1 / 25

Rajiv Gandhi Grameen Vidyutikaran Yojana

Rajiv Gandhi Grameen Vidyutikaran Yojana. Goa, Gujarat , Madhya Pradesh, Maharashtra & Rajasthan. Power Sector Conclave Mumbai 14 th -15 th July2008. RAJIV GANDHI GRAMEEN VIDYUTIKARAN YOJANA. Launched in April,2005

Download Presentation

Rajiv Gandhi Grameen Vidyutikaran Yojana

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Rajiv Gandhi Grameen Vidyutikaran Yojana Goa, Gujarat , Madhya Pradesh, Maharashtra & Rajasthan Power Sector Conclave Mumbai 14th-15th July2008

  2. RAJIV GANDHI GRAMEEN VIDYUTIKARAN YOJANA • Launched in April,2005 • Initial sanction was for last two years of X Plan with capital subsidy of Rs. 5000 Crore • In the X Plan, 235 projects were sanctioned at an estimated cost of Rs. 9722 Crore • Goa is not participating in the scheme as it has achieved 100% village electrification • These projects, when completed, will ensure electrification of 68,763 un-electrified villages, intensive electrification of 1,11,936 electrified villages and provide free connections to 83.1 lakh BPL connections • Achievements as on 30th June 2008 - • Un- electrified villages: 49,272 (73.5%) • Intensive Electrification: 51,221 (45.8%) • Connections to BPL households: 27.47 Lakh (33%)

  3. Status of Rural Electrification in 2001

  4. X Plan Projects Achievements as on 30.06.08

  5. X Plan Projects Achievements as on 30.06.08

  6. X Plan Projects Achievements as on 30.06.08

  7. Achievements Implementing Agencies Wise (X Plan)

  8. Achievements Implementing Agencies Wise (X Plan)

  9. Issues: Expectations from Implementing Agencies • Delay in completion of Projects: • Projects to be completed in 24 months post sanction • All X Plan projects have crossed their schedule of completion • Project implementation to be expedited • Close monitoring of supplies & works 2. Release of BPL Connections: • Only 32.8% connections released in 4 states • Progress is very poor in M.P. (3.4%) and Maharashtra (28.9%). • Release of BPL connections to be taken up on top priority

  10. Issues: Expectations from Implementing Agencies 3. Delays in providing land for 33/11KV sub-stations – • This is one major reason towards delay in project implementation • Suitable land to be handed over to implementing agency within 3 months of award to avoid delay in energization of lines & thefts 4. Coordination of Material Supply- • Required quantities to be tied up: Poles, transformers, cables • Identification of local contractors • Enhancement of capacity of local industry for pole manufacturing

  11. Issues: Expectations from Implementing Agencies 5.Delay in energization of village – Big gap between number of villages where work completed and villages energized • Safety inspection to be arranged immediately on completion of work and village energized • Authorise Discom officers for safety inspection as in Chattisgarh • Administrative action to stop theft of material 6. Delay in issue of Panchayat certificates – • Rajasthan – Work completed: 1,631 villages, Certificates: 793 villages • M.P. - Work completed: 16 villages, Certificates: Nil • Certificate to be arranged immediately after completion of work

  12. Issues: Expectations from Implementing Agencies 7. Delay in taking over of physical assets by state utilities - • Assets should be taken over within 15 days of completion of work 8. Quality of Material & Inspection – • Third party inspection for X Plan projects • Three-Tier Quality mechanism for XI Plan projects

  13. Issues: Expectations from Implementing Agencies 9.Establishment of Franchisee in RGGVY Village – • None of the village electrified under RGGVY franchised so far • Participation in Franchisee training programme from Rajasthan is poor (only 1 so far) • Franchisee should be in place at the time of energization • Active participation in franchisee training programmes required. 10. Correctness of data- • The data submitted by States to different agencies do not match • States to coordinate with CEA to freeze the data i.r.o. un-electrified villages • States to submit authenticated data on RGGVY to REC • States to submit data through web based MIS

  14. Status of Un-Electrified Villages ?What is the programme of electrification of the villages at colmn 6 ? Are these villages became un-electrified as per new definition ? Are these villages being electrified under intensive electrification ? Why Madhya Pradesh have high figures of UEV in RE Plan

