1 / 13

CCG Meeting Angaston 3 rd December 2008

CCG Meeting Angaston 3 rd December 2008. Penrice CCG Meeting Action Arising. BLAST MONITORING Chris Linke Monitor Site Blast Data 21/11/09 60 holes located in south east pit face Vibration 0.53 mm/sec (Aust Std 5.0 mm/sec) Overpressure 95.4 dBL (Aust Std 115 dBL)

posy
Download Presentation

CCG Meeting Angaston 3 rd December 2008

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CCG Meeting Angaston 3rd December 2008

  2. Penrice CCG Meeting Action Arising BLAST MONITORING Chris Linke Monitor Site Blast Data 21/11/09 60 holes located in south east pit face Vibration 0.53 mm/sec (Aust Std 5.0 mm/sec) Overpressure 95.4 dBL (Aust Std 115 dBL) Salem Road Monitor Site (near Linke driveway entrance) Vibration 1.32 mm/sec Overpressure 106.6 dBL Further monitoring - 3/12/08 and the next week then relocation to south west of the mine

  3. Penrice – CCG Meeting • Blasting – Draft • Environmental Outcome • No nuisance to adjacent residents and sensitive receptors per definition of the relevant Australian Standard, currently AS2187.2 (2006) • Blasting will occur on weekdays (excluding Public Holidays) between 9.00 am and 4.30 pm. • Where the number of blasts in any year is estimated to be more than 20% above the average of the last 5 calendar years annual blast number, this will be communicated to the PCCG and community. • Environmental Criteria for Measurement • Blasting complies with Australian AS 2187.2 (2006) for overpressure (noise) (115dB environmental limit with 5% to a maximum of 120dB) and vibration levels (environmental limit 5 mm/s with 5% to a maximum of 10 mm/s) • Not more than 1% of the annual blasts will be out side these times • Strategies for Management • Compliance with Penrice Mine Operating Manual (procedure reference QFM2) • Overpressure and vibration levels will be measured during all scheduled blast activities • Blast modelling will be introduced using available industry technology. • Penrice will engage with community on alleged blasting damage to private infrastructure and investigate. Any mitigation measures will be determined and implemented based on investigation outcomes. • Ongoing review of new blasting technology to reduce vibration and air pressure • Ongoing training of blast technicians • Visual blast records and monitoring data maintained for each blast event • Annual audit of blast procedures by external parties

  4. Penrice CCG Meeting Action Arising • Barossa & Light Landscape Study 2005 • Study recommendations will be a part of a regional/council consultation process in 2009 • Particular emphasis of quarry impact • Importance of specific areas/features • Recommendations 5, 6, 7, 8 • Geotechnical Report • Initially supplied to PIRSA

  5. Penrice – CCG Meeting • Key Overburden Issues • 2007 recognized insufficient space for overburden • Storage overburden in the east area since early 1990’s • Mostly for low grade limestone in future years • Space impacted by height cap of the eastern storage area • 2M mt behind minimum extraction plan (Maptek) requirements • 4M mt planned in 2008 of both schist & low grade limestone to economically match out the internal haul fleet capacity • Storing low grade limestone in the north end of pit that will increase in coming years as the west face storage area is crushed to consume this inventory – 3M mt. • Extraction volumes limited in the last 5 months due to space issues • Consistent at all meetings with space issue and time constraints

  6. Penrice – CCG Meeting MAPTEK 30 year Mine Plan Increased overburden requirements due to geology & ore quality of high grade limestone, 2008/09 plan 4m mt with less in later years Of the 12.5M mt extracted in 4.4 years, 10m mt is schist

  7. Penrice – CCG Meeting Schist Overburden Extraction Volume (M mt)

  8. Penrice – CCG Meeting • CCG - MPL and Whole of Mine review • Gerlach land purchase contracted in December 2007 • In discussions with PIRSA since March 2008 on the MPL and the process with statutory consultation completed in August 2008 • Agreed with PIRSA for CCG to review environmental outcomes for whole of mine operation (not just the west MPL area) • This process will take another 6 -9 months

  9. Penrice – CCG Meeting • Visual Amenity • Penrice is: • Completing the profiling of the whole east and north faces to fit the hill line land form • Looking to find a temporary visual solution to the west face of east while crushing the low grade limestone inventory • It is not standing still and has limits on the capacity to remedy all areas of concern

  10. Penrice – CCG Meeting • Visual Amenity • In the meantime Penrice is: • Completing the profiling of the whole east and north faces • ( see photos) • Looking to find a temporary visual solution to the west face while crushing the low grade limestone inventory • It is not standing still and has limits on the capacity to remedy all areas of concern

  11. Penrice – CCG Meeting • Visual Amenity • In the meantime Penrice is: • Completing the profiling of the whole east and north faces • ( see photos) • Looking to find a temporary visual solution to the west face while crushing the low grade limestone inventory • It is not standing still and has limits on the capacity to remedy all areas of concern

  12. Penrice – CCG Meeting • Strategic Visual Amenity Plan Development • Visual Amenity is established through land form and vegetation, Oxigen are working up a strategic plan for the site covering • Existing Mine Area • Increase plantings and renew poor or dead vegeatation and under-story plantings to increase wildlife habitat – see map • Eastern Area • Estimated 30,000 trees/shrubs required for completionof eastern face at 12000/annum • Plantings on the north & east faces to RL400 in progress • Grass west face of eastern mound - low grade limestone and iron stone road benches • Western Area • Interim MPL proposal • Outside Mine Boundary • In conjunction with council/residents/land owners agree a tree planting regime. • (Suggested areas include areas of Stockwell Road & Penrice Road)

  13. Penrice – CCG Meeting • Interim WEST MPL (South-block) • This will allow PSP to continue mine operations for 9 – 12 months • This time will be needed to review all the environmental outcomes for the whole of mine site by the CCG and • To investigate other OB disposal options that are • economical • operationally practical and • do not limit the ability to extract high grade limestone • OXIGEN plan • Lease conditions are as detailed by PIRSA • A MARP with environmental outcomes and criteria are being finalized to match the newly issues lease conditions • Penrice is committed to finding solutions to community concerns

More Related