Network & Gantt chart

Network & Gantt chart. Project management ( lecture ). Why to translate a network to a Gantt chart?. Gantt chart is more readily to understood by ‘unskilled’ people. It is especially useful when presenting to the top management. Progress can be easily displayed on it

peyton
Download Presentation

Network & Gantt chart

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Network & Gantt chart Project management (lecture)

  2. Why to translate a network to a Gantt chart? • Gantt chart is more readily to understood by ‘unskilled’ people. It is especially useful when presenting to the top management. • Progress can be easily displayed on it • Visualise floats and activity times. Effective explanatory and teaching instrument. • Resource allocation can be performed on it.

  3. Two ways af translating networks into bar chart • Calculating activity times and loacting these on the bar chart • Drawing activities directily to a time-scale, using the node numbers ensuring correct relationships (time-scaled network) • AoA type • AoN type

  4. The time-scaled network (AoA) • Mark activities by nodes (events) • Any dummy must be drawn in as a vertical line with its head and tail node-labels • Activitiy bars will fall from top-left to bottom-right. Dependent activities are always lower in the chart.

  5. 10 20 15 0 25 30 5 1 2 4 4 3 The time-scaled network (AoA) 7 2 10 7 13 c a 0 23 1 4 15 8 0 23 b 15 d 3 15 a c free float b d burst merge

  6. Dummy activities on a time-scaled AoA network 15 2 20 0 3 4 20 25 20 1 10 20 15 0 25 5 30 15 5 a b 3 1 4 2 c 20 25 0 3 a 2 c b dummy

  7. 0 0 0 0 0 0 START a d FINISH c b 20 15 7 0 0 0 6 0 0 0 0 0 20 0 20 15 7 17 5 0 7 10 0 15 20 0 6 0 13 15 15 13 20 0 20 23 Time-scaled AoN network (example 1) • Re-draw the first AoA project as an AoN network: • On AoN networks start and finish activities should be created if thereis no single starting/ending activities.

  8. Translate standard AoN to a time-scaled network 10 17 20 23 15 25 30 5 0 7 FINISH START a c b d

  9. Time-scaled AoN network (example 2) 0 0 5 0 0 START a b c FINISH 25 20 0 0 0 0 5 0 0 0 25 0 25 15 20 20 0 15 0 5 20 0 0 25 5 20 20 25 0 25 Re-draw the second AoA: Translate it to a time-scaled network.

  10. Solution 10 20 15 25 30 5 0 FINISH START a c b

  11. 0 0 0 5 0 0 3 e c a START FINISH b d 10 13 0 2 0 0 2 5 0 0 0 0 3 0 13 5 7 2 13 10 0 5 5 3 8 0 2 0 0 13 5 5 10 0 2 0 13 10 2 10 13 10 Time-scaled AoN network(individual exercise)

  12. 10 20 15 25 30 5 0 START FINISH Solution c a d b

  13. Reading • Lockyer – Gordon (2005): Chapter 16