1 / 13

Photonic band gap structures made by lithography (top) and fiber-drawing (bottom).

E163: Laser Acceleration at the NLCTA Goal: Demonstrate the technical feasibility of laser-driven particle acceleration. Stanford University Bob Byer (co-PI), Tomas Plettner SLAC

Download Presentation

Photonic band gap structures made by lithography (top) and fiber-drawing (bottom).

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. E163: Laser Acceleration at the NLCTAGoal: Demonstrate the technical feasibility of laser-driven particle acceleration Stanford University Bob Byer (co-PI), Tomas Plettner SLAC Eric Colby(spokesman), Bob Noble (Project Manager), Bob Siemann (co-PI), Jim Spencer, Dieter Walz (UTR & Project Engineer) Ben Cowan, Mehdi Javanmard, Chris Sears (students) Photonic band gap structures made by lithography (top) and fiber-drawing (bottom). Fire Protection Plans, February 3, 2003

  2. E163 Layout E163 Counting Room (b. 225) 225 Moved here Summer 2003 Overhead Cable Tray 7 3 N ORION Extension 2005 LASER ROOM Oct 2003 SHIELDED ENCLOSURE 6 2 May 2003 1 NLCTA 4 Add/change equipment inside NLCTA enclosure:March 2004 RF System 5 Oct 2003

  3. E163 Plan April 2003: Core drill penetrations May 2003: Start assembly of shielded enclosure Summer 2003: Relocate building 225 to NE corner of ESB October 2003: Start construction of laser room, rf system March 2004: Installation of beamline components, commissioning 2005: Start construction of ORION low energy hall 2006: Knock out ceiling, North, and East walls of E163 enclosure and join to ORION low energy hall

  4. Concrete Shielding Enclosure Fire Detection and Alarm System (“Area 2”) Combustible Content: ~200# cabling in trays Occupancy: 0.5-1.0 FTE per year MCFL: ~200k$ MPFL:~50k$ Total value of equipment: ~$500k Structure lifespan: 3 years Start Construction: May 2003

  5. Laser Room Fire Detection and Alarm System (“Area 1”) Combustible Content: ~50# cabling, ~100# books, ~1 liter solvents, 1 rack of electronic equipment Occupancy: 0.5-1.0 FTE per year MCFL: ~400k$ MPFL:~50k$ Total value of equipment: ~$500k Structure lifespan: >10 years Start Construction: Oct 2003

  6. E163 Concrete Enclosure Roof Fire Detection and Alarm System (“Area 3”) Combustible Content: ~200# cabling, 3-4 racks of electronic equipment Occupancy: few days per year total MCFL: ~100k$ MPFL:~25k$ Total value of equipment: ~$100k Structure lifespan: >10 years Start Construction: Oct 2003

  7. NLCTA-Area Fire Detection and Alarm System (“Area 4”) Combustible Content: ~200# cabling Added Occupancy: 0.1 FTE per year MCFL: ~500k$ MPFL:~100k$ Total value of equipment: ~$500k Equipment lifespan: >10 years Start Construction: Mar 2004

  8. RF Power System Area Fire Detection and Alarm System (“Area 5”) Combustible Content: ~100# cabling, ~100# oil, 2-3 racks electronic equipment Occupancy: 0.1 FTE per year MCFL: ~400k$ MPFL:~50k$ Total value of equipment: ~$750k Equipment lifespan: >10 years Start Construction: Oct 2003 NLCTA S 8-pack HVPS Klystron & modulator Extend existing HSSD sampling tube Power to modulator, HVPS, other large supplies disconnected on fire alarm by contactors controlled by FACP

  9. NLCTA Rack-Area Fire Detection and Alarm System (“Area 6”) Combustible Content: ~100# cabling Added Occupancy: few days per year MCFL: ~100k$ MPFL:~25k$ Total value of equipment: ~$100k Equipment lifespan: >10 years Start Construction: Oct 2003 Additional Rack Of Equipment SW corner of ESB

  10. NLCTA Rack-Area Fire Detection and Alarm System (“Area 6”) Combustible Content: ~100# cabling Added Occupancy: few days per year MCFL: ~100k$ MPFL:~25k$ Total value of equipment: ~$100k Equipment lifespan: >10 years Start Construction: Oct 2003 Additional Rack Of Equipment SW corner of ESB

  11. E163 Counting Room (b. 225 Relocated) (“Area 7”) Combustible Content: ~200# cabling Added Occupancy: 1.0-1.5 FTE MCFL: ~500k$ MPFL:~50k$ Total value of equipment: ~$500k Equipment lifespan: >10 years Start Relocation: Summer 2003 B. 225 has sprinklers, which will be reconnected 225

More Related