1 / 17

The Capacity Allocation & Congestion Management Network Code An overview & status update

The Capacity Allocation & Congestion Management Network Code An overview & status update. Antonio Lopez-Nicolas Manager - Markets. Outline. Brief background to network codes & ENTSO-E The network codes required to facilitate the IEM

quiana
Download Presentation

The Capacity Allocation & Congestion Management Network Code An overview & status update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. The Capacity Allocation & Congestion Management Network CodeAn overview & status update Antonio Lopez-Nicolas Manager - Markets

  2. Outline • Brief background to network codes & ENTSO-E • The network codes required to facilitate the IEM • A focus on the Capacity Allocation & Congestion Management code • Questions and discussion

  3. The role of TSOs – ENTSO-E • Mandate for network codes and ten-year plans in Reg. 714/2009 • 41 TSOs from 34 countries • Fully operational since July 2009 • A trans-European network • 530 million citizens served • 910 GW generation • 300,000 km of transmission lines • 3,400 TWh/year demand • 380 TWh/year exchanges • Replaced former TSO organisations: ATSOI, BALTSO, RTSO, NORDEL, UCTE, UKTSOA System Development System Operation Electricity Market Research and Development

  4. The objectives of a Network Code The rationale for network codes as set out in Regulation 714/2009. • Clearly, simply and transparently outline a consistent approach to addressing each issue raised by ACER in relevant framework guidelines. • Achieve this in a proportionate manner which minimisesthe overlap with national regulation while covering cross-border issues. • Ensure that all obligations are clear and unambiguous and can be clearly understood by all stakeholders.

  5. ENTSO-E’s role according to Regulation (EC) 714/2009

  6. The Network Code Development Process Development of FWGL Development of NC

  7. The network codes required to facilitate the IEM - State of Play Black = Final FG Received, Yellow = Final FG Developed, Purple = Scoping Work

  8. CACM Network Code – The challenge

  9. CACM Network Code - Scope • The CACM network code describes: • The day ahead target model for market coupling. • The intra-day target model of implicit continuous trading. • Rules for calculating capacity and defining bidding zones. • Forward market design is part of the FWGL but will be addressed later.

  10. CACM Network Code – State of play Developing the CACM draft is a real challenge. We are in the process of merging 3 technical sections. And dealing with interactions with other areas and codes. Including reflecting informal comments from stakeholders. Ahead of a formal consultation.

  11. CACM Network Code – Stakeholder Engagement A stakeholder group was established in June 2011. The group will meet throughout the process of developing codes. Open workshops planned for early 2012. Bilateral meetings with stakeholders ongoing. Information is available via entsoe.eu

  12. CACM Network Code - Feedback from 3rd Stakeholder Group meeting • 3rd Stakeholder Group meeting of the CACM Network Code took place in Brussels on 8 December • Wide participation of stakeholder organizations. EC and ACER also attended as observers. • Active discussion focused on day-ahead markets and capacity calculation issues. • Next meeting will be hold on 2 February 2012 and will focus inter alia on intraday issues. • Relevant information about the stakeholder group can be consulted at ENTSO-E website.

  13. CACM Network Code – Key milestones

  14. CACM Network Code – Interaction with ongoing projects Network codes and implementation projects are compliments. Experience gained via projects is reflected in the codes and the codes facilitate the projects. But the codes also drive progress in areas where it hasn’t been seen to date. Both are important for the delivery of the Internal Electricity Market by 2014

  15. From North-West Europe towards a Pan-EU Market • ENTSO-E is fully committed to promote the completion and functioning of the internal electricity market according to its legal duties. • The 20th Florence Forum supported the continuation of the NWE project for both day-ahead and intra-day markets, in order to meet the target date of 2012. • ENTSO-E is ensuring further extendibility of NWE day-ahead and intraday solutions to other regions through the work of the Day-Ahead and Intraday Monitoring Groups where non-NWE TSOs are widely represented.

  16. Conclusions • The network codes will affect market participants. • And could cause changes in local market rules. • It is difficult to develop effective network codes for Europe. • So getting a range of stakeholder views is vital. • We urge parties to monitor progress and provide views. • Codes and implementation projects complement each other.

  17. Antonio.Lopez-Nicolas@entsoe.eu

More Related