human services department video conference augmentation project n.
Download
Skip this Video
Download Presentation
Human Services Department Video Conference Augmentation Project

Loading in 2 Seconds...

play fullscreen
1 / 6

Human Services Department Video Conference Augmentation Project - PowerPoint PPT Presentation


  • 93 Views
  • Uploaded on

Human Services Department Video Conference Augmentation Project. Project Closeout Presentation, August 27, 2014. Presenters: William Russell, HSD IT Project Manager Mario Gonzalez, HSD ITD Project Management Bureau Chief

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about 'Human Services Department Video Conference Augmentation Project' - norman-owens


Download Now An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
human services department video conference augmentation project
Human Services DepartmentVideo Conference Augmentation Project

Project Closeout Presentation, August 27, 2014

Presenters:

William Russell, HSD IT Project Manager

Mario Gonzalez, HSD ITD Project Management Bureau Chief

Steven Chavez, HSD ISD Bureau Chief, Program Administrative Services

project overview
Project Overview
  • The purpose of this project was to augment and expand the current HSD video conference network by 22 more offices.
  • The benefit will be automation of the current manual scheduling function, reduced travel cost and travel time to attend meetings, and improved communication between field staff.
  • The expanded equipment was successfully installed, tested and is now in production.
project delays lessons learned
Project Delays / Lessons Learned
  • The project took far too long to complete.
  • Delays commonly tie back to state resource availability and scheduling commitments.
  • Internal resource forecasts need improvements and should receive proper review up front.
  • Staff turnover through the end of 2013 encompassed the entire technical team including the bureau chief.
appropriation certification history
Appropriation & Certification History

Note: All certified funds were used for hardware procurement