  15. Issues: Expectations from Implementing Agencies • Notification of RE Plan – • Only Gujarat & Maharashtra have finalized • MoP circulated sample RE Plan • M.P. draft RE Plan commented by MoP • M.P. and Rajasthan to submit their final/draft RE Plans • States to finalize before August ‘08 12. Fixing of RGGVY Boards – Few boards installed in Rajasthan • Boards to be fixed in all un-electrified villages (nil in Gujarat & Maharashtra, M.P.:115), where work has been completed or under progress

  16. Issues: Expectations from Implementing Agencies 13. New service connections to APL households – No connection in Gujarat & M.P. • Utilities to release APL connections simultaneously • Utilities to arrange awareness campaigns 14.Regular meetings of State Coordination Committee headed by Chief Secretary - • State to arrange monthly meetings to sort out state level & inter-departmental issues 15. Regular meetings of District Committee - • Utilities to arrange regular meetings to review progress and to sort out local problems

  17. XI Plan Projects

  18. Implementing Agencies XI Plan Projects

  19. Conditions for RGGVY in XI Plan RGGVY • States to ensure minimum daily supply of 6 to 8 hours of electricity in the RGGVY network. • Deployment of franchisees is mandatory for the management of rural distribution in projects financed under the scheme. • States to give assurance of meeting any financial deficit in this context by supplying electricity at subsidized tariff • Three-Tier Quality Monitoring Mechanism introduced to be adopted to ensure quality of material & implementation. • The states to notify their Rural Electrification Plans in 6 months (Aug. ’08)

  20. New Initiatives • For effective implementation and better monitoring of the RGGVY projects sanctioned in XI Plan, all the implementing agencies have to adopt following procedures • Adoption of Three-tier Quality Monitoring Mechanism : RGGVY Quality Manual finalized & released • Web-based Monitoring • Milestone based monitoring system • Electronic fund transfer up to contractor level • Constitution of State Level Coordination Committees headed by Chief Secretary to resolve state level and inter-departmental issues • Activation of district level committees for review of rural electrification

  21. RGGVY- Three Tier Quality Control Mechanism • 1% villages randomly selected • At least one new & augmented Substations each • 100% verification of BPL connections in 0.5% villages and 5 connections in other inspected villages TIER-III NQM (National Quality Monitor)‏ MOP • Minimum one inspection of major material • 10% villages randomly selected • At least one new & augmented Substations each • 100% verification of BPL connections in 2.5% villages and 5 connections in other inspected villages TIER-II RQCC (REC Quality Control Coordinator)‏ REC • 10% randomly selected materials • 50% villages randomly selected • All new & 50% augmented Substations • 100% verification of BPL connections in 5% villages and 5 connections in other inspected villages TIER-I 3rd Party Appointed by Implementing Agency Implementing Agency • All materials as per MQP/ Drawings • All villages & Substations as per FQP • 100% verification of BPL connections Turnkey Contractors

  22. Milestone Based Project Monitoring Preparation for Franchisee 15 M 3 M Release of BPL Connections Hand Over BPL List 6 M 2nd Inst. Fund# 3rd Inst. Fund* S/S construction Hand Over S/S Land 6 M Material Insp. By RQM Franchisee Establishment Material Orders by EPC 12 M Material Supply Comp. Project Sanction 3 M 3 M Award Material Supply 1st Inst. Fund 6 M 12 M Material Inspection Project Comp. Survey Comp. Equipment Erection 4 M Hiring of TPIA 1st Stage 2nd Stage Site Inspections Site Insp. By RQM Site Insp. By RQM # After commencement of material supply & Pole erection *After supply of 75% material & completion of minimum 10% Villages

  23. Web based Monitoring System for RGGVY • Monitoring of works up to Village level • Status of quality Inspections • Status of fund utilization • Status of village energization & taking over • Status of Panchayat certificate • The implementing Agencies to provide all these data through web based monitoring system • Workshop for hands-on experience held at REC on 6th June ‘08

  24. State Level Coordination Committee • The Committee Chaired by Chief Secretary to review status and resolve matters related to: • Issue of NITs and placement of awards • To identify sufficient number of contractors within the state/outside the state to avoid delays • Coordination among various suppliers and agencies involved to avoid delay in supply of material • Coordination with the forest department is required for early forest clearances • Identification & allotment of suitable land for substations • Release of BPL list • Energization of lines to avoid theft of material • Installation of franchisees • Supply of minimum 6 to 8 hours power supply to RGGVY villages

  25. THANK YOU

More Related