An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. May 2021 January 2022

  2. Tower 18 18B 18C 18D 18A TOWER STATUS MILESTONES ACHIEVED • Tower 18 A Kitchen dado completed, Plumbing at stilt and Lobby flooring work in progress. Tower 18B Painting / Putty, Lobby flooring work in progress. Tower 18C Painting / Putty work in progress. Tower 18D Gypsum work in progress. Tower 18E Balcony Flooring work in progress. Tower 18F Flooring, Toilet Dado and Railing work in progress. Tower 18G Terrace Slab completed. • 18ABC&D – Flooring & Windows completed. • UPCOMING MILESTONES 18E 18F 18G • • 18DE&F – Completion of Flooring & Windows. 18 A B C completion of stair cases, lift wells, and lobbies of the floor in which the purchaser's apartment. • • • • Actual site photograph • PROGRESS TIMELINE September 21 October 21 November 21 December 21 January 22 Construction Updates

  3. Tower 17 17BC4 17CC2 17AC2 TOWER STATUS MILESTONES ACHIEVED • • Tower 17AC2 Above terrace works are in progress. Tower 17BC4 Above Terrace OHT work completed. Tower 17CC2 Above terrace works are in progress. Tower 17BC4 Above Terrace OHT work completed. • UPCOMING MILESTONES • Actual site photograph • T17 A,B &C completion of stair cases, lift wells, and lobbies of the floor in which the purchaser's apartment. PROGRESS TIMELINE September 21 October 21 November 21 December 21 January 22 Construction Updates

  4. Tower 16AC5 TOWER STATUS MILESTONES ACHIEVED • • • • Terrace slab completed. Gypsum work in progress. Flooring in progress. Terrace Slab completed. UPCOMING MILESTONES • Completion of Flooring & windows. Actual site photograph PROGRESS TIMELINE September 21 October 21 November 21 December 21 January 22 Construction Updates

  5. Tower 15AC5 TOWER STATUS MILESTONES ACHIEVED • • Above terrace works are in progress. Gypsum work completed. Flooring work in progress. Terrace Slab Completed. • • UPCOMING MILESTONES • Completion of Flooring & windows. Actual site photograph PROGRESS TIMELINE September 21 October 21 November 21 December 21 January 22 Construction Updates

  6. Tower 14AC5 TOWER STATUS MILESTONES ACHIEVED • • Above terrace works are in progress. Gypsum works completed. Cornice completed. Terrace Slab completed. • • UPCOMING MILESTONES • Completion of Flooring & Windows. Actual site photograph PROGRESS TIMELINE September 21 October 21 November 21 December 21 January 22 Construction Updates

  7. Tower 13AC5 TOWER STATUS MILESTONES ACHIEVED • • Above terrace works are in progress. Flooring completed. Gypsum work in progress. Toilet Dado work in progress. Terrace Slab Completed. • • • UPCOMING MILESTONES • Completion of Flooring & Windows. Actual site photograph PROGRESS TIMELINE September 21 October 21 November 21 December 21 January 22 Construction Updates

  8. Tower 12 12BC3 12AC6 TOWER STATUS MILESTONES ACHIEVED • • Tower 12AC6 Gypsum & Flooring completed, Toilet Dado work in progress. Tower 12BC3 Vitrified flooring, Railing & Gypsum completed, Toilet Dado work in progress. T12-A&B Terrace slab completed. • UPCOMING MILESTONES • T-12-A&B Completion of Flooring & Windows. Actual site photograph PROGRESS TIMELINE September 21 October 21 November 21 December 21 January 22 Construction Updates

  9. Tower 11AC6 TOWER STATUS MILESTONES ACHIEVED • • Above terrace works are in progress. Flooring & Gypsum completed. Toilet, Balcony and Utility Flooring work in progress. Terrace slab completed. • UPCOMING MILESTONES • • Completion of Flooring & Windows. Actual site photograph PROGRESS TIMELINE September 21 October 21 November 21 December 21 January 22 Construction Updates

  10. Tower 10 10BC6 10CC3 10AC4 TOWER STATUS MILESTONES ACHIEVED • • Tower 10AC4 Above terrace work in progress. Tower 10BC6 Above terrace works in progress, Flooring completed. Tower 10CC3 Above Terrace, Toilet Dado and Balcony Flooring works in progress. T10 A,B,C – Terrace slab completed. T10 A&B flooring & windows completed. • • • UPCOMING MILESTONES Actual site photograph • T10 C completion of Flooring & Windows. PROGRESS TIMELINE September 21 October 21 November 21 December 21 January 22 Construction Updates

  11. Tower 9 9BC6 9AC6 TOWER STATUS MILESTONES ACHIEVED • • Tower 9AC6 4th slab pour 2 work in progress. Tower 9BC6 Excavation in progress. Tower 9AC6 2nd Slab completed. • UPCOMING MILESTONES • Tower 9AC6 completion of 4th Slab. Actual site photograph PROGRESS TIMELINE September 21 October 21 November 21 December 21 January 22 Construction Updates

  12. Tower 8 8BC5 8AC2 TOWER STATUS MILESTONES ACHIEVED • • Tower 8BC5 Plinth Beam work in progress. Tower 8AC2 Footing work in progress. Yet to achieve. • UPCOMING MILESTONES • Tower 8BC5 completion of Plinth. Tower 8AC2 completion of Plinth. Actual site photograph • PROGRESS TIMELINE September 21 October 21 November 21 December 21 January 22 Construction Updates

