1 / 11

AERONAUTICAL COMMUNICATIONS PANEL (ACP) 20th MEETING OF WORKING GROUP M

AERONAUTICAL COMMUNICATIONS PANEL (ACP) 20th MEETING OF WORKING GROUP M Montreal, Canada January 23 - 25, 2013. Agenda Item: 6 (b). FAA Departure Clearance Trials Activities (Presented by: Peter Muraca, FAA). Agenda. DCL Trials Overview Activities Trials Stakeholders

sage
Download Presentation

AERONAUTICAL COMMUNICATIONS PANEL (ACP) 20th MEETING OF WORKING GROUP M

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. AERONAUTICAL COMMUNICATIONS PANEL (ACP) 20th MEETING OF WORKING GROUP M Montreal, Canada January 23 - 25, 2013 Agenda Item: 6 (b) FAA Departure Clearance Trials Activities (Presented by: Peter Muraca, FAA)

  2. Agenda DCL Trials Overview Activities Trials Stakeholders End to End Architecture Functional and Operational Test Activity DCL Trials Timeline / sites 2

  3. DCL Trials Overview DCL – Data Communications Departure Clearance Service: Initial and revised clearances to participating FANS equipped aircraft Data Comm Trials Automation Platform (DTAP) – Standalone application end system w/ Controller CHI Flight Deck logs on via AFN service, and Initiates the Clearance Request (DM25) Uplinked Route information is auto-loadable into Flight Deck FMS Flight Deck can Wilco, Standby, Unable uplinked messages AOCs receive real time copies of messages uplinked to flight deck (AOC responds with Gate info) MEM, EWR, ATL selected to host DCL Trials: FAA, NATCA and industry participation in site selections Trials expected to run for 1 year under Test NCP’s DTAP independent of current Tower Data Link Services (TDLS)

  4. Data Comm Implementation Team (DCIT) established Jan 2011 Members include operators, FAA reps, automation system manufacturers, research organizations, NATCA, Communication Service Providers, avionics manufacturers, aircraft manufacturers, as well as support contractors Working Groups for DCIT: Management, AOC, Flight Deck, and Systems Integration Three trials sites and leading partners are: Memphis/FedEx, Newark/United-Continental, Atlanta/Delta MOUs in process to include Union participation Additional sites possible, as necessary DCL Trials Activities

  5. DCL Trials Stakeholders DCIT Committee Aircraft operator participants ANSP participants Aircraft Manufacturers Data Comm Service Providers Ground systems suppliers Avionics suppliers Airline and controller unions Focus of DCL trials De-risking the operational DCL system Clarifying and validating system requirements Verifying benefits

  6. DCL Trials Architecture Airline HOST TOWER ARTCC DTAP 1 Boeing flight deck HOST MONITOR HADDS CSP & API FDP ARINC HID KYBRD HMI DCL HADDS ERAM FAA Technical Center FNTB FANS 1/A+ STACK AFN MOUSE DEMARC TEST IP DATA RECORD FTI OPSIP NESG ATL HADDS NESG ACY OS DEMARC DEMARC ERAM TOWER HID 2 IP TEST DTAP TDLS 2 HOST DEMARC TOWER DTAP HADDS ERAM 3 2,3 2,3 DTAP TDLS 3 SITA HID 2,3 Airbus flight deck HOST 2,3 PC-RCU Strip Printer ARTCC 2,3 Airline HOST

  7. Functional and Operational Test Activity Lab Environment End to End Functional Testing End to End Operational Scenarios Testing (includes controller crew) FANS Avionics Platforms DCIT Aircraft (FedEx, UPS, United, Delta) Site Acceptance Testing (Field Environment) Sub_set of Functional End to End Operational end to end scenarios Training Activity FedEx Aircraft

  8. MEM Limited Ops Trials Timeline Functional Testing @ WJHTC & MEM 11/27 – 12/14 Additional Functional Testing BUFFER 12/14 – 12/24 Holiday Break 12/24 – 1/2 OT2, ATC Training, SAT @ MEM 1/2 – 1/7 BUFFER 1/7 – 1/16 Limited Ops Trials Window (TBD Ops/Day – 2 Weeks) 1/16 – 2/10 NOV FEB DEC JAN DCL Trials: On 1/16/13 FDX303 (KMEM=KMIA P2125) was the first operational revenue FANS DCL operation in the US

  9. MEMFull Ops Trials Timeline FDX Pilot Training 30 Day Notice – 2/4 FDX GOC Training 14 Day Notice – 2/15 Functional Testing @ WJHTC DTAP B6 End of Limited Ops Trials, MEM DTAP Upgrade 2/10 – 2/15 B6 SAT @ MEM, Trials FF GO Checkpoint 2/18 – 2/22 Buffer Full Functionality Trials Start, Procedures Shake Out (~50 DCL Flights) 3/4 – 4/4 Full Functionality 24x7 Trials Ops 4/4 + 120 Days OT3 & ATC Training @ MEM 1/29 – 2/8 APR FEB MAR JAN

  10. MEMFull Functionality 24x7 Ops Trials • April 4 - MEM Full Fleet • Starts 120 Day Trials Review Checkpoint Timer • Independent Safety Assessment Office (AJI-321) planning Trials evaluation and analysis

  11. EWR & ATL Trials Schedule / Planning • EWR Trials Activities underway (planned start April 2013) • Meeting at facility with ATC and Tech Ops Mgt (12/17) • FTI Telco/Network Connectivity Order Initiated • DTAP ZNY HADDS interface configuration Initiated • HADDS, FDIO Test NCP development Initiated • Equipment Implementation goal in March • Initial operators include UAL, FDX, UPS, LFT • ATL Trials Activities (planned start October 2013) • Initial operators include: Delta Airlines

More Related