PIP Update. Nov 7 2012. Agenda. Summary Update Current Activities Updates/Talks: Elmie and Ken: RLS – Updates – Budget Summary. Update. Current Work Booster RF cavity rework RF6 in test stand being tested…..

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about 'PIP Update' - oakes


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
pip update

PIP Update

Nov 7 2012

agenda
Agenda
  • Summary Update
    • Current Activities

Updates/Talks:

Elmie and Ken: RLS – Updates – Budget Summary

update
Update
  • Current Work
    • Booster RF cavity rework RF6 in test stand being tested…..
      • Cavity 1017 was mechanically finished on 10/29. Vacuum pump issues were resolved on 10/31
    • Tuner Work: Three tuners waiting to be assembled once we have cones
      • Building 12 cone assemblies – since none available. Goal is to complete these next week.
    • Cavity 1013 build: (Mike May ), center is scheduled to be in the machine shop before Thanksgiving.
    • SS PA Work: Not much has changed - will have the copper cooling rings for the tube sockets this week (the machine was very busy.)?
      • Water Manifolds are presently being constructed by Larsen MFG in Mundelein, IL. Possibly finished by late next week.
    • SS Install: The modified 'taller' SSD rack was finished and brought over to station 9 in the East Booster Gallery.
    • Modulator Work: First 10 completed/Tested,Next twelve - two are 100% (1/week)
    • LCW: Booster LCW return pump work is complete.
      • Some Booster enclosure LCW work is ongoing; Long 3 hose replacement, EDWA magnet hook-ups, minor leaks, may try to install some more strainers and valves.
      • PreAcc LCW work is ongoing; RFQ and Solenoid magnet LCW is complete, PSQA doublet magnet LCW in progress
    • MCC – moved to lower gallery and is in the process of being connected!!!
    • RFQ: Entire Line Connected, Surveyed and Under vacuum!! Connections/Conditioning
      • Schedule -> Finish Safety Testing this week, Beam permit signoffs next week ….
    • HPower RF : ODDONE had signed the 1.4Mrequisition  Well Not Any More – Put back on Hold (NOVA)
    • Booster Absorber – Blocks Installed, Drawings approved -
    • Linac Modulator –SLAC requisition placed to continue work.
    • Cogging – Software work continues
    • Booster Shielding – Safety did tunnel tour – will have a update end of month

Shutdown - comments (Fernanda, Todd, Mary)

Fiscal Year – There is still some FY12 –> FY13 funding discussions occurring – Today Talk has more information…..

slide4
So far on schedule – or a little ahead but

will like to have extra time for working on sources, efficiency an measurements.

upcoming
Upcoming
  • RLS – Finishing updates
  • Fiscal Year Start –
    • Labor requests – mostly worked out
    • M&S – still depends upon 2nd floor decision but have tasks that ready to go/continue
  • Reports – none at this time
  • Meetings:
    • Roger regular PIP – yesterday
      • Talked about fiscal (labor) concerns for both AD and PIP
    • Meet with Ann again (Nov 14?)
talks
Talks
  • Elmie Peoples / Ken Domann - Project Status Updates