mitigate flooding • Create Green / Complete Street • Create additional wetland beneath the bridge • Create Storm Water Management facilities

  9. Sunnyside Avenue Bridge Replacement Right-of-Way and Environmental Impacts Beltsville Agricultural Research Center (BARC) 2.67 Acres 0.34 Acres Fee Simple Right-of-Way • 2.67 acres Temporary Construction Easement • 0.34 acre Permanent Section 4(f) Use • 3.01 acres (2.67 acres + 0.34 acre)

  10. Sunnyside Avenue Bridge Replacement Right-of-Way and Environmental Impacts Washington Metro Area Transit Authority (WMATA) 0.21 Acre 0.11 Acre Fee Simple Right-of-Way • 0.21 acre Temporary Construction Easement • 0.11 acre

  11. Sunnyside Avenue Bridge Replacement Proposed Bridge

  12. Sunnyside Avenue Bridge Replacement Construction Stage I • Maintain traffic on existing bridge • Construct south portion of new bridge • Construct south portion of approach roadway • Relocate Utilities South Side

  13. Sunnyside Avenue Bridge Replacement Construction Stage II • Shift traffic to the new bridge • Remove the existing bridge • Construct the north portion of new bridge • Construct the north portion of approach roadway South Side North Side

  14. Sunnyside Avenue Bridge Replacement Construction Stage III • Reset the temporary barrier and shift traffic to the • final lanes of new bridge • Construct the sidewalk on the south portion of new bridge North Side South Side

  15. Sunnyside Avenue Bridge Replacement Next Steps Complete Final Design Spring 2013 Right-of-Way Acquisition Fall 2013 Advertise for Construction Fall 2013 Begin Construction Spring 2014 Total Construction Duration 18 Months

  16. Sunnyside Avenue Bridge Replacement QUESTIONS? Prince George’s County DPW&T Project Website: WWW.PRINCEGEORGESCOUNTYMD.GOV/DPWT