AE Senior Thesis 2010 Buffalo State College Science Building – Phase 1

Loading in 2 Seconds...

play fullscreen
1 / 18

AE Senior Thesis 2010 Buffalo State College Science Building – Phase 1 - PowerPoint PPT Presentation


  • 96 Views
  • Uploaded on

AE Senior Thesis 2010 Buffalo State College Science Building – Phase 1 Marie Ostrowski - Lighting/Electrical - April 14, 2010. INTRODUCTION. Project Overview College within the State University of New York system School of Natural and Social Sciences

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about 'AE Senior Thesis 2010 Buffalo State College Science Building – Phase 1' - sana


Download Now An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
slide1

AE Senior Thesis2010

Buffalo State CollegeScience Building – Phase 1

Marie Ostrowski - Lighting/Electrical - April 14, 2010

slide2

INTRODUCTION

  • Project Overview
  • College within the State University of New York system
    • School of Natural and Social Sciences
  • New Science Building Phase 1 Addition - 96,000 ft2
  • Introduction & Project Overview
  • Lighting Depth
    • Working Space
    • FacadeAtrium
  • Daylighting (MAE)
  • Acoustical Breadth
  • LED Study (Honors)
  • Electrical Depth
  • Project Summary
  • Criteria:
    • Maintain Architect’s theme + Design Intent
    • Establish energy consumption/savings
    • Evaluate alternative motor controller arrangement

Buffalo State College

BSC Campus

source: www.maps.google.com

N

Courtesy of Cannon Design

source: www.buffalostate.edu

slide3

LIGHTING DEPTH

pts

  • Introduction & Project Overview
  • Lighting Depth
    • Working Space
    • FacadeAtrium
  • Daylighting (MAE)
  • Acoustical Breadth
  • LED Study (Honors)
  • Electrical Depth
  • Project Summary

Director’s Office *

Genetics Teaching Lab

Facade

Atrium

*Not presented

slide4

LIGHTING DEPTH – WORKING SPACE

GENETICS TEACHING LAB

F13

F14

F15

F16

F17

  • Introduction & Project Overview
  • Lighting Depth
    • Working Space
    • FacadeAtrium
  • Daylighting (MAE)
  • Acoustical Breadth
  • LED Study (Honors)
  • Electrical Depth
  • Project Summary
  • Goals
    • Flexible, efficient space
  • Criteria
    • LPD ≤ 1.4 W/ft2
    • 50 fc at task plane (36”)
    • Uniformity at Task Surfaces
  • Materials:

Furniture

Flooring

Walls

Ceiling

slide5

LIGHTING DEPTH – WORKING SPACE

2)

1 )

  • Introduction & Project Overview
  • Lighting Depth
    • Working Space
    • FacadeAtrium
  • Daylighting (MAE)
  • Acoustical Breadth
  • LED Study (Honors)
  • Electrical Depth
  • Project Summary
  • Performance:
    • LPD = 1.29W/ft2
    • Maximum ceiling luminance = 550 cd/m2

2 )

3)

2 ) Average Illuminance: 33.75 fcSwitched Ambient, Board + Perimeter On

3) Average Illuminance: 22.98 fcSwitched Ambient, Board On

Average Illuminance: 52.64 fcAll ambient and perimeter on

slide6

LIGHTING DEPTH – OUTDOOR SPACE

FACADE

L1 F11 F12

  • Introduction & Project Overview
  • Lighting Depth
    • Working Space
    • FacadeAtrium
  • Daylighting (MAE)
  • Acoustical Breadth
  • LED Study (Honors)
  • Electrical Depth
  • Project Summary
  • Goals
    • Expose interior corridor walls, create depth with varying light levels
  • Criteria
    • LPD :
      • 30 W/lin. Ft. (Entrance)
      • 1 W/lin. Ft. (Walkway)
  • 0.2 W/sq. ft (Façade)
    • 5fc at the entrance and walkway
  • Materials:
    • Alternating aluminum and clear glass panels
slide7

LIGHTING DEPTH – OUTDOOR SPACE

  • Introduction & Project Overview
  • Lighting Depth
    • Working Space
    • FacadeAtrium
  • Daylighting (MAE)
  • Acoustical Breadth
  • LED Study (Honors)
  • Electrical Depth
  • Project Summary
  • Performance:
    • LPD complies with 26W to spare considering the 5% unrestricted allowance
  • Average walkway illuminance 3.7fc
slide8

LIGHTING DEPTH – ATRIUM

atrium

F6 F7 F8 M1

  • Introduction & Project Overview
  • Lighting Depth
    • Working Space
    • FacadeAtrium
  • Daylighting (MAE)
  • Acoustical Breadth
  • LED Study (Honors)
  • Electrical Depth
  • Project Summary
  • Goals
    • Highlight height of space, create a sense of movement, mimic rectilinear geometries
  • Criteria
    • LPD :
      • 0.6 W/ft2 (Level 1)
      • 0.5 W/ft2 (Level 2 + 3)
    • Horizontal Illuminance: 10fc
  • Materials:

