1 / 46

Update on ALICE background and TDI pressure

Update on ALICE background and TDI pressure . A. Alici (INFN), A. Di Mauro (CERN) LBS #40, 17/09/2012. Introduction.

sana
Download Presentation

Update on ALICE background and TDI pressure

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Update on ALICE background and TDI pressure A. Alici (INFN), A. Di Mauro (CERN) LBS #40, 17/09/2012

  2. Introduction • Since July 27 a new injection sequence (fill B1 and B2 up to ~1.0E14 p, then pause B2 and complete B1) has been adopted to mitigate vacuum degradation in TDI.4L2. This choice was driven by the observation that: • above ~ 1E14 p in both beams the pressure increases until the opening of the jaws at the end of B1 injection; • the larger the P increase during injection the longer the recovery time is. • That injection procedure allowed to minimize the pressure spikes observed in TDI at the end of injection; it worked in a large fraction of the fills. However, since ~ Aug 12 (after the increase of bunch charge) a new behavior of TDI pressure has been observed: the decrease after the initial spike is suddenly followed by a large pressure bump which can last several hours. • Since Sept 4 the separated injection of first B1 followed by B2 is under test to minimize the duration of B1 injection. • As a reminder, ALICE cannot ramp up most of gaseous detectors when the TDI P is larger than ~ 3E-8 mbar, corresponding to bkgd contamination up to 50% (depending on luminosity); ideal operating conditions would be P < 7E-9 mbar LBS#40

  3. TDI P overview in August step in beam intensity LBS#40

  4. TDI P overview in August step in beam intensity 3E-8 Monotonous decrease after initial spike Bump following decrease LBS#40

  5. TDI P overview in August 3E-8 Large P bump , most of fill duration TDI P > 3E-8 mbar LBS#40

  6. FILL 2984 before RAMP Last injections of B1 delayed, some P increase LBS#40

  7. FILL 2984 P bump after initial decrease: 6 h lost LBS#40

  8. FILL 2991 before RAMP Another example of not perfect “modified injection” LBS#40

  9. FILL 2991 P bump after initial decrease: 4 h lost LBS#40

  10. FILL 2992 before RAMP A nice injection example, P ~ 3E-8 mbar LBS#40

  11. FILL 2992 Very limited P bump LBS#40

  12. FILL 2997 before RAMP Last injections of B1 delayed, some P increase LBS#40

  13. FILL 2997 Large P bump: 6 h, no data taking at all LBS#40

  14. FILL 3002 before RAMP A good example of modified injection, P ~ 3E-8 mbar LBS#40

  15. FILL 3002 Very limited P bump As in FILL 2992, if P after injection is below 3E-8 mbar the P bump does not exceed this value LBS#40

  16. FILL 3009 before RAMP When injecting only B1 P stays below ~ 2 E-8 mbar -> test B1 and B2 separated injections LBS#40

  17. TDI P overview in September Since 04/09: B1 injected before B2 3E-8 TDI P almost always below 3E-8 mbar, shorter recovery time but exceptions are always possible LBS#40

  18. FILL 3027 before RAMP LBS#40

  19. FILL 3027 Start data taking at SB declaration !! LBS#40

  20. FILL 3032 before RAMP LBS#40

  21. FILL 3032 LBS#40

  22. TDI P “cumulative” effect How to explain the exceptions…. FILL 3035 FILL 3034 FILL 3036 When interval between subsequent fills is short, TDI P cannot recover and adds to next fill P LBS#40

  23. FILL 3035 before ramp 6E-8! P already above 1E-8 mbar Some hesitations during B1 injection LBS#40

  24. FILL 3036 before ramp 5E-8! P already at ~2E-8 mbar Nice injection but… LBS#40

  25. FILL 3071 before ramp P starts increasing when both beams are above 1e14 p LBS#40

  26. FILL 3071 LBS#40

  27. Overall vacuum in August TDI ID800 VGPB.120 VGPB.623 Left LSS2 Right LSS2, good vacuum condition VGPB.623 ID800 VGPB.120 After polarity reversal ID800 vacuum improved a lot LBS#40

  28. Overall vacuum in September TDI ID800 VGPB.120 VGPB.623 Left LSS2 Right LSS2, good vacuum condition VGPB.623 ID800 VGPB.120 LBS#40

  29. L-side vacuum FILL 2981 FILL 2976 TDI drives pressure in close sections (ID800, VGPB.120) LBS#40

  30. L-side vacuum FILL 2984 FILL 2983 TDI drives pressure in close sections (ID800, VGPB.120) LBS#40

  31. TDI Position Sensors: LVDT • One LVDT on each side of the support bar allows to detect deformation Beam 900 mm 2200 mm 900 mm DOWN UP Jaw 2 1 2 1 Motor Motor From C. Bracco’s slides at MPP, 14/09/12 LBS#40

