Certification Committee July 25, 2007

Student Teacher Accountability Reporting System (STARS) FY 2008 Appropriation Certification Presentation. Certification Committee July 25, 2007. Pre-STARS Background. Prior to STARS, ADS (Accountability Data System) was the State’s educational data and reporting system

nixie
Download Presentation

Certification Committee July 25, 2007

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Student Teacher Accountability Reporting System (STARS)FY 2008 Appropriation Certification Presentation Certification Committee July 25, 2007

  2. Pre-STARS Background • Prior to STARS, ADS (Accountability Data System) was the State’s educational data and reporting system • ADS was originally designed in 1995 and piloted in 1997 • ADS was created to address educational data reporting requirements circa 1995 • Federal and State requirements have significantly evolved, most notably with the 2001 No Child Left Behind (NCLB) Act • Continued maintenance and enhancements to ADS became unacceptably expensive and compromised system integrity and usability • A series of independent audits were conducted on ADS: • 2001: LFC, Audit of Data Used in Accountability Program • 2003: LFC, Audit of Special Education • 2004: LFC, Audit of Bilingual Education Program • 2003-04: ECS, Study on Federal Requirements Compliance • 2004: CCSSO, Accountability & Indicators Report • These audit findings prompted several detailed evaluations: • 2004: CCSSO/DSAD, Case Study of New Mexico • 2004: LFC/LESC/OEA/PED, Joint Needs Assessment

  3. STARS Was Born • Audit and Study efforts resulted in two clear conclusions: • PED needed to develop a system that meets Federal and State laws while addressing the concerns and directives of the Legislature and Audits • PED needed to address district concerns and dissatisfaction in current methods and systems • A multi-year ‘fund as we build’ plan was developed specifically to: • Minimize development and deployment risk through a milestone-based method • Ensure effective and efficient progress • Maintain accountability and transparency to the Legislature and tax payer • Initial funding of $6.6M was appropriated during the 2005 Session • A national search and solicitation for a development partner was conducted • 11 nationally recognized vendors submitted proposals • Selection criteria based on ‘Commercial Off-the-Shelf’ (COTS) solution as well as demonstrated track record with prior projects relevant to NM’s environment • The partner was selected and the initiative began January, 2006

  4. Achievement to Date – First 24 Months • We have exceeded our originally set objectives on time and on budget: • Built and piloted an operational prototype • Implemented uniform student ID methods statewide • Rolled-out the fully operational data warehouse statewide (in less than 8 months from start) • Collected SY 2007 40th, 80th, 12/1 SPED, 120th, and EOY data via STARS • Calculated and Reported SEG, AYP, HQT • Submitted EDEN Special Education data through STARS • We are now actively collecting and reporting student, teacher and salary data in support of: • Federal reporting requirements • NEA reporting requirements • Governor’s Office and Legislative requests • We have accomplished all of these achievements in a manner that respects district autonomy by interfacing with more than 12 different district systems • These achievements have set the foundation for continued success in our next phases of development, implementation and associated funding needs On time, on budgetachievements On time, on budgetachievements

  5. We Have Had Our Bumps Along the Way • We anticipated a higher level of data-reporting proficiency in the districts • We under estimated the amount of communication, outreach and training necessary to support the changes associated with the new STARS system • We under estimated the ‘silo’ affect – both within the districts and PED We have learned from these challenges and are adapting our next phase activities accordingly

  6. Relative Comparisons • Thirteen states started to build an educational data and reporting system when we did: • None of them have made it as far as we have • Only four others have completed what they set out to do • We have been highly effective given some comparative benchmarks: • New York: $500M spent and still not performing to desired functionality • North Carolina: $700M spent and also not performing to desired functionality • Kentucky: $125-$250M spent and also not performing to desired functionality • Idaho: Initial funding of $54M swelled to $180M and terminated the program • New Mexico’s performance is currently the envy of the country: • We are frequently invited to national meetings to present our story • Of particular interest is our: • Approach (high flexibility and decentralization) • Pace of achievement • Cost effectiveness of achievement • STARS Project Manager now sits on a national task force for a term of 3 years