A

B

A

B

Existing Walls

Corridor Walls

Ceiling

Floor/Accent Wall

slide9

LIGHTING DEPTH – ATRIUM

atrium

F6 F7 F8 M1

  • Introduction & Project Overview
  • Lighting Depth
    • Working Space
    • FacadeAtrium
  • Daylighting (MAE)
  • Acoustical Breadth
  • LED Study (Honors)
  • Electrical Depth
  • Project Summary
  • Goals
    • Highlight height of space, create a sense of movement, mimic rectilinear geometries
  • Criteria
    • LPD :
      • 0.6 W/ft2 (Level 1)
      • 0.5 W/ft2 (Level 2 + 3)
    • Horizontal Illuminance: 10fc
  • Materials:

A

B

A

B

Existing Walls

Corridor Walls

Ceiling

Floor/Accent Wall

slide10

LIGHTING DEPTH – ATRIUM

atrium

F6 F7 F8 M1

  • Introduction & Project Overview
  • Lighting Depth
    • Working Space
    • FacadeAtrium
  • Daylighting (MAE)
  • Acoustical Breadth
  • LED Study (Honors)
  • Electrical Depth
  • Project Summary
  • Goals
    • Highlight height of space, create a sense of movement, mimic rectilinear geometries
  • Criteria
    • LPD :
      • 0.6 W/ft2 (Level 1)
      • 0.5 W/ft2 (Level 2 + 3)
    • Horizontal Illuminance: 10fc
  • Materials:

A

B

A

B

Existing Walls

Corridor Walls

Ceiling

Floor/Accent Wall

slide11

LIGHTING DEPTH – ATRIUM

  • Introduction & Project Overview
  • Lighting Depth
    • Working Space
    • FacadeAtrium
  • Daylighting (MAE)
  • Acoustical Breadth
  • LED Study (Honors)
  • Electrical Depth
  • Project Summary
  • Performance:
    • LPD
      • Level One = 0.62
      • Level Two = 0.28
      • Level Three = 0.35
    • Complies Overall
  • Average Illuminance
    • One: 12.84 fc
    • Two: 12.54 fc
    • Three: 18.67 fc
slide12

DAYLIGHTING

EXISTING SYSTEMS

Available Daylight

  • Introduction & Project Overview
  • Lighting Depth
    • Working Space
    • FacadeAtrium
  • Daylighting (MAE)
  • Acoustical Breadth
  • LED Study (Honors)
  • Electrical Depth
  • Project Summary
slide13

DAYLIGHTING

  • Proposed redesign
    • Electric Light Integration
    • - Open Loop Switching
    • - Three Zones
    • Energy Savings Summary
  • Introduction & Project Overview
  • Lighting Depth
    • Working Space
    • FacadeAtrium
  • Daylighting (MAE)
  • Acoustical Breadth
  • LED Study (Honors)
  • Electrical Depth
  • Project Summary
slide14

ACOUSTICAL BREADTH

  • ACOUSTICS
  • Carpeting vs. Tile Flooring
    • Existing
    • Level One Replaced w/ Carpeting
    • All Atrium Flooring Replaced w/ Carpeting
  • Comparison at 1,000 Hz
  • Target Range: 1.3-1.9 s
  • Results:
    • RT = 1.75
    • RT = 1.36
    • RT = 1.16
  • Introduction & Project Overview
  • Lighting Depth
    • Working Space
    • FacadeAtrium
  • Daylighting (MAE)
  • Acoustical Breadth
  • LED Study (Honors)
  • Electrical Depth
  • Project Summary
slide15

LED STUDY

LED Luminaire Options

  • Introduction & Project Overview
  • Lighting Depth
    • Working Space
    • FacadeAtrium
  • Daylighting (MAE)
  • Acoustical Breadth
  • LED Study (Honors)
  • Electrical Depth
  • Project Summary
  • 21 luminaires arranged perpendicular to tables
  • 2) 16 luminaires parallel and in between lab tables

Scenario 1

Scenario 2

Average Illuminance: 44.4 fc

Payback Period: 16 years

Average Illuminance: 41.5 fc

Payback Period: 7 years

slide16

ELECTRICAL DEPTH

  • Motor Controller Center Design
  • Existing Distribution
  • Direct Replacement: Motor Loads = 2867.9 A
  • Removing Chillers: Motor Loads = 1341.9 A
    • -reduces size of incoming feeder bus
  • Introduction & Project Overview
  • Lighting Depth
    • Working Space
    • FacadeAtrium
  • Daylighting (MAE)
  • Acoustical Breadth
  • LED Study (Honors)
  • Electrical Depth
  • Project Summary
slide17

PROJECT SUMMARY

  • summary
    • LIGHTING: Illuminated spaces to satisfy IESNA standards and ASHRAE power requirements
    • DAYLIGHTING: Reduced annual energy consumption by over 50% with integrated photosensor system
    • ACOUSTICS: Validated improvements with alternative flooring; not critical to implement
    • LED STUDY: Alternative general illumination system for labs insufficient
    • ELECTRICAL: MCC designed for mechanical penthouse is not practical
  • Introduction & Project Overview
  • Lighting Depth
    • Working Space
    • FacadeAtrium
  • Daylighting (MAE)
  • Acoustical Breadth
  • LED Study (Honors)
  • Electrical Depth
  • Project Summary
slide18

Acknowledgements

Thank you to:

AE FacultyCannon Design

Family

Classmates + Friends

thank you