  13. Tower 7 7BC6 7DC3 7AC6 TOWER STATUS MILESTONES ACHIEVED • • • Tower 7DC3 Terrace slab work in progress. Tower 7BC6 Walls up to Plinth completed. Tower 7AC6 Walls up to 1st Slab in progress. T-7D plinth completed. Tower 7DC3 4th Slab completed. Tower 7AC6 Plinth Beam Completed. • • • UPCOMING MILESTONES Actual site photograph • Tower 7DC3 Completion of Terrace Slab. Tower 7BC6 Completion of Plinth Beam. • PROGRESS TIMELINE September 21 October 21 November 21 December 21 January 22 Construction Updates

  14. Tower 6 6BC4 6CC5 6AC4 TOWER STATUS MILESTONES ACHIEVED • • Tower 6AC4 2nd Slab reinforcement started. Tower 6BC4 4th Slab work in progress. Tower 6CC5 1st slab work in progress. Tower 6DC6 Terrace Slab completed. Tower 6EC3 Terrace slab completed. 6BC4 2nd Slab completed. • • UPCOMING MILESTONES 6DC6 6EC3 • • • 6BC4 completion of 4th Slab. 6BC4 completion of Terrace Slab. • Actual site photograph PROGRESS TIMELINE September 21 October 21 November 21 December 21 January 22 Construction Updates

  15. Tower 5 5BC5 5AC5 TOWER STATUS MILESTONES ACHIEVED • • Tower 5AC5 4th Slab work in progress. Tower 5BC5 1st Slab completed. Tower 5CC5 1st Slab completed. Tower 5DC3 Terrace OHT Works in progress. Tower 5AC5 2nd Slab completed. • • UPCOMING MILESTONES 5CC5 5DC3 • • Tower 5A completion of 4th Slab. Actual site photograph PROGRESS TIMELINE September 21 October 21 November 21 December 21 January 22 Construction Updates

  16. Tower 4 4BC4 4CC6 4AC4 TOWER STATUS MILESTONES ACHIEVED • • Tower 4AC4 Terrace slab completed. Tower 4BC4 Terrace Slab completed. Tower 4CC6 Walls up to 1st Slab work in progress. Tower 4BC4 4th Slab completed. Tower 4BC4 Terrace Slab completed. • • • UPCOMING MILESTONES Actual site photograph • 4C – completion of 2nd slab. PROGRESS TIMELINE September 21 October 21 November 21 December 21 January 22 Construction Updates

  17. Tower 3 3B 3A TOWER STATUS MILESTONES ACHIEVED • • Tower 3A Waterproofing in progress. Tower 3B OHT Works in progress. Tower 3C Walls up to Stilt Slab completed. Tower 3D Excavation work in progress. T-3A &B Terrace slab completed. • • UPCOMING MILESTONES 3C 3D • • T-3A completion of Flooring & Windows. Actual site photograph PROGRESS TIMELINE September 21 October 21 November 21 December 21 January 22 Construction Updates

  18. Tower 2 2B 2A TOWER STATUS MILESTONES ACHIEVED • • • • Tower 2A Terrace Slab completed. Tower 2B Gypsum and Waterproofing in progress. Tower-2A 2nd slab completed. Tower-2A 4th Slab completed. Tower-2A Terrace Slab completed. • UPCOMING MILESTONES • Tower-2B Flooring & Windows completion. Actual site photograph PROGRESS TIMELINE September 21 October 21 November 21 December 21 January 22 Construction Updates

  19. Tower 1 1B 1A TOWER STATUS MILESTONES ACHIEVED • • Tower 1A Walls up to Plinth completed. Tower 1B Plinth work in progress. Yet to achieve. • UPCOMING MILESTONES • Completion of Tower 1B Plinth Actual site photograph PROGRESS TIMELINE September 21 October 21 November 21 December 21 January 22 Construction Updates

  20. Other activities TOWER STATUS • STP-1 STP walls in progress. • UG Sump Walls work in progress. • Entrance Portal Block work in progress. • Compound wall Block work in progress. • Blu Area Excavation work in progress. • MUC STP & UG Raft & Walls work in progress • STP-2 Excavation completed. • Road Excavation & Retaining Wall work in progress. • Club House Foundation work in progress. Actual site photograph PROGRESS TIMELINE September 21 October 21 November 21 December 21 January 22 Construction Updates

  21. Site Office : Provident Adora de Goa Sy.No.198, Zuari Nagar, VidhyanagarColony, Chicalim, Goa – 403726. Regional Office : Provident Housing Limited No.8, Ulsoor Road, Bengaluru- 560 042 Tel: 080-44555544 Email : crm@providenthousing.com (Subject line – Project name/ unit number) Call Us : +91 - 80-67724001 / 1 860 208 0000 Web : www.providenthousing.com RERA Registration Number : RERA No.: PRGO02190645 (ROW 5 & 6) RERA Nos.: PRGO02180009 (Row 10,11 & 12), PRGO07180544 (Row 13) PRGO07180560 (Row 14), PRGO07180561 (Row 15)