  32. TDI Position Sensors: LVDT • One LVDT on each side of the support bar allows to detect deformation Beam 900 mm 2200 mm 900 mm Jaw DOWN UP 2 1 2 1 Motor Motor Junction which allows for some expansion without deformation From C. Bracco’s slides at MPP, 14/09/12 LBS#40

  33. FILL 2505 I~ 8.3E13 p, TDI P <1E-8 mbar, LVDT variation ~ 10um LBS#40

  34. FILL 3021 I~ 2.1E14 p, TDI P ~4E-8 mbar, LVDT variation ~ 12um LBS#40

  35. FILL 3036 I~ 2.1E14 p, TDI P ~5E-8 mbar, LVDT variation ~ 13um LBS#40

  36. Offline checks: BkgdvsLumi Run 186003, 01/08/2012 BG/ALL ~ 0.13 (L = 1.6 Hz/cm2) BG/((ALL-BG)*L0/L + BG) ~ 0.2 normalized at L0 = 1Hz/cm2 beam-bkgd side A (Left) beam-bkgd side C (Right) LBS#40

  37. Offline checks: BkgdvsLumi Run 188025, 09/09/2012 BG/ALL ~ 0.53 (L = 0.36 Hz/cm2) BG/((ALL-BG)*L0/L + BG) ~ 0.29 normalized at L0 = 1Hz/cm2 beam-bkgd side A (Left) beam-bkgd side C (Right) LBS#40

  38. Offline checks: BkgdvsLumi Run 188028, 09/09/2012 BG/ALL ~ 0.5 (L = 0.21 Hz/cm2) BG/((ALL-BG)*L0/L + BG) ~ 0.17 normalized at L0 = 1Hz/cm2 beam-bkgd side A (Left) beam-bkgd side C (Right) LBS#40

  39. ALICE luminosity in Jul-Aug ALICE Online Integrated luminosity in 2012 = 2.75 pb-1 recorded luminosity = 1.95 pb-1 (71%) July luminosity issues August new injection procedure since 26/07 31 32 33 34 35 week 35 0.11 pb-1 delivered 0.08 pb-1 recorded e = 72% week 34 0.2 pb-1 delivered 0.15 pb-1 recorded e = 75% week 32 0.08 pb-1 delivered 0.06 pb-1 recorded e = 78% week 33 0.06 pb-1 delivered 0.04 pb-1 recorded e = 58% week 31 0.41 pb-1 delivered 0.21 pb-1 recorded e = 50% LBS#40

  40. ALICE luminosity in Jul-Aug lumi scans again low luminosity, maybe due to abort gap cleaning fill 2929 (8/08) ALICE target luminosity Since the 8th of August and for more than 10 days LHC was not able to deliver to ALICE luminosities higher than 0.6Hz/cm2.The reason: very poor satellite population . LBS#40

  41. Conclusions • Separated injection of B1 and B2 allows to mitigate vacuum degradation in TDI • TDI P large bumps still observed when injection is longer • Correlation with heating (jaws deformation) to be further studied • After ALICE magnets polarity reversal (and increase of crossing angle) P spikes in ID800.R2 disappeared • Incidence of bkgd on quality of data taking is clearly also related to the delivered luminosity LBS#40

  42. BACKUP SLIDES LBS#40

  43. ALICE vacuum layout A C A side 70 m 69.7 m VGPB.623.4L2 VGI.500.4L2 120m C side 70 m 69.7 m VGPB.623.4R2 VGI.500.4R2 120m LBS#40 43

  44. ALICE layout Beam 1 BCM-A 8 sensors z = + 6 m, r = 10 cm Beam 2 BCM C 7 sensors z = -18.5 m, r=10 cm LBS#40 44

  45. The V0 detector ITS V0A rin=8 cm rout=100 cm V0C rin=8 cm rout= 76 cm SPD V0C V0A 340 cm 90 cm Two arrays of scintillator counters (V0A and V0C). Time spectra allow beam-gas events rejection LBS#40 45

  46. V0 timing properties V0A V0C IP beam2 beam1 340cm ~11.3ns 90cm ~3ns V0A+V0C ≈ 14.3ns V0A-V0C ≈ 8.3ns collisions IP beam1 Beam background from beam2 ~-11.3ns ~3ns V0A+V0C ≈ -8.3ns V0A-V0C ≈ -14.3ns Bkgd1 (BGA) Beam background from beam1 IP satellites beam2 ~11.3ns ~-3ns V0A+V0C ≈ 8.3ns V0A-V0C ≈ 14.3ns Bkgd2 (BGC) LBS#40

More Related