1 / 32

Pavement Type Selection – Updated Guidance on Use of Alternate Bidding

Virginia Concrete Conference Richmond, VA March 6, 2014. Pavement Type Selection – Updated Guidance on Use of Alternate Bidding . Session Outline. Background on FHWA Policy & Guidance Information. Federal Register Oct 8, 1981 PTS Policy

orrin
Download Presentation

Pavement Type Selection – Updated Guidance on Use of Alternate Bidding

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Virginia Concrete Conference Richmond, VA March 6, 2014 Pavement Type Selection – Updated Guidance on Use of Alternate Bidding

  2. Session Outline

  3. Background on FHWA Policy & Guidance Information • Federal Register Oct 8, 1981 PTS Policy • If designs equivalent then alternate bidding permitted • Federal Register Nov 9, 1981 Clarification • Discourages use of price adjustment clauses w/ AB • 23 CFR, Part 626 Non-Regulatory Supplement April 8, 1999 • FHWA does not encourage use of AB for PTS due to issue of equivalent pavement designs

  4. Background on FHWA Policy & Guidance Information • FHWA Memo Nov 13, 2008 • Clarifies & consolidates FHWA policy • AB is not encouraged • Use of commodity price adjustments should not be used • SEP 14 approval needed if using price adjustments • NCHRP Report 703 – Guide for Pavement Type Selection March 2011

  5. PTS Method #1 Identify feasible alternatives Perform LCCA Cost within specified % of lowest estimate Cost within specified % of lowest estimate • Consider subjective factors: • constructability, adjoining pavement, competition, • traffic control, • budget, etc. YES NO Eliminate alternative Make Decision 8 states

  6. PTS Method #2 (MI) Identify feasible alternatives 1 rigid, 1 flexible Perform LCCA Alternate with lowest LCC YES Make selection decision NO Eliminate alternative

  7. PTS Method #3 Identify feasible alternatives Perform LCCA Submit to selection committee. Committee evaluates engineering and economic factors Committee recommends a decision

  8. PTS Method #4 Both rigid and flexible alternatives are feasible Identify feasible alternatives NO YES Perform LCCA Prepare LCC Adjustment factor Eliminatealternative Alternate Bids to determine pavement type 10-25 states

  9. Overview of Pavement Type Selection • Components of Agency Processes • Selection of alternatives • Structural design • Economic Analysis • Primary/Secondary Factors • Contractor-based processes • Alternate Bidding • Design Build • Long Term Warranty • Other ( PPP, Value Engineering, BV Contracting, Contract Maintenance)

  10. State Usage State has advertised at least 1 alternate bid job State has not utilized alternate bidding State did not reply to survey

  11. Technical Advisory • Use of Alternate Bidding for Pavement Type Selection, T 5040.39 December 20, 2012 • Elimination of SEP 14 approval for price adjustments, November 8, 2012

  12. Question 1 Purpose of TA • Guidance on use of AB for PTS on Federal-aid projects on NHS

  13. Question 2 Does TA Supersede other Guidance • TA Supersedes: • Federal Register FHWA PTS Policy Statement 11/9/81 • 23 CFR 626 NR Supplement issued 4/8/99 • HIPT Memorandum issued 11/13/08

  14. Question 3 Background on AB for PTS • Risk associated w/ material costs and performance • 23 CFR 626 NR Guidance did not encourage use of AB • Limited use due to: • lack of national guidance, • consistent approach to AB and • open competitive bidding environment

  15. Question 4 Scope/Applicability of TA • Recommended practice for use on FA projects on NHS

  16. Question 5 FHWA Position • Suitable approach when, • Engineering/economic analysis shows no clear choice between different pavement designs

  17. Question 6 When is AB Appropriate • Equivalent Designs • Similar level of service over same performance period (use of ME Design software) • Similar life-cycle costs • Performance period should include min one major rehab • NPV < 10% of alternative

  18. Question 6 When is AB Appropriate • Discount Rate • Guidance available in LCCA in Pavement Design – Interim Tech Bulletin Sept 1981 • Recommend use of NPV for future costs • Recommend use of Real Discount Rate consistent w/ OMB Circular A-94

  19. Question 6 When is AB Appropriate • Consideration of Uncertainty • Determine total LCC for each alternative • Consider use of RealCost software

  20. Question 6 When is AB Appropriate • Maintenance and Rehab Strategy • Should reflect realistic pavement management practices • Should utilize realistic timing and extent of M&R activities • Provide similar level of service over performance period • NCHRP Report 703 Section 3.5 has reasonable approach http://onlinepubs.trb.org/onlinepubs/nchrp/nchrp_rpt_703.pdf

  21. Question 6 When is AB Appropriate • Non-Economic Factors • Agency may consider, • Constructability • Continuity of adjacent pavements • Availability of local materials • Experience

  22. Question 6 When is AB Appropriate • Appropriate Application • Only use when AB will likely influence determination of lowest bid • Projects w/ substantial quantities of different pavement items not suited for AB

  23. Question 6 When is AB Appropriate • Work Zone User Delay Costs • Not suited when user delay costs for initial construction and M&R exceed 20%

  24. Question 7 Administration of AB • LCCA Bid Adjustment • Should be used for all AB projects • Compute NPV of all unique costs over performance period • Establish process w/ industry input • Include LCCA bid adjustment in project specs • Should not include non-agency costs • User delay costs • Vehicle operating costs • Environmental costs. Etc

  25. Question 7 Administration of AB • Commodity Price Adjustment • Not desirable • Difficult to administer equal treatment • May result in in different levels of material cost risk

  26. Question 7 Administration of AB • Quality Price Adjustments • If used, • Provide similar incentives/disincentives for all alternate pavement types

  27. Question 7 Administration of AB • Material Quantities • Pay items based on weight/mass may result in cost overruns • Recommend agency establish process to monitor costs to prevent any systematic bias

  28. Question 7 Administration of AB • Approvals • Title 23 U.S.C. 112 FA construction contracts awarded based on lowest responsive bid • SEP 14 Innovative Contracting • Evaluated use of alternate pavement type bidding using LCCA bid adjustments • Approval of LCCA bid adjustments no longer required per Nov 8, 2012 memo

  29. Question 7 Administration of AB • Change Orders • Should not allow post-award change order for pavement type

  30. Question 8 Program Effectiveness • Monitor number of bidders and unit cost of projects • Solicit input from respective pavement industry groups

  31. Question 9 Reference Materials • NCHRP Report 703 dated November 2011, Guide for Pavement Type Selection http://onlinepubs.trb.org/onlinepubs/nchrp/nchrp_rpt_703.pdf

  32. Questions • Gary CrawfordPavement Design and Analysis TeamTele: (202) 366-1286E-mail: gary.crawford@dot.gov

More Related