1 / 10

OPIM 5894 Advanced Project management Ariba implementation at med-x managing earned value

OPIM 5894 Advanced Project management Ariba implementation at med-x managing earned value. Team 3 Richard Buskey Jonathan Weiss Daniel Mahzonni Prashant Mishra Vijay Gadigeppa Jonathan Koenig. http://users.business.uconn.edu/snair/opim5894.html. Which component is underperforming?.

rhea
Download Presentation

OPIM 5894 Advanced Project management Ariba implementation at med-x managing earned value

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. OPIM 5894 Advanced Project managementAriba implementation at med-xmanaging earned value Team 3 Richard Buskey Jonathan Weiss Daniel Mahzonni PrashantMishra Vijay Gadigeppa Jonathan Koenig http://users.business.uconn.edu/snair/opim5894.html

  2. Which component is underperforming? • Technical Infrastructure • Cost variance – ($75,500) • Schedule variance – ($110,000)

  3. Components within budget? • Software Customization – YES • Positive cost variance – $159,500 • Cost performance index > 1

  4. Components within budget? (cont.) • Technical Infrastructure – NO • Negative cost variance – ($75,500) • Cost performance index < 1

  5. Combined earned value data for the project • Misleading • Project appears to be on schedule/within budget • Software Customization is ahead of schedule and budget offsetting technical infrastructure deficiencies

  6. Combined earned value data for the project (cont.) • Misleading • Project appears to be on schedule/within budget • Software Customization is ahead of schedule and budget offsetting technical infrastructure deficiencies

  7. Terry Baker • Vague Gantt chart being used as primary management tool • Did not take costs into account • Metrics not gathered throughout project • Only requested when problem appeared (i.e., over budget and behind schedule) • Looking at project from a very high level

  8. How much longer will the project take? • Technical infrastructure portion of project appears to be approximately 6% behind schedule (as of September) • ~8 additional days required

  9. What should Martin have done earlier to prevent delays? • Gather ratios on different aspects of project earlier • Proactive approach rather than reactive approach • Better recognition of potential problems • Management of resources • Delay in Sun server equipment • System testing and development scheduled late

  10. What should Martin do in the future to prevent similar issues? • Plan for gathering data to produce metrics at key milestones within project • Avoid using only Gantt chart to manage project • Create more detailed project timeline • Critical path management • Better resource management