  7. FY 2008 Appropriation In the 2007 legislative session House Bill 2 (2007), Section 7, page 258, line 1, item 32 appropriated $2,500,000 based on the following appropriation. (32) PUBLIC EDUCATION DEPARTMENT: To continue implementation of the student and teacher accountability reporting system. The appropriation is from the appropriation contingency fund dedicated for the purpose of implementing and maintaining educational reforms created in Section 12 of Chapter 114 of Laws 2004. The appropriation is contingent on the public education department reengineering its business processes before proceeding and expending additional funds and on the public education department developing and enforcing reporting compliance. The public education department shall provide monthly status reports to the legislative finance committee and the office of the chief information officer. Based on this appropriation, the funding is contingent upon: • Reengineering its business processes before proceeding and expending funds. • PED has redesigned the following processes: • Data Review - districts are now able to submit and review immediately after submission and prior to the data being available for reporting. Programs are now able to review and audit data prior to developing reports. • Reporting – districts and users are now able to run their own reports instead of having PED push the report to them. Powerful decision support tools are available to users to assist them in their reporting needs. • Program Improvements: HQT is now fully automated; SPED data is electronically created and submitted through EDEN; Error correction for AYP is down from 50,000 errors to 93; AYP results are now available to the benchmark level. • Developing and enforcing reporting compliance • For the first time districts are able to review their data for accuracy prior to reporting. Due to this district submissions took longer this year; 40th approximately 66 days; 80th day approximately 60 days; 120th approximately 60 days; EOY approximately 21 days. • For SY2008 PED will enforce the submission schedule, while providing a defined submission process, monitoring program, and performance metrics to track district submission • Providing monthly status reports to the LFC and OCIO • PED has been, and will continue to, supply status reports and executive briefings to all STARS stakeholders

  8. Next Phase Summary The appropriation will be divided into two parts: 1. License and Hosting Fees This section of the appropriation will be used to pay those fees. Estimated Costs: $900,000. 2. Operational Support Also in the FY2007 Appropriation Cycle NMPED requested operational budget to transfer the four term employees that were designated in HB2 for STARS development into a STARS operational support operational position. This request was also denied. As we continue to work with the districts and PED staff to better utilize STARS, a portion of the remaining appropriation will be used to fund these term position as internal operational support. Additional tools, reports and training is necessary to assist stakeholders in fully optimizing their use of STARS. Support will include: • District/Charter Level Submission Support • District/Charter Level Reports and Cube Development • Design and development of a Proof of Concept for the Statewide Education User Interface to provide PED and districts with the tools to communicate, collaborate, and mange content and data across the state. • Design, develop, and implement STARS security and user provisioning. As STARS is roll-out to more and more users, Access control will be a major component of the STARS security strategy. STARS security and user provisioning will develop and implement a plan to mange the access to confidential student, staff and financial data. • Training will continue to include specific district level training related to how to better access and evaluate the existing aggregated and disaggregated data now available to the districts. Users now have direct access to the student, teacher, financial, and facility data necessary to better evaluate the student progress. Training is required to assist district and school personnel to access and interpret the available data. Estimated Costs: $1,6,00,000

  9. STARS Budget

  10. STARS Operational Support Timeline

  11. Independent Validation & Verification • IV&V Tasks to include: • Periodic review of ‘Project’ • Project Plan and Execution • Issues Identification and Resolution • Risk Identification and Risk Mitigation Strategies • Review of ‘Project’ Deliverables • Assessing Organizational Readiness • Assessing Executive Awareness

  12. Potential / Future Enhancements • Addition of Pre-K and Higher Ed data requirements. • Unique ID for Higher Ed • Develop Unique ID for certified staff. • Continued reduction in district work load • Add data elements such as NMEPLA and Dibbles testing, Nutrition, Transportation, etc. • Provide additional analysis tools such as GIS. • Provide analysis and reporting capabilities to larger audience including School Administrators, teachers and potentially parents.

  13. CCSSO/DSAC Funded Component.

  14. Procurement Process / Plan • Project Management Plan Certified • RFP Released July 2005 • COTS • Vendor ability to implement at district / state of equal or larger than NM • 11 Nationally Recognized Vendors submitted proposals • Selection Process • Evaluation Team Reviewed / Scored Three Finalists in late September 2005 (Deloitte,IBM, and Pearson) • Secretary announced Deloitte, eScholar, COGNOS, and Bency at team awarded the bid

  15. The STARS Project team STARS Proposed Governance / Advisory Team

  16. Our Vision for STARS State of New Mexico • Comply with state reporting requirements • Meet special data needs various state entities and policy-makers Teachers • Assess historical performance of incoming students • Identify peer teachers and resources to meet student needs • Collaborate with peer teachers through professional learning communities Parents • View teacher profiles • Review curriculum • Communicate with teacher • Identify tutoring and enrichment resources Personalized K-12 Database that connects people, data and resources Principals/Administrators • Create improvement plans and communicate to teachers • Assess progress against goals • Adjust strategies and communicate to teachers • Compare performance to peer schools Students • View profile to track progress toward goals • Access research resources US Department of Education • Comply with federal reporting requirements

More Related