West Melbourne Lease Requirements. CICCC 12 March 2009. Stage 1by 2004 (Complete). New Vapour Emission Control System (Combustor) Upgrade Acrylate Storage Tanks (10 tanks) to have: Under tank liner for leak detection New dock lines and hard piped exchange areas

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about 'West Melbourne Lease Requirements' - nyssa-tillman


Download Now An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
stage 1by 2004 complete
Stage 1by 2004 (Complete)
  • New Vapour Emission Control System (Combustor)
  • Upgrade Acrylate Storage Tanks (10 tanks) to have:
  • Under tank liner for leak detection
  • New dock lines and hard piped exchange areas
  • Sealed truck loading systems and cast steel pumps with double mechanical seals
  • High pressure alarms
stage 2 by 2008
Stage 2 by 2008

50% of flammable/hazardous tanks to have: (60% actually done)

  • Tank renovations including foundations where required (16 tanks)
  • Under tank liner for leak detection (16 tanks)
  • Hard piped exchange areas (all complete)
  • New piping systems, cast steel pumps and sealed truck loading systems (all complete)
  • High pressure alarms (all complete)
stage 3 by 2012
Stage 3 by 2012

Remaining 50% of flammable/hazardous tanks to have:

  • Tank renovations including foundations where required
  • Under tank liner for leak detection
  • Hard piped exchange areas
  • New piping systems, cast steel pumps and sealed truck loading systems
  • High pressure alarms
  • Installation of impermeable liner to tank bunds and bund walls (Plant C done)
plans for 2009
Plans for 2009
  • Tank renovations and under tank liner for leak detection for 3 tanks (1 done already)
  • Install new fill lines to all remaining tanks
  • Remove existing carbon beds and replace with static carbon bed
  • Replace old boilers unmanned system