MORAY COUNCIL - ROADS MAINTENANCE WINTER SERVICE. ARRANGEMENTS WITH FARMERS & CONTRACTORS. Bill Ross, Road Maintenance Manager, Moray Council. Moray Council – Winter Service. Historical Arrangements with farmers Pre 1974 Banff and Moray County Councils 1974 – 1996 Grampian Regional Council

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about 'MORAY COUNCIL - ROADS MAINTENANCE WINTER SERVICE' - sandro


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
Moray council roads maintenance winter service l.jpg

MORAY COUNCIL - ROADS MAINTENANCEWINTER SERVICE

ARRANGEMENTS WITH FARMERS & CONTRACTORS

Bill Ross, Road Maintenance Manager, Moray Council


Moray council winter service l.jpg
Moray Council – Winter Service

  • Historical Arrangements with farmers

    • Pre 1974 Banff and Moray County Councils

    • 1974 – 1996 Grampian Regional Council

    • 1996 – 2011 Moray Council


Slide3 l.jpg

Moray Council – Winter Service

  • Since 1996 Moray Council have steadily increased the number of farmers (and contractors) under contract and we currently have 34 such contracts in place with plans to increase this further.

  • Contractual arrangements.

    • 34 contracts .

    • Plans to increase this further.

  • Contracts evolved as needed.

  • Father to son.

  • Limited gritting service.

  • However the need to comply with European procurement policies means that we may need to review how farmers are selected in future.


Arrangements l.jpg

Moray Council – Winter Service generation to generation or are awarded to farmers who have been specifically selected in an area on an as-need basis.

Arrangements

  • Contracts clearly identify the terms and conditions including such issues as hourly hire rates, insurances, licensing of vehicles, maintenance of ploughs, lines of communications and method of payment. Maps are provided to the farmers detailing the minor local roads in their areas for which they are responsible.

  • Contracts clearly indentify the terms and conditions.

  • Route maps provided.


Slide5 l.jpg

Moray Council – Winter Service generation to generation or are awarded to farmers who have been specifically selected in an area on an as-need basis.

  • Farmers Routes


Slide6 l.jpg

Moray Council – Winter Service generation to generation or are awarded to farmers who have been specifically selected in an area on an as-need basis.

  • Farmers directed by Duty Supervisor.

  • Strong element of trust.

  • Specification not too prescriptive.


Arrangements7 l.jpg

Moray Council – Winter Service generation to generation or are awarded to farmers who have been specifically selected in an area on an as-need basis.

Arrangements

  • Rates fixed by the Council.

  • Generally based on Ringlink (Scotland) Ltd.

  • 2011/12 - £21.00/hour to £28.50/hour (150 H.P.) Larger tractors even higher.


Slide8 l.jpg

Moray Council – Winter Service generation to generation or are awarded to farmers who have been specifically selected in an area on an as-need basis.

  • Public appreciate the service.

  • Mostly local farmers working locally.

  • Otherwise compacted to ice before Council get through


Slide9 l.jpg

Moray Council – Winter Service generation to generation or are awarded to farmers who have been specifically selected in an area on an as-need basis.

  • Many farmers contract machinery nowadays.

  • Biggest tractors supplied by agricultural contractors.


Slide10 l.jpg

Moray Council – Winter Service generation to generation or are awarded to farmers who have been specifically selected in an area on an as-need basis.

Health and Safety issues?


Arrangements11 l.jpg

Moray Council – Winter Service generation to generation or are awarded to farmers who have been specifically selected in an area on an as-need basis.

Arrangements

  • In addition, during the recent severe winters, offers were also made by Forest Enterprise to carry out snow clearing on certain rural roads free of charge. This offer has been readily accepted and is mutually beneficial as it allows forestry contractors and their hauliers to continue operating in some areas even in severe conditions. A formal agreement with Forest Enterprise has been put in place which allows this arrangement to continue should the need arise again.

  • Arrangement with The Forestry Commission.

  • Arrangement with The Lecht Ski Centre


Arrangements12 l.jpg

Moray Council – Winter Service generation to generation or are awarded to farmers who have been specifically selected in an area on an as-need basis.

Arrangements

  • The cost benefit is clearly positive.

  • There are clear benefits to farmers and contractors clearing minor roads first thing in the morning, before other traffic starts to compact snow into ice.

  • Average expenditure on farmers is approximately £30k p.a. out of a total annual spend of over £2million.


Slide13 l.jpg

Moray Council – Winter Service generation to generation or are awarded to farmers who have been specifically selected in an area on an as-need basis.

  • Arrangements work well and have grown over time.

  • However EU procurement procedures to be considered?


Slide14 l.jpg

Moray Council – Winter Service generation to generation or are awarded to farmers who have been specifically selected in an area on an as-need basis.

  • Uplifting of snow from urban roads and footways.

  • When to do it?

  • During January 2010, 19 local contractors employed along with council resources at a cost £250k.


Arrangements15 l.jpg

Moray Council – Winter Service generation to generation or are awarded to farmers who have been specifically selected in an area on an as-need basis.

Arrangements

  • Excluding the last two severe winters the expenditure on farmers has averaged around £30k p.a. which, from an average total Winter spend of over £2m, is considered to be good value for money. ****(Check spend over last few years)

  • Where do you put it?

    • SEPA involvement?

  • Need for pre-arranged plans, risk assessments and plant hire contracts.


Any questions l.jpg
Any Questions? generation to generation or are awarded to farmers who have been specifically selected in an area on an as-need basis.