This document outlines the preliminary summer work schedule for the P0D project. Key activities include immediate fabrication of required equipment, opening the magnet on July 2, and a three-week post-opening water target checkout. Important milestones include CWT disconnection and preparation from July 13 to July 27, lifting on August 13, bladder replacement completion by August 20, followed by another three-week water target checkout. New installations are scheduled for September 14, with the project completion goal set for September 17.
E N D
Summer work schedule • The following is a rough first-blush pass at a schedule for summer work on the P0D • Work includes: • Fabrication of required equipment beginning essentially immediately • Opening magnet beginning July 2 • 3-week post-opening water target checkout • CWT disconnecting & prep July 13 – July 27 • CWT lifting beginning August 13 • Bladder replacement complete August 20 • 3-week post-replacement water target checkout • New drip pans & dry air covers installed September14 • P0D repair complete September 17
Work at J-PARC Assumptions: Magnet begins opening July 2 “Beneficial occupancy” July 9 Project complete September 17