Machine Status Update: Proton Source Commissioning and MI30 Vacuum Completion – Sept 2013

This document summarizes the key developments and status updates from the Experimenters' Meeting held on September 2, 2013. Major highlights include successful commissioning of the Proton Source, completion of vacuum work on the Main Injector (MI30), and restoration of beam to MI. Additionally, updates on KRS T85, NuMI target installation, and magnet replacements are provided. A scheduled power outage for MI conventional systems is also noted. Reference to August/September 2013 draft schedules is included for operational insights.

saad
Download Presentation

Machine Status Update: Proton Source Commissioning and MI30 Vacuum Completion – Sept 2013

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. All Experimenters’ Meeting September 02, 2013

  2. Machine Status • Proton Source Commissioning and Studies • Main Injector • MI30 vacuum work completed • Beam returned to MI on Wednesday • MI back-fed from Master Sub-Station • KRS T85 work complete, but still using Feeder 45 for MI conventional • Need to schedule a 20 minute MI conventional power outage to remove the back-feed from Master Sub-Station after tunnel work. • MI beam studies • NuMI • Horn scans completed • Target installed • Target scans completed • SY120 • H201-10 magnet replacement • MTest paperwork scheduled for Tuesday, Sept 3rd. • MI Slow extraction studies / extraction to absorber

  3. Neutrino Muon • G2 NM1 Berm Pipe Progress • Final pull this week. M. Geelhoed 8/16/2013

  4. Power Outage • Feeder 43 fault : 0956 Sept 1 • Glitch affected AD accelerators, enclosures, buildings along with FCC and IB complex • A0 switch flashed over • Accelerators were recovered by 1508 • Feeder 43 re-energized at 1702.

  5. August/September 2013 DRAFT

  6. Schedules and Links: • Schedule can be accessed from the Operations Home Page • - Schedules -> Operations Schedule • Direct link to schedule • - http://www-ad.fnal.gov/ops/schedule.html