An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LHCOPN perfSONAR MDM update Otto Kreiter LHCOPN Utrecht 21st April 2009

  2. Agenda • Status of the MoUs • Status of the deployment • How to access LHCOPN portal • Demo • Next steps

  3. Status of the agreements • MoU signed • NL-T1, DE-KIT, ES-PIC, UK-T1-RAL, FR-CCIN2P3, NDGF, IT-INFN-CNAF, TW-ASGC • Collaboration Agreement • CERN • Gentlemen's agreement • US-FNAL-CMS, US-T1-BNL, CA-TRIUMF.

  4. Status of the deployment - I Finished • NL-T1, DE-KIT, ES-PIC, FR-CCIN2P3 • only fine tuning of the configuration required • and GPS antenna installation (ES and FR).

  5. Status of the deployment - II In progress • UK-T1-RAL • Both servers on site. Awaiting installation. • NDGF • Pre-shipment form received by Service Desk • Hades server received • MDM server shipment in progress (should be on site).

  6. Status of the deployment - III In progress • CERN • Working on the shipment. • Expect the server to be delivered w/c 27th April • IT-INFN-CNAF • MoU just received. • Waiting for deployment initiation meeting to be set-up.

  7. Status of the deployment - IV • US-FNAL-CMS • Waiting for pre-shipment for to be received. • US-T1-BNL • Working on the shipment of the servers • TW-ASGC • Working on the shipment of the servers – estimated delivery beginning of May • CA-TRIUMF • Working on the shipment of the servers – estimated delivery beginning of May.

  8. LHCOPN perfSONAR portal

  9. How to access it ? • http://lhcopn-mdm.geant2.net/portal/ • Authentication and Authorisation is required via a national Identity Provider.

  10. How to get credentials • If your NREN operates a production Identity provider service Please ask them to create you an account with the following attributes: Project Memberships = LHCOPN Project Specific Roles = LHCOPN-operator Contact person to confirm the attributes: GÉANT ServiceDesk (service.support@geant2.net) and Tier-1 of the country

  11. How to get credentials - II • If your NREN does not have an Identity provider service https://gidp.geant2.net Please ask the contact person from your NREN to create you an account with the following attributes: Project Memberships = LHCOPN Project Specific Roles = LHCOPN-operator Contact person to confirm the attributes: GEANT ServiceDesk (service.support@geant2.net) and Tier-1 of the country

  12. LHCOPN perfSONAR portal - demo

  13. Next steps • Finish installation • Set up training • Gather further requirements • Develop some sort of strategy/plan on how to interact with Tier-2 perfSONAR monitoring. • The T1 boxes are ready (software and hardware) just the process/methodology/support is unclear.