natania
Uploaded by
8 SLIDES
205 VIEWS
80LIKES

Software Development Plan for ROGER BACON Project: Overview and Timeline

DESCRIPTION

Welcome to the ROGER BACON project, led by Matt Warner and supported by a dedicated NSG Software Development Team, including developers, a webmaster, and a librarian. This document outlines the project's goals, problem and system definitions, constraints, and planned functions. We will follow a linear sequential method in our development (Classic Waterfall Model) with key scheduling dates for submissions and presentations. Important documents will be submitted on Oct 24 and Nov 28, 2005, with presentations set for Oct 26 and Nov 30, respectively. We welcome any questions and look forward to your input on what's next in this exciting project!

1 / 8

Download Presentation

Software Development Plan for ROGER BACON Project: Overview and Timeline

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript

Playing audio...

  1. Excel Grading Project Welcome Ms. Cotler and Dr. Hunter

  2. Software Plan ROGER BACON 328 SEPTEMBER 21, 2005 • Matt Warner Team Leader • Dan Lomanto Developer

  3. NSG Software DevelopmentTeam Members • Matt Warner Team Leader • Justin Spegele Webmaster • Kristen Dobreski Librarian • Dan Lomanto Developer

  4. System Definition • Problem Definition • Goals • Constraints • Planned Functions

  5. Project Plan • Linear Sequential Method (Classic Waterfall Model)

  6. Development Schedule

  7. Key Scheduling Dates • Software Requirements Specifications • Documents Submitted: October 24, 2005 • Presentation: October 26, 2005 • Preliminary Design • Documents Submitted: November 28, 2005 • Presentation: November 30, 2005

  8. Summary • What’s Next? • Any Questions?