210 likes | 318 Views
Explore the unique process of corridor planning for NEPA compliance using the Goose Creek Canyon Bypass Case Study. Learn about challenges, solutions, and a model for future work. The case study includes the application of Quantm and GIS to address highway environmental concerns and engineering criteria. Find out how strategic collaboration and data management were key to achieving project goals swiftly and cost-effectively.
E N D
A Highway Corridor Planning Process for NEPA Compliance Using Quantm Goose Creek Canyon Bypass Case Study A Unique Approach to Corridor Planning
Acknowledgements Co-Authors – Dale Anderson, Karen Comings, Trevor Howard – Entranco, Inc. Len Bettess – Quantm, Inc. Jason Brinkman - ITD
What are our presentation objectives? • Discuss challenges – Highway Corridor Planning for NEPA Compliance • Present unique approach using Quantm and GIS • Describe solutions • Provide model for future NEPA work
What is purpose of Bypass? • Construct safe, economical, and environmentally acceptable highway around Goose Creek Canyon. • Why? • Narrow 22-foot wide roadway • Steep 7 percent grades • Shaded areas - frequent icing • Poor curvature, low driving speeds, • Inadequate passing opportunities.
What are challenges of the Highway Environmental Process? • Previously studied highway alternatives • Evaluate the existing highway upgrade comparably to new highway alternatives • Consider other highway alternatives with dollar and time limitations
What are challenges of the Highway Environmental Process? • Gain the trust and confidence of the citizens and resource agencies • Obtain concurrence on highway alternatives screening • Agree on how much data is enough to make a screening decision
What is Quantm? • Provides a highway planning, computer-based optimization tool • Helps locate highway alternatives • Meets pre-determined engineering & environmental criteria • Staff training and support
How was Quantm Applied to the Goose Creek Project? • Develop GIS data base • Linear Features - Roads, Railroads, Utility Network (power lines and power transfer stations), Streams, Nordic and Snowmobile Trails • Special Zones - Wetlands, Lakes, northern Idaho ground squirrel habitat (surveys from the recovery team field work), bald eagle habitat, cultural areas, public land, 4(f) recreational property and historic property, private land, and land use • Additional Data - Geologic Zones
Baseline highway alternatives – no environmental constraints
Establishing highway corridors – Quantm generates array of alternatives
Establishing highway corridors – Quantm generates array of alternatives
Establishing highway corridors – variable width corridor for detailed environmental inventory
How did our approach address challenges? • Previously studied highway alternatives? Imported into Quantm – compared on equal basis for engineering and environmental • Evaluate the existing highway upgrade? – Optimization for canyon route – not cost effective to meet design standards • Other alternatives with dollar and time limitations? Used existing GIS data, established design criteria, looked at new alignment within days
How did our approach address challenges? • Gain the trust and confidence of the citizens and resource agencies? Timely results for skeptical stakeholders – objective – costs and environmental impacts • Obtain concurrence on screening? Collaborate with stakeholders through workshops – demonstrate Quantm attributes – work through alternatives together • How much data is enough to make a screening decision? Agree on data needs for screening and corridor inventories – maintain flexibility – provide clear documentation
Where should we go from here? • Established highway corridor planning / environmental / engineering process • Establish highway corridors • Selects alternatives • Complies with NEPA • Addresses challenges – objective, cost-effective – quicker • We believe – it is worth repeating in Idaho