Brochure. R Jermyn 23 September 2008. Brochure. R Jermyn 23 September 2008. Services. Commodity Experience: 10 years Iron Ore (2 years); Mineral Sands (3 years); Diamonds (5 years). Combined production and capital projects experience throughout.

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about 'Brochure' - paul2


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
brochure

Brochure

R Jermyn

23 September 2008

brochure2

Brochure

R Jermyn

23 September 2008

services
Services
  • Commodity Experience: 10 years
    • Iron Ore (2 years); Mineral Sands (3 years); Diamonds (5 years).
    • Combined production and capital projects experience throughout.
  • LIMN Simulation Software: 10 years experience
    • LIMN Agent for Western Australia (software sales and support).
    • LIMN Training: 2 day beginner; advanced training; 1 on 1 coaching.
    • Plant Flowsheets: A0 plant overviews; detailed sectional flowsheets.
    • LIMN simulations: flowsheet option trade offs; constraint studies; de-bottlenecking; scenarios; calibrated against plant performance.
  • Capital Projects:
    • Financial analysis and trade off studies (NPV, IRR, payback etc).
    • Pre-feasibility through to Commissioning, Optimisation and Handover.
  • Natural leadership skills.
  • Problem solving and trouble shooting.
  • Green Belt Six Sigma (Define, Measure, Analyse, Improve, Control).
  • Mentoring of junior process engineers. Lead process engineer on projects.
  • Climate Change: calculation of carbon footprints and implementation of projects to reduce GHG emissions.
the proven method

Step 2:

1. Develop LIMN model

2. Calibrate with plant performance

3. Constraints simulations

4. De-bottlenecking scenarios

Step 4:

1. Finance capital project

2. Detailed design

3. Install, commission, optimise

4. Update flowsheet

Step 3:

1. Scope Of Work for options

2. Capital and Operating Costs for options

3. Revenue, NPV, IRR, payback for options

4. Select desired option

The Proven Method

Step 1:

1. Draw the flowsheet

2. Unit operation information

3. Check material flow

4. Check metallurgical accounting

The Continuos

Improvement

Cycle

slide5

Western Australia

Generic Diamond Plant Flowsheet

Compiled by: R Jermyn

Date: 24 July 2008

slide6

Western Australia

Generic Mineral Sands Plant Flowsheet

Compiled by: R Jermyn

Date: 24 July 2008

slide7

Western Australia

Generic Water Usage Flowsheet

Compiled by: R Jermyn

Date: 24 July 2008

slide8

Western Australia

Generic Hematite Plant Flowsheet

Compiled by: R Jermyn

Date: 24 July 2008