Market Trials Update

Market Trials Update. Agenda. LFC Testing Review Review of materials presented at TAC Changes in Market Trials schedule and activities 168-Hour Handbook Review (presentation in the afternoon). LFC Update and Review of Materials Presented at TAC.

roderickb
Download Presentation

Market Trials Update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Market Trials Update 1 Texas Nodal

  2. Agenda • LFC Testing Review • Review of materials presented at TAC • Changes in Market Trials schedule and activities • 168-Hour Handbook Review (presentation in the afternoon) 2 Texas Nodal

  3. LFC Update and Review of Materials Presented at TAC 3 Texas Nodal

  4. Issues & Observations During the 8 Hour Test on June 17th 4 Texas Nodal

  5. Issues During the 8 Hour Test - ERCOT • Issue #1 – Missing Shift Factors for Electrical Busses affected SPP calculation • EMS integration did not properly provide electrical bus shift factors • Load Zone, Hub, and Electrical Bus LMPs/SPPs incorrect when constraints binding or violated • Issue introduced with EMS Bug Fix end of last year • Issue #2 – Missing Shift Factors for constraints in SCED for brief period • Shift Factor transfer from EMS to MMS from1320-1339 had issues • Constraints were ignored by SCED for 19 minutes • Dispatch closely monitored by Operators until resolved • Issue introduced with EMS Bug fix in mid-May • Issue #3 – Incorrect flag setting in EMS • ERCOT did not use load distributed bus as the reference bus • Telemetry changes created topology changes which lead to a bus in the west zone to be the reference bus • Having 3% shift factor cut off caused several WGRs to have no shift factors on the constraint causing WGRs to be marginal 5 Texas Nodal

  6. Issues During the 8 Hour Test – Market Participants • Issues during test for Market Participants • Telemetry: • Inconsistencies between JOU owners (e.g., telemetry, COP) • Incorrect Ancillary Service values in telemetry for Resource • Incorrect Resource Status Codes • Incorrect HSL/LSL values telemetered • Resource with nodal Output Schedule offering BES into zonal market • Resources not following their nodal Base Points • Resources not following regulation signals • Zonal Resource Plans not in agreement with Nodal 6 Texas Nodal

  7. Next Steps – LFC Tests • Migrate fix to views that will resolve the issue with the Shift Factors not being available (Code migrated, still monitoring) • Migrate fix to views that will resolve the issue with transferring an incomplete Shift Factor set (Code migrated, still monitoring) • Use Distributed Load Bus as the Reference Bus instead of Single Reference Bus • Set Shift Factor cut-off to a much smaller value such as .0001 • More closely monitor Resources in how they are following their Base Points and provide feedback • Confirm parameter settings prior to every test • Leave OC1 in Zonal during transition. Once 100% Nodal, take out OC1 in Zonal. Bring the OC1 back at the start of transitioning back to Zonal • Specific time slots for tuning for both Market Participants and ERCOT 7 Texas Nodal

  8. Changes in Market Trials Activities 8 Texas Nodal

  9. Changes in Market Trials Activities • Issues encountered during the 8-Hour LFC test demonstrated the need to shift the focus of Market Trials Activities • The following changes are to achieve the following: • Reduce the number of DAMs to create more resource availability to support additional LFC tests • Increase the number of LFC tests in order to gradually step into a multi-day scenario • DAM will focus on the quality of the data submitted (deconstructed offer curves, more complete coverage of online generation with offer curves, accurate COPs) • Provide more flexibility to address issues and refine Market Trials activities as needed 9 Texas Nodal

  10. Changes in Market Trials Activities • Additional LFC testing will be added • Week of 7/19 – 5-Hour Test • Week of 8/02 – 24-Hour Test • August will include 1 – 2 additional tests • September will include 1 – 3 additional tests • Additional tests will be confirmed no later than 2 weeks prior to the testing date • Day Ahead Market (DAM) and Reliability Unit Commitment (RUC) • Will be run for LFC Operational Dates during the weeks of LFC testing • A focused input day will be included where MPs will submit trades, bids, offers and COPs that more representative of the post go-live market • On non-LFC testing weeks: • DAM and RUC will continue to run up to 5 times weekly 10 Texas Nodal

  11. Changes in Market Trials Activities • August will remain our target for running any operational scenarios that have been added or need to be re-run • Examples of scenarios that are being reviewed for inclusion are: • Emergency Base Point (SCED Failure) SASM for Undeliverable AS / Failure to provide AS • Manual Offset for SCED SASM for ERCOT Load Increase, • DCS Event HRUC / DRUC Failure and Timeline Deviation • EEA Event Capacity Shortage Intra-day and Real Time • DC Tie at max import trips Frequency excursion high • Settlements and Credit will continue to run daily and produce normal outputs taking into account the revised Market Trials activities (e.g. no DAM settlements on non-DAM dates) • CRR and Outage Scheduling activities remain unchanged and will align with the communicated go-live transition plans (note that ERCOT will consolidate these transition plans into a Cutover Handbook to be published and reviewed at the Market Readiness Seminar (MRS) #5 on 7/28/2010) 11 Texas Nodal

  12. 168-Hour Handbook Review(word document) 12 Texas Nodal