Design Review #1 Autonomous Hovercraft. Mechanical Engineering 8936 Term 8 Design Project February 3, 2012. Agenda. Project Scope Background Simulation Design Considerations Hardware Software Project Management Future Considerations Conclusion. Project Scope.
E N D
Design Review #1Autonomous Hovercraft Mechanical Engineering 8936 Term 8 Design Project February 3, 2012
Agenda • Project Scope • Background • Simulation • Design Considerations • Hardware • Software • Project Management • Future Considerations • Conclusion
Project Scope The scope of this project is to complete research that will lead to the design and construction of an autonomous hovercraft. The hovercraft will have the ability to maneuver a path that will contain multiple obstacles. This hovercraft can then be used to find an object or give video surveillance and return to its initial launch point.
Background of Hovercraft A hovercraft is a vehicle that floats or hovers on a cushion of pressurized air. A hovercraft consists of: • Hull • Skirt • Lift Fan • Propulsion Fan
Design Parameters • α = Hovercraft Angle Heading • β = Hovercraft Angle of Velocity • E = Drive Force • F = Friction Force • T = Yaw Torque • M = Mass • I = Yaw Inertia • K = Dart Effect • J = Yaw Drag • X = Prop Coefficient Relating Ramp up Speed • Y = Prop Coefficient Relating Maximum Torque • Z = Coefficient of Friction
Governing Equations Equations of Motion Drive Equation Yaw Control Translation Control
Simulation • Effects of Variables on Hovercraft Control • Root Locus & Simulink
Design Consideration • Motor Selection Lift Fan Motors Propulsion Motors
Design Consideration • Foam Skirt
Design Consideration • Fabric Skirt
Design Consideration • Rubber Skirt
Hardware • 16F876 PIC • 2200 mAhLiPo Battery (11.1 Volts) to run H Bridges • 9 Volt Battery to run PIC
Hardware • Sharp GP2Y0A02YK0F IR Range Sensor - 20 cm to 150 cm • Maxbotix LV-MaxSonar-EZ0 High Performance Sonar Module • Dual Axis Gyro Breakout Board IXZ500 ±500° / sec • HMC6352 Compass Module
Software • Programming in C, Converted to Hex • Code Will Interpret Sensors to Navigate Path • PID Control Algorithm for Cornering • Potential Issues With Errors in Calculations, Sampling Time
Project Management • Project Schedule • Project Budget • Website
Project Website www.autonomoushovercraft.yolasite.com Please Visit!
Way Forward • More robust prototype • Video surveillance • Determine system parameters for simulation • Integration of PIC board with sensors • Designing lift fan • Purchase new hardware
Conclusion • Project Scope • Background • Simulation • Design Considerations • Hardware • Software • Project Management • Future Considerations