170 likes | 317 Views
Dredging: Methods, Options, and Issues. Presentation to Adirondack Sustainable Communities. By Dave Wick, District Manager Warren County Soil and Water Conservation District. Project Goals. Why dredging? Environmental or Economic benefit? Scale of Project Finances available.
E N D
Dredging: Methods, Options, and Issues Presentation to Adirondack Sustainable Communities By Dave Wick, District Manager Warren County Soil and Water Conservation District
Project Goals • Why dredging? • Environmental or Economic benefit? • Scale of Project • Finances available
Define the Project • What is the material to be dredged? • Dredging technique (mechanical vs. hydraulic) • Who will “own” the project, who will “run” the project • Permitability • Liability
Techniques Mechanical Dredging • Excavators, Trucks, Loaders, Dozers, etc. • 50-70% solids • No large dewatering area required
Techniques Hydraulic Dredging • Augur in front, like a snowblower • 10-20% solids • 80-90% water • Need large dewatering area
Permits • NYS DEC / US Army Corps of Engineers Joint Application for permit • State Environmental Quality Review Act (SEQRA) • Wetlands disturbance permit (APA)
Sediment Sampling • Over 1,500 cubic yards, cost per sample approximately $800 each • Scale of project determines sampling density • NYS DEC determination • Under 1,500 cubic yards, costs greatly reduced
Project Ownership • Who will sign the permit, i.e. own the project? • Project management • Liability coverage • Insurance requirements
Costs • Highly variable, based upon methods, access, equipment availability, etc. • Glen Lake shoreline dredging project was approximately $100,000
Timeframes • Project planning and permitting, approximately one year if all goes well • Actual dredge time dependent upon scale of project