CIRI. Wind Generation in Alaska: A Case Study Update on the Fire Island wind project. Introduction. Fire Island : a case study for commercial-scale wind power development in Alaska: Project description Status update Project hurdles Lessons N ext steps. Project Description.

orinda
Download Presentation

CIRI

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CIRI Wind Generation in Alaska: A Case Study Update on the Fire Island wind project

  2. Introduction • Fire Island: • a case study for commercial-scale wind power development in Alaska: • Project description • Status update • Project hurdles • Lessons • Next steps

  3. Project Description • Utility-scale wind generation development • Project Entity: Wind Energy Alaska, LLC—a 50/50 joint venture between CIRI and enXco • Location: Fire Island • Current Status: Permitting and final design

  4. Project Description • 20 to 36 turbines • 1.5 megawatts per turbine • 30 to 54 megawatt project • 3 mile undersea transmission intertie

  5. Project Description • Turbine facts • GE 1.5 megawatt turbine information • Towers: 264 feet tall • Turbine blades:150 feet long • Rotational speed: 18-21 rpm

  6. Status Update • 8+ years on-site wind and weather data • 5 met towers collecting data • Preliminary engineering and design completed • Project permitting begun

  7. Status Update • Project timeline • 2008-permitting, design & PPAs • 2009-Final permitting, PPAs & construction • 2010-Construction & commissioning

  8. Project Hurdles • VOR—VHF Omni-directional Radio Range • Project impacts: • Reduced number of turbines • Reduced hub height • Upgrade cost

  9. Project Hurdles • Permitting • Army Corps of Engineers 404 permit • ACMP consistency • USF&W

  10. Project Hurdles • Power Purchase Agreements • Railbelt utilities (e.g. CEA, HEA & ML&P) • Up to 4 individual PPAs with utilities • Up to 6 months to negotiate • Crucial project item

  11. Lessons • "Alaska factors” • Project development timeline • Power integration issues (cost & engineering) • Site selection & control

  12. Next Steps • Complete permitting & design • Negotiate & Execute PPAs • Construction

  13. Conclusion • Questions?