New Wednesday meeting cycle. 9.11 AD&I biweekly 16.11 SCRF ML meeting monthly 23.11 AD&I biweekly 30.11 (Free slot) monthly 7.12 AD&I 14.12 …. Two meetings per month for AD&I team. TDR related work: design (& cost) work documentation (EDMS) TDR writing (coming soon!). Today.

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about 'New Wednesday meeting cycle' - sawyer-holcomb


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
new wednesday meeting cycle
New Wednesday meeting cycle
  • 9.11 AD&I biweekly
  • 16.11 SCRF ML meeting monthly
  • 23.11 AD&I biweekly
  • 30.11 (Free slot) monthly
  • 7.12 AD&I
  • 14.12 …
  • Two meetings per month for AD&I team.
  • TDR related work:
  • design (& cost) work
  • documentation (EDMS)
  • TDR writing (coming soon!)
today
Today
  • Review DESY BTR meeting summary
    • Sent to AD&I mailing list 01.11.11
  • Action item list (for today)
    • status
  • Agenda for next meeting (23.11)
baseline decisions
Baseline Decisions
  • Retain a two-stage bunch compressor
  • Reduced field Flux Concentrator for e+ source
  • 500 MV s-band linac for auxiliary positron source
  • Include e+/e- production overhead (margin) in specification for RF
  • HLRF system for 5 GeV Boosters RDR/DRFS
  • Adjustment of the damping ring transfer lines (Central Region)
  • Physics related instrumentation accepted as proposed.
  • BDS/FFS length fixed at current length
other issues discussed
Other issues discussed
  • Global timing
    • Finalisation of path length for TDR
    • Understand construction tolerance (survey)
    • Location (and design) of adjustment chicane
    • Final path lengths not known until after KEK BTR (Jan 2012).
  • Operations and commissioning
    • Understand strategy and use of beam dumps
      • desired rating etc.
    • Understand scope of use of aux. positron source
action items 4 11 11
Action Items (4.11.11)
  • Prepare detailed design change document for PLTR, PRTL, ELTR, PRTL
    • Palmer, Paterson
    • Friday 4.11
  • Prepare central region cartoon indicating updated beamline and dump locations
    • Walker, List, Palmer
    • Friday 4.11

Draft document complete 

(Report from Palmer/List)

action items for today 1
Action Items (for today) #1
  • Update top-level parameters
    • Make Dp/p consistent with two-stage compressor and FC undulator parameters
      • Walker, List, Gai -> try for end of next week!
    • Include shifted waist enhancement in luminosities
      • Walker [Meeting tomorrow with T. Hartin → next week].
action items for today 2
Action Items (for today) #2
  • Update machine parameters
    • Consolidate/update compressor parameters for two-stage system
      • Solyak
    • Consolidate positron source parameters for 3.2 T Flux Concentrator
      • Gai
    • Update/confirm Damping Ring acceptance parameters
      • Guiducci, Palmer, Gai -> Review Wanming’s design parameters
    • Review and update source RF parameters (gradient etc.)
      • Walker, Gai, Sheppard -> send proposal tomorrow
action items for today 3
Action Items (for today) #3
  • Lattice design work
    • Propose remaining treaty points:
      • e- ML to e+ source – End of MPS collimator section
      • e+ ML to e+ BDS – End of MPS collimator section
        • Walker, List
  • Conceptual layout of Aux. source (CFS requirements)
    • Gai, Kuriki
  • CFS: Detector hall layout – finalise numbers of shafts and overall layout, support tunnel
    • mid December for CERN/FNAL like sites.
  • Include installation in commissioning group?
  • Meeting to discuss service tunnel layout (soon)
next adi meetings tentative
Next ADI meetings (tentative)
  • 23.11.11
    • Review action item status
    • Review progress on lattice design work
      • note: freeze due 30.11
    • TDR writing assignments and schedule
  • 7.12.11
    • Review action item status
    • CFS update to central region drawings, service tunnel etc.
    • TeV upgrade status (parameters)