Tmt status update bonneville second powerhouse behavioral guidance structure bgs
Download
1 / 6

TMT Status Update Bonneville Second Powerhouse Behavioral Guidance Structure (BGS) - PowerPoint PPT Presentation


  • 237 Views
  • Uploaded on

TMT Status Update Bonneville Second Powerhouse Behavioral Guidance Structure (BGS). Technical Management Team Briefing April 9, 2008. Status of BGS. CRFM Funded $3 Million for Construction $1.1 Million for Research Evaluation Installation complete as of 29 March Total overall Length of 720’

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about 'TMT Status Update Bonneville Second Powerhouse Behavioral Guidance Structure (BGS)' - omer


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
Tmt status update bonneville second powerhouse behavioral guidance structure bgs l.jpg

TMT Status UpdateBonneville Second PowerhouseBehavioral Guidance Structure (BGS)

Technical Management Team Briefing

April 9, 2008


Status of bgs l.jpg
Status of BGS

  • CRFM Funded $3 Million for Construction

  • $1.1 Million for Research Evaluation

  • Installation complete as of 29 March

  • Total overall Length of 720’

  • 10’ steel panels create wall effect

  • Intent to increase guidance of Yearling and Subyearing Chinook to B2CC.

  • Historical Guidance Findings

    • 33% Yearling guidance

    • 39% Subyearling guidance



Bgs construction solid panels l.jpg
BGS ConstructionSolid Panels