An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. SPIRAL II 27 – 28 February 2006 Marcel Jacquemet

  2. Summary Spiral II View Spiral II Layout Status of the Project Project Management Main tasks of the Project Team during 2006 • To build project management • To take technical decisions • To begin the Spiral 2 construction • To share the work packages

  3. Spiral 2 Layout GANIL facility CIME Cyclotron Acceleration of RI Beams E < 25 MeV/n, 6-8 MeV/n for FF DESIR (LIRAT) Production building C converter+UCx target  1014 fissions/s Heavy-Ion ECR source (A/q=3) 1mA RFQ Stable Heavy-Ion Exp. Hall Super conducting LINAC 40MeV d - 5mA -14MeV/n HI

  4. Spiral 2 Layout

  5. Status of the project End of 2004 Technical report published Situation of the APD phase : * Accelerator :APD studies finished * Radioactive Isotope Beams :not completely finished * Infrastructure :not completely finished

  6. Status of the project From January to September 2005 Project structure maintained during a“transition period” Objectives : • Contract for definition of the production building • Safety studies and authorisation procedures • R& D • End of APD studies

  7. Status of the project May 2005: Project approved July 2005: Appointment of Project Leader and Scientific by DSM and IN2P3 Directors October – December 2005: Organization of the Project Team

  8. Tasks of the Spiral 2 management For 2006 : • To build project management • Project team • Work breakdown structure • Quality Assurance Plan • Planning and budget • To take technical decisions • Separator • Nuclear studies • To share the Work packages • To begin the Spiral 2 construction

  9. Tasks of the Spiral 2 management For 2006 : • To build project management • To take technical decision • To share the work packages • To begin the Spiral 2 construction

  10. Project Management Décideurs Pilote stratégique Pilote opérationnel Sections Laboratoires CEA /DSM CNRS/IN2P3 STEERING COMMITTEE TAC – SAC National & International Partners Scientific Commu Project Direction GANIL Project management 19 Infrastructure Accélérateur RIB production Other labs

  11. Direction Team Project Leader M. Jacquemet Project scientist M. Lewitowicz Safety & radioprotectionB. Rannou Assistant A. Latour AcceleratorLeaderT. Junquera Radioactive Isotope Beams LeaderM. H. Moscatello Infrastructure LeaderCh. Chéron Quality Engineer M. Perret Gatel System Engineer E. Petit Project Control Engineer Ph. Laborie Manpower & budget Assistant X

  12. Tasks of the Spiral 2 management For 2006 : • To build project management • To take technical decisions • To share the work packages • To begin the Spiral 2 construction

  13. Technical Decisions Risks analysis and “reduction of the causes” Nov. 05 – May 2006 Nuclear engineering studies April 06

  14. Technical Decisions Nuclear engineering studiesApril 06 Target area – RED ZONE 1+ Zone IIIA- Yellow zone 1+ N+ Intensities limitations to few 10 10 pps (variable limitation according to masses) EXISTING EXPTs AREAS

  15. Technical Decisions target in oven Assembly of 1st prototype of tantalum oven Tests and temperature measurements Converter and UCx target

  16. Tasks of the Spiral 2 management For 2006 : • To build project management • To take technical decisions • To share the work packages • To begin the Spiral 2 construction

  17. Work packages sharing CEA /DSM CNRS/IN2P3 STEERING COMMITTEE TAC – SAC National & International Partners Scientific Commu Project Direction GANIL Project management Infrastructure Accélérateur RIB production Other labs

  18. The French Laboratories involved in Spiral 2 Research Construction DSM DAPNIA/SPhNDAPNIA/SACM – SIS - SENAC DAM DASE et DP2I DEN Expertise DPSN Expertise

  19. The French Laboratories involved in Spiral 2 Research and Construction CEN de Bordeaux-Gradignan Centre de Spectroscopie Nucléaire et Spectroscopie de Masse Orsay Institut de Physique Nucléaire Orsay Institut de Recherches Subatomiques Strasbourg Laboratoire de Physique Corpusculaire de Caen Laboratoire de Physique Subatomique et de Cosmologie Grenoble

  20. Accelerator Work packages Injector Superconducting Linac High Energy Beam Transport Cryogenic system RF System Diagnostics

  21. Accelerator Work packages

  22. Accelerator Work packages PROJECT

  23. RIB Work packages ECS Transport faisceaux radioactifs GANIL existant

  24. Accelerator Work packages

  25. Accelerator Work packages

  26. Accelerator Work packages

  27. RIB Work packages ECS Transport faisceaux radioactifs GANIL existant

  28. RIB Work packages Converter Target & Sources Coordination – tunning maintennace Converter U Cx Target Other targets ECR Source Febiad Source Laser Ion Source Surface Ion Source Test station for ECS Intégration ECS tests ECS & Converter environment

  29. RIB Work packages Beam transport Beam lines for RIB Coordination – Procédure exploitation Separator Charge Breeder Multi- charged Beam Lines Tests Bench Identification bench Intégration Diagnostics

  30. RIB Work packages Exist. GANIL experim. area Coordination – Procédure exploitation Cime Cyclotron Beam Lines Diagnostics

  31. For 2006 : • To build project management • To take technical decision • To share the work packages • To begin the Spiral 2 construction • Preparation of safety documents • Realization of sub systems

  32. Intense Ion sources • p,d; HI (mA) Techn. specs for call for tender In progress RFQ tests in Grenoble(Sept. 2005)

  33. Linac Accelerator : SC cavities High beta cavity 0.12 ZANON Tested in Orsay Feb 2005 « Pre serial » fabrication : Order in progress before end of 2006

  34. Linac Accelerator: SC cavities « Pre serial » fabrication Order in on month before end of 2006 Low beta cavity  0.07 -ACCEL Tested in Saclay Nov. 2004